Nunavut Planning and Project Assessment Act (NuPPAA) - Before and After Coming Into Force: July 9, 2015

Notice

This website will change as a result of the dissolution of Indigenous and Northern Affairs Canada, and the creation of Indigenous Services Canada and the eventual creation of Crown-Indigenous Relations and Northern Affairs Canada. During this transformation, you may also wish to consult the updated Indigenous and Northern Affairs home page.

BEFORE
NuPPAA
NuPPAA
IN FORCE NOW
"Single Window" Entry Point
  • Review processes were triggered by various regulatory applications
  • Projects could enter the review system at several different starting points
  • Confusion over processes, including what steps a project had to follow and in what order
Timelines
  • No legislated timelines
  • Legislated time limits for each decision making step in the review process:
    • NPC conformity determination
    • NIRB screening/report
    • NIRB issuing of project certificate
    • Federal panel report
    • Ministerial decisions
  • Proponent time not included
  • Time taken by public/stakeholder input not included
  • Time during which the process is suspended by the boards not included
Definition of a Project
  • Broad definition of "project" captured all physical works and activities
  • More precise definition of "project"
  • Does not include:
    • Projects with minimal environmental impacts
    • Certain municipal projects
    • Emergencies
Enforcement/Inspection
  • Limited enforcement options
Now enforceable:
  • Terms and conditions included in project certificates
    • Terms and conditions included in land use plans
    • NPC conformity decisions
    • NIRB screening decisions
  • Introduction of fines and/or imprisonment for contraventions
    • Maximum fine of $100,000 and/or imprisonment for up to one year
    • If an offence is committed or continues for more than one day, it will be considered a separate offence for each day on which it is committed or continued
  • Minister has authority to designate employees of federal/territorial departments/agencies for inspections
    • Not limited to current enforcement staff
Board Appointments/Quorum
  • Rigid appointment process resulted in occasional difficulties meeting quorum, causing operational challenges, delays in reviews
  • Greater flexibility to extend NPC commissioners’ and NIRB members’ terms in the middle of a proceeding
  • New NPC commissioners and NIRB members appointed for full three-year terms
  • NIRB has authority to create smaller panels (3 or more members) and work on several reviews at the same time
Transboundary Projects
  • Duplication of efforts, multiple reviews had the potential to create delays for transboundary projects
  • Impacts of shipping of goods/persons into/out of territory for large scale projects could trigger the project being classified as transboundary. Transboundary projects were reviewed by a special federally-appointed environmental assessment panel, not the Nunavut Impact Review Board
  • "One project, one assessment"
    • NIRB now has authority to enter into agreements with other environmental assessment panels to conduct a joint review of transboundary projects
  • Shipping of persons or goods does not automatically make a project transboundary
    • NIRB makes final decision
Activities Allowed Prior to Environmental Assessment Decision
  • No legislated control over activities allowed prior to environmental assessment decision
  • Clarification of activities allowed prior to environmental assessment decision including
    • Certain exploration/development activities
    • Nunavut Water Board can issue interim/short term water licences for the use of water or deposit of waste
Emergency
  • No guidelines for emergency situations
  • Federal or territorial minister can declare an emergency
  • Reporting requirements for projects undertaken in response to an emergency
Land Use Plans
  • Government of Canada and Government of Nunavut are the only signatories to accepting/ rejecting a plan and any amendments under the Nunavut Land Claims Agreement
  • Lack of clarity on proponent’s rights if land use plans changed after a conformity decision
  • Designated Inuit Organization has authority to accept/ reject a draft land use plan or a plan amendment
  • One, territory-wide land use plan for the Nunavut Settlement Area, but with flexibility for various planning models
  • Land use plans apply to all lands in the Nunavut Settlement Area, including Inuit Owned Lands
  • Proponents rights preserved after a conformity decision
Other
  • Lack of clarity/consistency, limited detail for some processes
  • Key processes clarified, more detail added including:
    • "Grandfathering" how projects started under the old system will be treated under NuPPAA
    • How significant modifications to projects during an assessment will be addressed
    • Implications of termination/suspension of an assessment
    • Land use planning and assessment process for land administered by Parks Canada