ARCHIVED - Northern Contaminated Sites Program Performance Report 2007-2008

Archived information

This Web page has been archived on the Web. Archived information is provided for reference, research or record keeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

PDF Version   (651 Kb, 31 Pages)

 


Table of Contents





Introduction

Management Statement – ADM Northern Affairs Organization (NAO)

I am proud to present the Northern Contaminated Sites Program's seventh annual Performance Report for the 2007-2008 fiscal year. This report provides a summary of the results achieved by Indian and Northern Affairs Canada, Northern Affairs Organization in the management of contaminated sites in the North, including environmental and socio-economic benefits.

Unlike many other federal contaminated sites that are the result of federal operational activities, INAC's portfolio of contaminated sites in the North originated from private sector resource development and national defence activities on federal Crown lands. These sites date back over half a century, long before the environmental impacts of such activities were adequately understood or managed. INAC has recognized since the late 1980s that the potential for risks to human health and the environment from contaminated sites in the North must be addressed and has directed considerable resources to care and maintenance, environmental site assessment, remediation and monitoring of these sites.

The NCSP is a decentralized program which is implemented in the three territories. Primary front-line responsibility rests in each region, with Headquarters providing program management support and policy direction. The NCSP's reporting strategy is contained within the program's Results-Based Management and Accountability Framework (RMAF). A number of reports are produced each year, designed to meet various federal policy requirements and to monitor implementation progress. The activities of the NCSP are also reported in various departmental reports including the Departmental Report on Plans and Priorities (RPP), Departmental Performance Report, the Strategic Outcomes Plan, and the Sustainable Development Strategy.

The positive results contained in the March 2008 Office of Auditor General (OAG) audit show that the NCSP has progressed in identifying and assessing its contaminated sites. The OAG report also indicated that the NCSP has given high importance and effort to four of its abandoned mines, Colomac, Faro, Giant, and Mount Nansen, and has continued additional care and maintenance and remediation activities to deal with urgent issues at other sites.

The NCSP has implemented many of the recommendations of the independent program review completed in 2006-2007 resulting in significant improvements in the delivery of the program. In addition, the NCSP has increased its efforts in addressing the negative environmental impact of contaminated sites while maximizing the social and economic benefits accrued as a result of this work. In 2007-2008, numerous sites benefited from federal investments and local socio-economic benefits resulting in the employment of over 1,000 employees, many of whom were northern Aboriginal. Over the last year, more than 60 workshops and community consultations were held ensuring that over 1,100 people were able to provide input into the delivery of the NCSP.

I would like to thank our employees and partners for making 2007-2008 a success, and encourage them to persist with their efforts and dedication to managing northern contaminated sites.

I invite you to read this year's Performance Report for a greater understanding of NCSP's activities and progress in 2007-2008. To ensure that we continue to meet the needs of our stakeholders, I also invite you to provide comments and feedback on this report.

Patrick Borbey
Assistant Deputy Minister
Northern Affairs Organization
Indian and Northern Affairs Canada

Report Coverage

This is the seventh annual performance report for Indian and Northern Affairs Canada's (INAC) Northern Contaminated Sites Program (NCSP). INAC's Northern Affairs Organization (NAO) has been managing northern federal contaminated sites under the NCSP since 1991, and the purpose of this report is to present NAO's performance relative to NCSP objectives for the period from April 1, 2007 to March 31, 2008. This report outlines activities related to project and program management, and provides regional reports that highlight site-level case studies as well as regional performance data. A glossary of acronyms is included in Appendix 1. Please see our website for additional information on NCSP activities and for previous annual performance reports. Please note that project sites and information management systems are in various stages of development and there are some limitations with data (i.e. not all sites reporting on all metrics). INAC has attempted to address these limitations and will continue to improve data management in the coming years.

Profile of NAO Northern Contaminated Sites Program

INAC is the custodian of most federal lands in the North, and is committed to managing a number of contaminated properties through its Northern Contaminated Sites Program. Through the NCSP, INAC is responsible for contaminated sites located on reserve lands, on federal lands north of the 60th parallel, and on any other lands under INAC's custodial responsibility. In 2002, the NAO developed a Contaminated Sites Management Policy to ensure that management would proceed in a socially, fiscally, and environmentally responsible manner. Through the implementation of this policy, INAC states that it will "contribute to a safer, healthier, sustainable environment for First Nations, Inuit, and Northerners by striving to preserve and enhance the ecological integrity of the environment". The NCSP strategic objectives that guide the program are:

  1. To meet federal legal obligations;
  2. To require that suspected contaminated sites be assessed in a timely and cost-effective manner;
  3. To provide a risk management based framework for guiding planning and activities;
  4. To remediate all National Classification System (NCS) Class 1 contaminated sites in the North, and Class 1 and 2 contaminated sites on reserve, on a priority basis;
  5. To promote social and economic benefits that may accrue to First Nations, Inuit and Northerners; and
  6. To promote the federal "polluter pay" principle.

The Deputy Minister of INAC and the Assistant Deputy Minister of the NAO are responsible for the NCSP. Three regions – the Yukon, Northwest Territories (NWT), and Nunavut – are primarily responsible for implementing the NCSP. Headquarters (HQ) leads the NCSP strategic planning, policy making, and resource acquisition, and provides support to the regions. Key aspects of the NCSP management and governance structure can be found online.

In the NWT and Nunavut, NAO holds direct responsibilities for care and maintenance, assessment, and remediation of identified and suspected contaminated sites. Within the Yukon, the program's activities are guided by the requirements of the Devolution Transfer Agreement between the federal and Yukon governments and responsibilities for contaminated sites are shared. More information on this agreement   can be found online.

Over 60 INAC staff at HQ and in the regions contributed to the success of the NCSP in 2007-2008, as summarized

Table 1: NCSP Employment, 2007-2008
  Total Employment
Yukon 7.5
NWT 42.5
Nunavut 4.75
HQ 10.5
TOTAL EMPLOYMENT 65.25

NCSP maintains an electronic inventory of contaminated sites that is updated regularly to provide an accurate record of the extent and nature of contaminated sites in the North. As of March 31, 2008, 437 contaminated sites (assessed and suspected) in the North require action, such as assessment, remediation or risk management. Of these 437 sites, 40 are considered "priority sites" [Note 1] (down one from last year) and are the focus of many of NCSP's activities.

CHALLENGES OF MANAGING CONTAMINATED SITES IN THE NORTH

Factors unique to managing contaminated sites in the North, such as those related to climate, access, capacity, risk, and scope, contribute to the significant resources required to run the NCSP. Some challenges unique to the North are listed below, highlighting the need for addressing these sites in a tailor-made approach for northern realities.

Climate Challenges

  • Sensitive ecology, extreme temperatures, and the existence of permafrost soils and groundwater.
  • Shorter operating seasons due to short summers and reliance on winter roads.
  • Increasingly unpredictable northern climate, which affects both the summer season and winter roads and increases weather-related risks (climate change).

Access/Economic Challenges

  • Logistical challenges accessing remote locations - typical mobilization and demobilization costs are in the order of millions of dollars.
  • Extremely high cost of materials, labour and logistics due to the long distances involved and a rapidly changing economy.
  • Equipment often having to be leased or contracted for an entire year even if it is only needed for a few months.

Capacity/Jurisdictional Challenges

  • Difficulty of finding and retaining skilled labour in the North.
  • Limited capacity of northern partners (knowledge, experience and resources) to participate in assessment and remediation activities.
  • Dynamic and evolving jurisdictional landscape (land claim interim measures, Approvals-in-Principle and final agreements that may have overlapping interests; devolution; split surface/subsurface responsibilities).

Risk Challenges

  • Reliance of Northerners on traditional foods in territories where risks to human and environmental health may exist.

Scope Challenges

  • Large scope and scale of some contaminated sites, in particular abandoned mines.
  • Requirement for an ongoing presence at large sites to operate critical systems and monitor conditions and controls.

 

Return to Table of Contents





Northern Contaminated Sites Management

This report presents NCSP's performance in two key areas:

Return to Table of Contents





Project Management

This section provides updates on contaminated sites project management information under NCSP jurisdiction, including:

NCSP Contaminated Sites

There are a number of sites in the NCSP inventory at various stages of activity. A total of 2006 sites exist in the inventory, up from 1828 in 2006-2007. Of these, 1089 or 54% have been assessed and require no action or remediation is done (up from 1020 last year), and 917 sites or 46% require action (up from 808 last year). Figure 2 provides a further breakdown of the sites that require action. Part of the increase in the number of suspected sites is due to the fact that Nunavut reclassified a number of sites in the contaminated sites database in 2007-2008.

Figure 1: Status of Sites in the NCSP Database

Figure 1 shows a diagram of NCSP's site statuses.

Text description for figure 1: Status of Sites in the NCSP Database

This image is a diagram of NCSP's site statuses. It reads:

2006 - the number of sites in the CSP inventory (up from 1828)
1089 - the number of assessed sites that require no action (up from 1020)
917 - the number of sites that still require action (up from 808)
This last box branches to two boxes:
20 - Contingent liabilities (same)
and 897 - assessed or suspected contaminated sites (cs) or physical hazards (ph) (up from 788)
This last box branches to two more boxes:
352 - assessed cs/ph sites (up from 348), and
545 - suspected cs/ph sites (up from 440)
These two boxes branch to one box:
437 - assessed or suspected sites (contaminated sites only)

 

Table 2 illustrates the history of how sites in the NCSP have been classified according to the National Classification System (NCS). There has been an increase of five sites to the NCS list compared to the previous year – one NCS 1 and three NCS 2's in the NWT and one NCS 2 in Nunavut. These five sites were added to the NCS list after they were determined, following the completion of site assessments in 2007-2008, to be contaminated and under INAC's jurisdiction.

Table 2: NCSP Sites in CCME Classifications, 2003-2007
CLASS 2003-04 2004-05 2005-06 2006-07 2007-08
Note: Sites under risk management and monitoring maintain their NCS designation and are included in this table. However, these sites are not as high a priority for the NCSP and are not considered as part of the group of "priority sites" referenced throughout this report.
1 43 44 44 49 50
2 14 19 19 22 26
3 9 5 0 0 0
N 0 0 0 0 0
I 0 0 0 0 0
TOTAL 66 68 63 71 76

Overall Spending

The NCSP budget was $115 million in 2007-2008, 88% of which was supplied by Treasury Board through the Federal Contaminated Sites Action Plan (FCSAP) (see Table 3).

Table 3: Source of Funds, 2004-2008
SOURCE OF FUNDS 2003-2004 2004-2005 2005-2006 2006-2007 2007-2008
*Treasury Board established the Federal Contaminated Sites Action Plan (FCSAP) in 2003-04 to address the significant financial and environmental liabilities associated with federal contaminated sites.  Prior to FCSAP, Treasury Board administered funds through the Federal Contaminated Sites Assessment Initiative (FCSAI).
INAC $22,468,514 $22,000,000 $18,499,924 $18,500,000 $13,510,605
FCSAP* $39,439,200 $45,331,784 $72,073,654 $92,441,194 $101,703,175
TOTAL $61,907,714 $67,331,784 $90,573,575 $110,941,194 $115,213,780

Figure 2 identifies the program's expenditures over the last five years. NCSP spent $89.1 million on contaminated sites in its inventory during the reporting period. [Note 2] Financial resources for 88% of the total expenditures were supplied through FCSAP. Up to 2006-2007, expenditures increased each year as NCSP completed more site assessments and carried out more extensive site remediation work. This trend of increasing expenditures did not carry over into the 2007-2008 fiscal year. Total expenditures in 2007-2008 dropped by 10% ($10.2 million dollars) from 2006-2007.

Figure 2: Contaminated Sites Expenditures, 2004-2008

Figure 2 shows Contaminated Sites Expenditures from 2003 to 2008 for each region.

Text description for figure 2: Contaminated Sites Expenditures, 2004-2008

This image is a bar graph that shows Contaminated Sites Expenditures from 2003 to 2008 for each region:

In 2003-04, NWT had around $28 million, Yukon $19 million, and Nunavut $13 million in expenditures
In 2004-05, NWT had around $30 million, Yukon $21 million, and Nunavut $13 million
In 2005-06, NWT had around $35 million, Yukon $24 million, and Nunavut $20 million
In 2006-07, NWT had around $56 million, Yukon $20 million, and Nunavut $22 million
In 2007-08, NWT had around $47 million, Yukon $23 million, and Nunavut $18 million in expenditures.

 

The Yukon was the only region that experienced an increase in spending compared to the previous year (10% or $2.1 million). Site expenditures in NWT and Nunavut both decreased by 16% in 2007-2008 from 2006-2007. However, NWT accounts for a greater overall reduction ($8.9 million) compared to Nunavut ($3.5 million). Appendix 2 illustrates detailed expenditures by site.

In the NWT, reductions in spending on care and maintenance activities ($6.4 million over the last year) account for the most significant change in expenditures. Reductions in spending on site investigation and assessment in the NWT ($2.2 million) also help to explain the overall reduction in expenditures. A large portion of the total reduction is attributable to changes in expenditures at Colomac. Overall spending at Colomac decreased by 53% from 2006-2007 as a result of a reduced scope of work in 2007-2008 related to remediation plans that still needed to be finalized and challenges in contractor hiring. Future years will see spending increase again as plans and contractors are put in place to finish the project. To a lesser extent, reductions in expenditures also occurred at Giant and Johnson Point, as a result of decreased spending on care and maintenance activities.

In Nunavut, expenditures on site remediation decreased by $4.1 million in 2007-2008 from 2006-2007. This decrease reflects the completion of remediation work at various sites, but also reductions in other activities such as consultations and project management as projects near closure. No expenditures occurred at Resolution Island in 2007-2008 as the site project is complete, and less spending occurred at Ekalugad Fiord and Radio Island, mostly due to reductions in site remediation work.

Increases in expenditures in the Yukon are primarily attributable to greater spending on care and maintenance activities and project management. The greatest increases in expenditures between 2006-2007 and 2007-2008 occurred at Faro and UKHM. Mount Nansen saw large drops in expenditures related to care and maintenance, regulatory approvals and remediation activity. Similarly, Clinton Creek reduced the amount spent on remediation by over $370,000, as the site's risk management strategy is being monitored.

Priority Sites

The INAC Contaminated Sites Management Policy requires program and project managers to follow the Government of Canada's Contaminated Sites Management Working Group's ten-step process to manage and remediate contaminated sites. Preliminary steps involve identifying and assessing sites, and later phases involve developing and implementing risk management plans. As of March 31, 2008, all sites have completed steps one through four. Currently, 10 sites are now proceeding with steps eight to ten. Sixteen sites moved further along in the process this year, and 15 sites remain unchanged. This is an improvement over last year, when only 13 sites moved up in the process. One new site was added to the priority list from the NWT (Sawmill Bay) and four sites were removed because they are either NCS 2 sites or the sites are under a risk management or monitoring program and thus are not considered "priority sites" (El Bonanza, North Inca, Canol Trail and Radio Island).

Five sites dropped in their progress along the ten-step process. Giant Mine in the NWT for example, dropped from step eight to step seven as the McKenzie Valley Licensing Review Board is further reviewing whether the remediation options put forward represent the best approach. Silver Bear has dropped in progress based on an organizational decision to take advantage of the logistically proximity of other sites (El Bonanza, Sawmill Bay and Contact Lake) and treat them as one site in terms of remediation. There has been an aggressive schedule to try and progress these other sites so that they are in-line with Silver Bear's progress, and thus less work was conducted on Silver Bear over the course of the fiscal year. In Nunavut, Padloping Island and Bear Island dropped in progress as a gap analysis determined that the current site assessment data is insufficient to complete a comprehensive remedial action plan and further consultations will be necessary following the additional studies. Following the long term plan review in Nunavut it was determined that it will be economically beneficial to remediate both the FOX A - Bray Island and FOX 1 - Rowley Island sites concurrently. As a result, the FOX A - Bray Island remedial action plan will have to be revised following the assessment of the FOX 1 - Rowley Island site, therefore dropping FOX A - Bray Island's status on the ten-step table.

Site-Level Progress

Seven project management activities take place as sites progress along the ten-step process. These activities include: care and maintenance; regulatory approvals; consultation; site investigation and assessment; site remediation; monitoring; and project management and program administration. This section of the report addresses these activities by highlighting trends in total spending and site-specific expenditures and progress.

Care and Maintenance

Total spending on care and maintenance activities in 2007-2008 was approximately $26.4 million, down 16% from 2006-2007. Spending on care and maintenance decreased in the NWT by $6.4 million and increased in the Yukon by $1.5 million. The increase in the Yukon is largely attributed to Faro Mine, and the large decreases in the NWT are related to Giant, Colomac and Johnson Point, which required less care and maintenance this year. Despite decreases in spending at Giant and Colomac, these sites still account for two of the largest care and maintenance expenditures by site in 2007-2008, along with Faro. Similar to 2006-2007, expenditures at these three sites account for roughly 88% of the total care and maintenance expenditures in 2007-2008. Care and maintenance activities undertaken at Faro, Giant, and Colomac, in 2007-2008 include:

Regulatory Approvals

Total spending on regulatory approvals decreased again this year from $922,572 in 2006-2007 to $600,013 in 2007-2008. Over the last two years, more and more sites have completed significant portions of the regulatory approval process and are moving into later phases of contaminated sites management, such as remediation and monitoring. The most substantial decreases occurred in the Yukon at Faro and Mount Nansen, and to a lesser extent at Bray Island and Radio Island (Nunavut) and Colomac and Port Radium (NWT). Nevertheless, five sites experienced an increase in spending on regulatory approvals. UKHM in the Yukon, and Giant in the NWT experienced the greatest increases ($161,800 and $182,630 respectively); with Roberts Bay in Nunavut, and Discovery and Johnson Point in the NWT experiencing smaller increases. UKHM's regulatory expenses resulted from water licensing and mining land use authorization activities. Giant incurred regulatory approval expenses as a result of developing a Remediation Plan that addresses management and disposal of arsenic trioxide material which it was required to submit in conjunction with its Water Licence renewal application.

Consultation

Consultation expenditures increased from $821,179 in 2006-2007 to $946,676 in 2007-2008 (an increase of 15%). At the regional level, consultation spending increased in the NWT and Yukon but decreased in Nunavut. Many sites in Nunavut that spent money on consultation activities in 2006-2007 did not spend any money on consultation activities in 2007-2008. Small amounts were spent on consultation activities at many new sites (86) currently under investigation in Nunavut. This included working closely with local elders to determine the historical uses for the sites and identify any potential additional sites in proximity to the subject sites. Mount Nansen (Yukon), Colomac and Johnson Point (NWT) experienced the greatest increases in spending on consultation in 2007-2008. Three sites in the NWT that did not have any consultation expenditures in 2006-2007 (North Inca, Indore Hottah, and Jean Marie River) undertook consultations in 2007-2008. Mount Nansen, Colomac, Port Radium, and Johnson Point account for over half (56%) of the total consultation expenditures in 2007-2008. Consultation activities that took place at these sites include:

Site Investigation and Assessment

Site investigation and assessment expenditures decreased 21% to $7.1 million in 2007-2008. A decrease in expenditures was experienced in the NWT, but both the Yukon and Nunavut experienced increases. Despite an overall decrease in expenditures for this activity, 83 more sites were assessed in 2007-2008 than in 2006-2007 (125 sites vs. 42 sites). Most of these assessments were Phase I historical reviews that took place at new sites in Nunavut. Assessment expenditures decreased most significantly at Colomac, Atkinson Point, Port Radium and Discovery in the NWT, and at UKHM in the Yukon. Faro continues to be the site that spends the most on site investigations and assessments, accounting for 40% of the total assessment expenditures in 2007-2008. Several assessment activities took place at Faro in 2007-2008, including: updating the water quality database; monitoring waste rock, seepage and groundwater; and completing supplementary geochemical studies. Bear Island and Clifton Point (Nunavut) and Giant and Tundra (NWT) had the next highest assessment expenditures in 2007-2008.

Site Remediation

After several years of increased spending on site remediation, spending decreased by 14% in 2007-2008 from 2006-2007, which reflects the completion of various remediation tasks at some of the sites. Site remediation was the activity that experienced the greatest change in spending from 2006-2007 (a decrease of $5.6 million), but continues to be the activity that expends the greatest amount of funds. In total, $35.3 million was spent on remediation in 2007-2008. Every region spent less on remediation in 2007-2008 than in 2006-2007. The largest reduction occurred at Colomac, which spent $11.4 million less than in 2006-2007. Smaller, but still substantial reductions occurred at Resolution Island (site is now completely cleaned up), Ekalugad Fiord, Radio Island, and Port Radium (site is 90% complete). Sarcpa Lake, Ekalugad Fiord, Atkinson Point (only demobilization is still required), and Tundra spent the most on remediation in 2007-2008. Remediation activities at these sites included:

Monitoring

Monitoring expenditures increased by $181,567 (12%) in 2007-2008 from 2006-2007, demonstrating a shift in activities at some sites, such as Port Radium, that are completing remediation activities and transitioning into monitoring. The greatest increases in expenditures occurred at Colomac and Port Radium. The majority (75%) of monitoring expenses were incurred in the NWT, most notably at Colomac, Port Radium, Giant, Discovery, and Tundra. Various monitoring activities were undertaken at these sites, including: dust monitoring, water quality monitoring, and confirmatory sampling.

Project Management and Program Administration

Both project management and program administration expenditures increased in 2007-2008, by 14% and 16% respectively. At the regional level, the Yukon spent more on both project management and program administration; Nunavut spent more on project management, but less on administration; and the NWT spent less on project management and more on program administration.

Table 4 lists the number of sites that have undertaken select project management activities over the last five years. The number of sites that conducted site investigations and assessments and consultations in 2007-2008 jumped dramatically from 2006-2007, demonstrating NCSP's progress in assessing new sites in Nunavut. Also in 2007-2008, more sites conducted remediation activities; the same number conducted monitoring activities; and fewer engaged in care and maintenance activities.

Table 4: Activities Undertaken at Sites, 2004-2008
TYPE OF ACTIVITY NUMBER OF SITES
  2003-
2004
2004-
2005
2005-
2006
2006-
2007
2007-
2008
Care and maintenance 6 9 16 13 11
Site investigation and assessment 13 20 30 42 125
Consultation 14 13 18 20 105
Remediation 9 14 19 20 28
Monitoring 22 19 13 13 13

Figure 3 shows the proportion of expenditures associated with each of the project management activities for both 2007-2008 and 2006-2007. [Note 3] As in 2006-2007, the largest proportion of expenditures in 2007-2008 was spent on site remediation. The amount of spending on regulatory approvals, consultations, and monitoring was consistent between the two years, but small increases in spending occurred for project management and program administration and small decreases in spending occurred for care and maintenance, site investigation and assessment, and site remediation in 2007-2008.

Figure 3: Program Expenditures by Activity, 2007-2008 and 2006-2007

Pie chart: Program Expenditures by Activity, 2007-2008.

Text description for pie chart: Program Expenditures by Activity, 2007-2008

This image shows a graphical representation of Program Expenditures by Activity in 2007-08 in a pie graph:

Program Administration was 5% of expenditures, Care & Maintenance 30%, Regulatory Approvals 1%, Consultation 1%, Site Investigation and Assessment 8%, Site Remediation 39%, Monitoring 2%, and Project Management 14%.

 

Pie chart: Program Expenditures by Activity, 2006-2007.

Text description for pie chart: Program Expenditures by Activity, 2006-2007

This image shows a graphical representation of Program Expenditures by Activity in 2006-07 in a pie graph:

Program Administration was 4% of expenditures, Care & Maintenance 31%, Regulatory Approvals 1%, Consultation 1%, Site Investigation and Assessment 9%, Site Remediation 41%, Monitoring 2%, and Project Management 11%.

 

Projected costs for the NCSP in 2008-2009 are expected to be slightly more than $101 million (see Figure 4). The majority of these expenditures will continue to be on site remediation; however, a smaller proportion of the total is allocated to remediation in 2008-2009 than was in 2007-2008. Correspondingly, the budget allocated to the other activities in 2008-2009 (with the exception of program administration which remains the same) has increased from 2007-2008.

Figure 4: Budget Forecast by Activity for 2008-2009

Text description of the figure 4: Budget Forecast by Activity for 2008-2009

This image shows a graphical representation of Budget Forecast by Activity for 2008-2009 in a pie graph:

Program Administration will be 5% of expenditures, Care & Maintenance 27%, Regulatory Approvals 3%, Consultation 3%, Site Investigation and Assessment 9%, Site Remediation 39%, Monitoring 3%, and Project Management 11%.

 

Contaminated Sites Liability

Liability: obligations arising from past transactions or events, the settlement of which may result in the transfer or use of assets, or the provision of services or other economic benefits in the future.

Contingent liability: an existing condition or situation involving uncertainty as to possible gain or loss to an organization that will ultimately be resolved when one or more future events occur or fail to occur. Resolution of the uncertainty may confirm the acquisition of an asset or the reduction of a liability or the loss or impairment of an asset or the incurrence of a liability.

Source: INAC Contaminated Sites Management Policy

INAC is responsible for ensuring that all potential and known costs related to the management and remediation of contaminated sites – also known as a site's liability – are accounted for and reported in accordance with Treasury Board policy/guidelines, available online.

The NCSP maintains up-to-date liability estimates for contaminated sites, which are based on engineering and site inspection reports. Estimates are either substantive or indicative, the former being more reliable and of higher quality. As of March 31, 2008, 22 project liability estimates (of the 76 NCS classified sites) were substantive, compared to 20 substantive liability estimates in 2006-2007, and 19 in 2005-2006.

Liability estimates tend to increase as a result of rising operating costs in the North, in addition to the completion of detailed assessments that provide more accurate information on a site's conditions. Liability estimates most often decrease as remediation work is implemented and completed.

In 2007-2008, overall liability estimates increased approximately 13% from 2006-2007 resulting in a total of about $1.4 billion. Nearly 75% of the total liability is accounted for by three major sites: Faro in the Yukon and Giant Mine and Colomac in the NWT. Figure 5 illustrates the liability values from the past five years, for all sites and for all sites excluding these three major sites.

Figure 5: Trends in Liability, 2004-2008

Figure 5 shows a graph of the trends in liability from 2004 to 2008.

Text description of the figure 5: Trends in Liability, 2004-2008

This image shows a line graph of the trends in liability from 2004 to 2008.

For all sites, liability started out around $800 million in 2004, and gradually increased to around $1.4 billion in 2008.

For all sites excluding the major sites of Faro, Giant and Colomac, the liability started around $300 million in 2004 and only very gradually increased to around $375 million in 2008.

 

Regional liabilities from 2006-2007 to 2007-2008 decreased in the Yukon (-2%), and increased in both the NWT (29%), and Nunavut (18%). The decrease in liability estimates in the Yukon is largely attributable to Clinton Creek, for which the liability estimate dropped by 95% due to the completion of over $400,000 of remediation work in 2006-2007. Liability estimates also decreased at UKHM (-9%) since many of the risks identified onsite were dealt with in 2007. Liability at Faro accounts for 86% of the total liability in the Yukon, and has remained fairly consistent since 2006-2007.

Increased liability estimates at Giant, Colomac, and Silver Bear Mines account for a significant portion of the increase in total liability in the NWT. Liability at Giant increased 39% over 2006-2007, which reflects additional costs related to the probable length of the anticipated Environmental Assessment, additional years of care and maintenance, and updated estimates of the Remediation Plan components. Liability at Colomac also increased 39% and liability at Silver Bear Mines increased slightly more than 62% over 2006-2007, both as a result of new contamination discovered at the sites. Together, Giant, Colomac, Silver Bear Mines, and Tundra (which represents a significant liability even though the estimate did not increase significantly) account for nearly 90% of the liability in the NWT. NWT sites experiencing a decrease in liability estimates include Port Radium, Atkinson Point, and Axe Point due to the successful implementation of remediation plans.

In Nunavut, the liability associated with Radio Island is now zero since site remediation is complete. Liability estimates at Sarcpa Lake decreased 81% due to the completion of some remediation activities. To a lesser extent, liability estimates decreased at Bray Island and Ekalugad Fiord by 43% and 11%, respectively. Due to better information and more reliable data, liabilities associated with other sites have increased such as Hat Island (314%), Bear Island (202%), Roberts Bay (66%), Akpatok Island (40%), and Simpson Lake (35%), and liability has been estimated for one new site, Cape Dorset 2 (Nottingham Island).

Table 5 lists the top two sites by region with the most significant changes in liability estimates between 2006-2007 and 2007-2008. Table 6 identifies liability estimates by region for the past five years, regional proportions of the total liability estimate for 2007-2008, and the total percent change of each region's liability estimates from 2003 to 2008.

Table 5 : Sites with the Most Significant Changes in Liability Estimates, 2007-2008
  Increasing Liability Estimates Decreasing Liability Estimates
Yukon Mount Nansen (42%) Clinton Creek (-95%)
Faro (1%) UKHM (-9%)
NWT Bullmoose (1425%) Axe Point (-93%)
Hidden Lake Mine (295%) Atkinson Point (-84%)
Nunavut Hat Island (314%) Radio Island (-100%)
Bear Island (202%) Sarcpa Lake (-81%)

 

Table 6: Liability by Region, 2003-2008
REGION  
  TOTAL LIABILITY REGIONAL PROPORTION % CHANGE
  2003-2004 2004-2005 2005-2006 2006-2007 2007-2008 2007-2008 2003-2008
Yukon $323,386,000 $322,407,675 $386,520,128 $621,644,970 $611,707,916 44% 89%
NWT $321,720,643 $431,822,348 $461,698,801 $482,079,746 $623,537,014 45% 94%
Nunavut $158,840,110 $159,976,145 $148,876,718 $139,314,007 $163,866,827 12% 3%
TOTAL $803,946,753 $914,206,168 $997,095,647 $1,243,038,723 $1,399,111,757 100% 74%

Social, Economic and Environmental Performance

The NCSP is committed to protecting human and environmental health through managing and remediating contaminated sites in the north, but also to promoting social and economic opportunities in the north by engaging First Nations, Inuit and Northerners in the management and remediation process. The NCSP has been improving its reporting process to systematically collect social, economic and environmental performance data from sites under its management. These data are presented below.

Environment, Health and Safety

As stated in the NCSP's Environment, Health and Safety Policy, health and safety of employees and protection of the environment are top priorities. NCSP management is committed to doing everything possible to prevent injuries and to maintain a healthy environment. Most northern contaminated sites are remote and exist on fragile Arctic landscapes, making safety incidents more challenging to deal with and exposure to things such as wildlife and severe weather more likely. A summary of 2007-2008 NCSP EH&S performance is discussed below including: safety performance; incidents, inspections and audits; and training. Overall, fewer lost-time accidents, more inspections, and a greater number of employee training hours were reported in 2007-2008 than in 2006-2007.

Safety Performance

Many sites did not report any lost-time accidents in 2007-2008. In total, eight lost-time accidents were reported in 2007-2008, all of which occurred at two sites. The number of accidents reported in 2007-2008 was roughly half of the number of accidents reported in the previous year. However the time lost due to the accidents in 2007-2008 was approximately double the time lost in the previous year. In addition, 84 near misses were reported at seven sites. About 80% of the near misses occurred at two sites.

Table 7: Safety Performance, 2006-2007 and 2007-2008
Safety   2006-2007 2007-2008
Lost-time accidents (LTA) Number 19 8
Time lost (person-h) 331 672
Near misses Number 82 84
Number of Sites Reporting Data by Year 23 of 30 28 of 29
Incidents, Inspections and Audits

As in 2006-2007, five significant environmental incidents were reported in 2007-2008. The incidents that occurred were: three fuel spills (50 L, 300 L, and 757 L); one fire; and one fall into a tank. Other minor incidents that were mentioned by sites, but that were not included as "reportable" incidents, were small fuel spills (4) and wildlife encounters resulting in bear kills (2).

Seventy-seven inspections were completed at ten different sites in 2007-2008, resulting in 20 non-compliances at five of those sites. Inspections were carried out by various agencies including: INAC, Public Works and Government Services Canada (PWGSC), Workers' Compensation Board (WCB), Environment Canada and other regulators. Half of the non-compliances identified were accounted for by one site. Further, ten audits, including EH&S and internal audits, were conducted at five sites, resulting in ten non-compliances at one site. Many non-compliance issues were simply suggestions for improvement, all of which, or most of which were addressed by the sites. Seven non-compliance issues are still outstanding. These pertain to a winter road, cylinder storage, smoking, Material Safety Data Sheets (MSDS) (x2), a non-functional emergency light, and Human Resources and Skills Development Canada direction to INAC and PWGSC regarding the fall into a tank.

Table 8: Incident, Inspections and Audits, 2006-2007 and 2007-2008
Incidents, Inspections and Audits   2006-
2007
2007-
2008
* Violation notices by regulatory agencies
Significant environmental incidents Number 5 5
Volume spilled or released (L) 1,442 1112
Outstanding compliance issues * Number 0 7
Inspections Number performed 29 77
Number of non-compliances 1 20
Audits Number performed 9 10
Number of non-compliances 20 10
Number of Sites Reporting Data by Year 23 of 30 29 of 29
Workforce Training

Fifteen sites reported providing training to roughly 1,460 employees in 2007-2008, which is over two times the number of employees that were reportedly trained in 2006-2007. Of the 1,460 people that were trained in 2007-2008, 73% were northerners and 26% were northern Aboriginal people. Two-thirds of all of the employees trained in 2007-2008 were trained at Giant. One training initiative that Giant undertook was mine rescue training, which included mine safety and scaling techniques.

Table 9: Workforce Training, 2006-2007 and 2007-2008
Workforce Training   2006-
2007
2007-
2008
Total training Number of persons 414 1,359
Duration (h) 9,242 27,382
Northern training Number of persons 332 989
Duration (h) 8,292 25,340
Northern Aboriginal training Number of persons 271 355
Duration (h) 4,219 23,968
Number of Sites Reporting Data by Year 26 of 30 27 of 29

In total, 7,278 hours of training were reported at sites in 2007-2008, up from 5,689 hours reported in 2006-2007. This change could reflect either an increase in the number of training hours held at sites between the years, possibly due to the greater number of sites undergoing remediation in 2007-2008 (28) than in 2006-2007 (20); or improved data collection and reporting by the sites from year-to-year.

As in 2006-2007, EH&S policy and procedure training was the most commonly reported training in 2007-2008: 14 sites reported 1,478 hours of training. However, more training hours (3,360 hours) were reported under the "other" category. The bulk of the training reported in the "other" category is attributable to scaling, mine rescue, site orientation, asbestos removal, and arsenic removal training that occurred at Giant mine. First aid training also accounted for a large portion of the total training that occurred in 2007-2008. Eleven sites reported conducting 1,171 hours of first aid training.

The number of hours of training reported for HAZWOPER, WHMIS, wildlife safety, and water safety substantially decreased in 2007-2008 from 2006-2007. In some cases, decreases may be due to the ways in which sites deliver training, and consequently report it. For example, one site included wildlife and water safety training in its Worker Orientation Session, thus counting this training as awareness training. Increases in the total number of hours of training occurred for both environmental training and other corrective actions.

Table 10: EH&S Training, 2006-2007 and 2007-2008
EH&S Training   2006-
2007
2007-
2008
Awareness training EH&S policy and procedures (person-h) 619 1478
H&S training HAZWOPER (person-h) 1,000 320
WHMIS (person-h) 444 37
First Aid (person-h) 930 1171
Wildlife safety (person-h) 599 161
Water safety (person-h) 686 29
Fire response (person-h) 182 151
Other (person-h) 775 3360
Environmental training Spills response (person-h) 127 137
Other (person-h) 316 407
Other corrective actions New procedures 13 17
Other initiatives 0 12
Number of Sites Reporting Data by Year 23 of 30 29 of 29

Socio-Economic Performance

The NCSP strives to create positive social and economic impacts for people in the North as program activities are carried out. Benefits can include direct employment, support to local businesses through the procurement of goods and services, and training programs that develop local capacity and build skills. A summary of 2007-2008 socio-economic performance measures is discussed below including: employment; workforce training; and the purchase of goods and services from northern and northern Aboriginal businesses. Overall, a greater percentage of employees were northern Aboriginal, more employees received training, and a greater number of northern suppliers were hired in 2007-2008 than in 2006-2007.

Employment

In 2007-2008, total reported employment by NCSP sites was 1,027 people, down 28 people from the previous year. However, the number of Northerners and Aboriginal people employed in 2007-2008 increased from 2006-2007; 73% of employees were from the North, and 49% of employees were Aboriginal.

Table 11: Employment, 2006-2007 and 2007-2008
Employment   2006-
2007
2007-
2008
* Aboriginal represents First Nation, Inuit, and Métis
Total employment Number 1,055   1,027  
person-d 73,317   32,425  
Northern employment (includes Aboriginal) Number 691 65% 754 73%
person-d 61,721   27,884  
Northern Aboriginal employment Number 441 42% 506 49%
person-d 41,495   17,405  
Southern Aboriginal employment Number 4 0.4% 0 0%
person-d 165   0  
Number of Sites Reporting Data by Year 26 of 30   27 of 29  
Purchase of Goods and Services

Twenty-eight sites reported doing business with a total of 929 northern suppliers in 2007-2008, of which 187 were northern Aboriginal suppliers. The total value of business with northern suppliers was roughly $25 million, 53% of which was from northern Aboriginal suppliers. Three sites in the NWT (Giant, Tundra, and Port Radium) held contracts with roughly half of the northern suppliers. Faro, UKHM, Sarcpa Lake, Port Radium, and Atkinson Point purchased 62% of the total goods and services from northern suppliers.

Table 12: Purchase of Goods and Services, 2006-2007 and 2007-2008
Purchase of Goods and Services   2006-
2007
2007-
2008
Northern suppliers (includes Aboriginal) Number 689   929  
Value ($) $42,344,739   $24,849,029  
Northern Aboriginal suppliers Number 198 29% 187 20%
Value ($) $26,684,363 63% $13,204,005 53%
Number of Sites Reporting Data by Year 26 of 30   28 of 29  

Stakeholder Consultation

The NCSP promotes First Nation, Inuit and Northerner participation throughout all stages of the remediation processes, including:

In 2007-2008, 62 community tours and meetings were held at 19 sites. Eighteen more tours and meetings were held in 2007-2008 than in 2006-2007, and roughly 2.5 times as many people participated in community meetings and tours in 2007-2008 than in the previous year. Port Radium held the greatest number of tours and meetings (12 events), and attracted the largest number of people to its events (272 people). To maintain on-going consultation efforts at Atkinson Point, a part-time community liaison was hired in Tuktoyaktuk to listen to community members' concerns.

Twenty-three site tours were conducted at 15 sites in 2007-2008. Although the number of site tours conducted in 2007-2008 (23) was less than the number conducted in 2006-2007 (31), approximately the same number of visitors toured the sites in both years.

Table 13: Consultation Performance Measures, 2006-2007 and 2007-2008
Consultation Performance Measures   2006-
2007
2007-
2008
Consultation Performance Measures Number 44 62
Audience (number of persons) 453 1146
Workshops Number 6 2
Audience (number of persons) 63 29
Site tours Number 31 23
Visitors (number of persons) 225 227
Media (TV, radio) events Number 28 14
Press reports Number 15 12
Number of Sites Reporting Data by Year 21 of 30 29 of 29
Regional Reports
Northwest Territories
NWT KEY PERFORMANCE MEASURES 2005-2006 2006-2007 2007-2008
Financial
Total Liability $ $461,698,801 $482,079,746 $623,537,014
Contingency Liability $ $41,996,767 $41,808,749 $90,521,751
Expenditures $ $35,563,781 $55,105,427 $46,155,769
Classifications
NCS 1 # 15 20 22
NCS 2 # 10 10 13
Risk Management / Monitoring # 3 3 4
Contingent Liabilities # 15 15 13
Environment, Health & Safety
Safety
Lost-time Accidents (LTAs) total 1 10  
LTA Time Lost (person - h) person-h 15 75  
Incidents, Inspections and Audits
Inspections  # performed 5 16 74
non-compliances 22 15
Audits  # performed 2 7 8
non-compliances 20 20  
EHS Training
Awareness Training (EHS Policy & Procedures) person-h 240 299 1180
HAZWOPER person-h   400  
WHMIS person-h   335 10
First Aid person-h 262 604 538
Wildlife Safety person-h 162 546 129
Water Safety person-h   648 15
Fire Response person-h   133 100.5
Socio-Economic
Employment
Total Employment # 147 710 687
  # person-d 18,662 35,989 16,778
Northern Employment (includes Aboriginal) # 92 382 451
  # person-d 14,175 25,689 13,831
Northern Aboriginal Employment # 40 216 295
  # person-d 9,941 14,964 10,543
Southern Aboriginal Employment # 2  
  # person-d 215 88  
Workforce Training
Total Training # persons 26 126 1,196
  Duration (h) 644 3,265 25,676
Northern Training # persons 17 112 868
  Duration (h) 286 2,957 23,851
Northern Aboriginal Training # persons 16 86 868
  Duration (h) 7,351 2,041 22,715
Purchase of Goods and Services
Northern Suppliers (includes Aboriginal) # 84 459 700
  $ $17,541,773 $32,483,506 11,713,446
Northern Aboriginal Suppliers # 26 79 83
  $ $14,702,548 $21,518,720 8,068,257
Consultation
Community tours and meeting # 23 32 50
  Audience (#) 189 288 918
Workshops # 5 5 2
  Audience (#) 354 63 29
Site Tours # 16 26 17
  Audience (#) 129 177 209

 

BAR D - ATKINSON POINT

BAR-D Atkinson Point is located in the Western Arctic on the coast of the Beaufort Sea. Originally reserved and developed as an Intermediate DEW Line site between 1956 and 1965, subsequent uses of this site included constructing military radar and support facilities, conducting scientific research, and managing a local caribou herd.

Health & Safety and Environmental Concerns

The risks associated with the site were driven by the presence of polychlorinated biphenyls (PCBs) and PCB contaminated soil. An ecological risk assessment demonstrated that there was some risk to the environment, as some contaminants were being taken up by vegetation and migratory birds were using this area for nesting. Human health risks were considered to be low based on assumptions that exposure was minimal.

Remediation

Major site remediation work is now complete at Atkinson Point. In the summer of 2007-2008 various remediation tasks were completed, such as the excavation and on-site remediation of hydrocarbon- contaminated soils by alluing (a process that involves aeration of soils through the use of a special excavator bucket), the collection and containerization of hazardous wastes, and the demobilization of the winter road. The final steps of the site remediation – demobilization and waste disposal – will be completed by October 2008.

Social, Economic and Environmental Highlights

INAC has provided regular updates to and engaged in extensive discussions with the Inuvialuit Regional Corporation during the project's life cycle. Further, they hired a part-time community liaison in Tuktoyaktuk to ensure there is someone in the community who people can talk to about their concerns. While developing the Remedial Action Plan in 2006-2007, a meeting was held to inform people about remediation options and to address any concerns. The remediation contract was awarded to a 100% Inuvialuit-owned company based in Tuktoyaktuk, who maintained employment and supplier objectives of 85% and 95% Inuvialuit content, respectively, for the duration of the contract.

Future Plans

Following final remediation and demobilization, a maximum of two annual site inspections will be required to ensure the remediation objectives are met. Post-remediation monitoring and inspection will likely be required for a few years to ensure the stability of contaminated soil excavations and borrow areas (sites where material is removed for use as fill elsewhere). Existing landfills and dumps were mostly removed, so long-term monitoring is not likely required.

 

COLOMAC

Colomac mine is located 220 km north of Yellowknife and 45 km west of the community of Wek'weeti. INAC assumed responsibility for Colomac, a former gold mine, in 1999.

Health & Safety and Environmental Concerns

Numerous human health and safety, and environmental risks exist at Colomac due to chemical and physical hazards. Chemical hazards include contaminated tailings, hydrocarbon spills, and hazardous materials within the mill complex. Physical hazards are associated with open pits, quarries, waste rock piles, buildings, and other infrastructure.

Remediation

INAC submitted a Remediation Plan to the Mackenzie Valley Land and Water Board in March 2004, and a new Land Use Permit and Water Licence were received in February 2005, granting INAC permission to implement the Remediation Plan. The project is currently in the remediation phase. Some remediation efforts that are currently underway include: hydrocarbon-impacted soil remediation, free product recovery, hydrocarbon-impacted water treatment, waste consolidation and non-hazardous landfill capping, quarry remediation, and waste rock berm and caribou ramp construction.

Social, Economic and Environmental Highlights

INAC continues to work closely with the Tli Cho people and government. Northern businesses continue to benefit from this project, and ongoing training and capacity development are provided. The Tli Cho have participated in an apprenticeship program, science camp, and summer student placement.

Future Plans

In 2009-2010, a Closeout Plan will be developed based on INAC guidelines and sign-off will be sought from the Tli Cho Government. Long-term monitoring will commence after project closure which is expected to occur in March 2011.

 

Yukon
YUKON KEY PERFORMANCE MEASURES 2005-2006 2006-2007 2007-2008
Financial
Total Liability $ $386,520,128 $621,644,970 $611,707,916
Contingency Liability $ $580,440,157 $468,640,871 $525,052,174
Expenditures $ $23,632,934 $20,156,992 $22,228,154
Classifications
NCS 1 # 8 8 8
NCS 2 # 1 1 1
Risk Management / Monitoring # 4 4 4
Contingent Liabilities # 1 1 1
Environment, Health & Safety
Safety
Lost-time Accidents (LTAs) total   3 4
LTA Time Lost (person - h) person-h   170 600
Incidents, Inspections and Audits
Inspections  # performed 4 3  
non-compliances      
Audits  # performed   1  
non-compliances      
EHS Training
Awareness Training (EHS Policy & Procedures) person-h   104 118
HAZWOPER person-h      
WHMIS person-h      
First Aid person-h     400
Wildlife Safety person-h     6
Water Safety person-h      
Fire Response person-h     20
Socio-Economic
Employment
Total Employment # 124 116 125
  # person-d 1,038 10,936 9,377
Northern Employment (includes Aboriginal) # 124 119 125
  # person-d 1,038 11,176 9,377
Northern Aboriginal Employment # 40 37 35
  # person-d   2,815 2,308
Southern Aboriginal Employment #      
  # person-d      
Workforce Training
Total Training # persons 5 54 31
  duration (h)   3,546 628
Northern Training # persons 3 44 30
  duration (h)   3,411 436
Northern Aboriginal Training # persons 4 10 1
  duration (h)   258 192
Purchase of Goods and Services
Northern Suppliers (includes Aboriginal) # 20 55 87
  $ $11,803,000 $5,929,337 8,344,982
Northern Aboriginal Suppliers # 2 7 9
  $ $1,260,000 $1,558,150 1,234,076
Consultation
Community tours and meeting # 33 6 3
  Audience (#)     23
Workshops #   1  
  Audience (#)      
Site Tours # 2 2 3
  Audience (#)   18 9

 

FARO

Faro mine is located in south-central Yukon, 22 km north of the Town of Faro and almost 200 km northeast of Whitehorse. Faro was an open-pit lead-zinc mine that began production in 1969 and went into interim receivership in 1998.

Health & Safety and Environmental Concerns

Large amounts of waste rock and tailings remain at the Faro Mine site that could potentially impact aquatic and terrestrial ecosystems. Waste rock and tailings generate acid and release metals that could contaminate water supplies for human and aquatic populations. Creation and transportation of contaminated dust particles could also affect terrestrial species. Minimizing acid and metal generation, treating contaminated water, maintaining and upgrading infrastructure, and covering and moving dust sources will be key features of a closure and remediation plan at Faro.

Remediation

In 2001, funding was provided by DIAND to develop a Comprehensive Risk Assessment for the Faro mine that would guide prioritization and management of environmental issues at the site. The risk assessment process has helped identify priorities for both care and maintenance activities and investigations, and has acted as a useful tool for communicating priorities to mine site management and the government. The risk assessment process is dynamic and is re-evaluated and modified on an annual basis. INAC administers a detailed risk register for Faro that includes over 110 risk items.

All approved site remediation projects planned for 2007-2008 were completed, the largest of which was the continuation of the scrap steel recovery program and the removal of over 400,000 kg of scrap steel from the mine site.

Social, Economic and Environmental Highlights

In 2006-2007 an Independent Peer Review Panel (IPRP) was established to identify information gaps and assess the engineering adequacy of reclamation alternatives pertaining to the impending mine closure. The IPRP concluded that the technical studies and the range of alternatives provided enough information to move forward with the development of a closure and remediation plan. In 2007-2008 the IPRP completed a comprehensive technical review of closure alternatives. Outputs of the review were used to further refine the suite of closure approaches and informed the set of six closure options that were taken into formal government and community assessment processes. A final technical review of the recommended closure plan is expected to occur in the first quarter of the 2008-2009 fiscal year.

Future Plans

The development of the closure and remediation plan is on track and is expected to be completed and ready for regulatory approval in fiscal year 2008/09.

 

CLINTON CREEK

Clinton Creek mine is an abandoned asbestos mine, located approximately 100 km northwest of Dawson City. Clinton Creek operated from 1968 to 1978, and approximately 12 million tonnes of serpentine ore were extracted from three open pits.

Health & Safety and Environmental Concerns

When the mine was operating, over 60 million tonnes of waste rock were deposited over the south slope of the Clinton Creek valley, and approximately 10 million tonnes of tailings were deposited along the west side of Wolverine Creek. The Clinton Creek waste rock dump failed in 1974, and a slide blocked the valley and the creek, creating an impoundment referred to as Hudgeon Lake. Currently, the primary environmental concern is that Hudgeon Lake could breach the waste rock slide, resulting in sudden and significant downstream flooding, as well as the possible release of hydrogen sulphide created at the bottom of the lake.

Remediation

A detailed risk assessment of this site was initially conducted in March 2005, and has been updated every fall since. Updates reflect changes due largely to remedial or risk management activities. Since November 2006 several high risks were mitigated and moved to a lower category, and these changes were updated in the most recent risk assessment in November 2007. For example, the likelihood and severity of adverse impacts to the environment from contaminant release and waste rock erosion have been reduced through channel stabilization measures. Further, risk of uncertain tenure was alleviated in late 2006 when the Government of Yukon seized control of the site.

Re-vegetation of the waste rock pile was planned for 2007-2008; however, this task could not be completed because grasses were unable to grow on the waste rock piles. No other site remediation was planned for the 2007-2008 fiscal year.

Social, Economic and Environmental Highlights

In 2007-2008, 10 people were employed at the site, all of whom were Northerners, and four of whom were Aboriginal.

Future Plans

Remedial work has progressed as needed, but a final closure plan will depend on the extent of the remaining channel stabilization work, potential adverse impacts of moving tailings, and the need for restoring fisheries habitat. To develop options for addressing these issues, a final closures alternative document will be prepared in 2008. The document will serve as a discussion piece for all governments and stakeholders, and the preferred alternatives will be incorporated into a closure strategy that will be in place by the end of 2008.

 

Nunavut
NUNAVUT KEY PERFORMANCE MEASURES 2005-2006 2006-2007 2007-2008
Financial
Total Liability $ $148,876,718 $139,314,007 $163,866,827
Contingency Liability $   $55,500 $3,006,249
Expenditures $ $19,613,301 $21,703,310 $18,175,977
Classifications
NCS 1 # 21 21 20
NCS 2 # 8 11 12
Risk Management / Monitoring # 2 3 3
Contingent Liabilities #   4 6
Environment, Health & Safety
Safety
Lost-time Accidents (LTAs) total   6 4
LTA Time Lost (person - h) person-h   86 72
Incidents, Inspections and Audits
Inspections  # performed   10 3
non-compliances     5
Audits  # performed   1 2
non-compliances     10
EHS Training
Awareness Training (EHS Policy & Procedures) person-h 120 216 180
HAZWOPER person-h 440 600 320
WHMIS person-h 120 109 27
First Aid person-h 120 326 233
Wildlife Safety person-h 120 53 26
Water Safety person-h   38 14
Fire Response person-h 120 49 31
Socio-Economic
Employment
Total Employment # 104 229 215
  # person-d 6,663 26,393 6,270
Northern Employment (includes Aboriginal) # 60 190 178
  # person-d 4,020 24,856 4,676
Northern Aboriginal Employment # 90 188 176
  # person-d 6,013 23,717 4,554
Southern Aboriginal Employment #   2  
  # person-d   77  
Workforce Training
Total Training # persons 62 234 132
  duration (h) 935 2,431 1,078
Northern Training # persons 60 176 91
  duration (h) 905 1,924 1,053
Northern Aboriginal Training # persons 59 175 88
  duration (h) 890 1,920 1,061
Purchase of Goods and Services
Northern Suppliers (includes Aboriginal) # 30 175 142
  $ $1,981,000 $3,931,896 4,790,601
Northern Aboriginal Suppliers #   112 95
  $   $3,607,493 3,901,672
Consultation
Community tours and meeting # 5 6 9
  Audience (#) 188 165 205
Workshops # 1    
  Audience (#) 18    
Site Tours # 3 3 3
  Audience (#) 21 30 9

 

CAM F - SARCPA LAKE

CAM F - Sarcpa Lake is located on the Melville Peninsula, approximately 85 km west of Hall Beach, and 100 km southwest of Igloolik. The CAM-F Intermediate Distant Early Warning (DEW) Line Site was constructed at this site in 1957 and subsequently abandoned in 1963, and the site was used as a seasonal scientific research station from 1977 until 1988.

Health & Safety and Environmental Concerns

Following the different uses of this site, both hazardous and non-hazardous wastes were left behind. Large structures left on the site include an airstrip, warehouse, Inuit house, a radar tower that had been knocked down, and oil and lubricants storage facilities. Further, the site contained approximately 10,000 mostly empty barrels, two former landfill areas, contaminated soil, and miscellaneous wastes and chemicals. One major concern included human exposure to physical and chemical hazards, since the site is located within a preferred hunting area for people from the communities of Hall Beach and Igloolik and the buildings on-site were often used as shelters. A further risk existed for terrestrial indigenous wildlife that might be exposed to hazardous materials.

Remediation

A site remediation plan was finalized in 2004 based on all data obtained in previous years and information obtained during community consultations. Both years of the planned two-year remediation phase of the CAM F - Sarcpa Lake Remediation Project have largely been completed. The final tasks to be completed in 2008-2009 include transporting hazardous wastes to Hall Beach so they can be shipped south for secure disposal, and removing the camp and other equipment from the site.

Social, Economic and Environmental Highlights

Final consultations for the remediation phase were completed in 2007, involving 85 people in a series of four events. The next round of consultations will be completed during the long-term monitoring phase, expected to begin in 2008. In 2007-2008, 128 people were employed at the site. Ninety-seven of these employees were Aboriginal peoples living in the North.

Future Plans

Following the final shipping and demobilization tasks, a 25-year long-term monitoring program is scheduled to begin in the fall of 2008.

 

RADIO ISLAND

Radio Island is located on the southern tip of Resolution Island, at the southeast end of Baffin Island. The Canadian Department of Transport operated a navigational aid and weather station at this site from 1929 to 1961.

Health & Safety and Environmental Concerns

Environmental site assessments completed in 1996 and 2001 revealed that hazardous and non-hazardous debris were scattered throughout this site. Non-hazardous debris consisted of cables, scrap metal, barrels, wood and building demolition material. Hazardous materials consisted of lead acid batteries, lead paint, asbestos, and soils containing arsenic, barium, cobalt, cadmium, copper, lead, mercury, molybdenum, nickel, selenium, tin, antimony and zinc.

Remediation

Findings from the environmental site assessments were used to develop a draft Remedial Action Plan, which consisted of the removal and disposal of wastes. Initially, completion of the remediation was planned for the end of 2006-2007, but challenges, such as weather conditions, difficult site conditions, and revised sealift schedule prevented the project from being completed. In 2007-2008, weather and sealift schedules delayed the field season, but the project was successfully completed with all waste disposed of at southern locations.

Social, Economic and Environmental Highlights

Training was provided to employees in a number of areas including: environmental health and safety policy and procedures, workplace hazardous materials information system, wildlife safety, water safety, fire response, helicopter safety, and spills response. Final remediation work was completed without any major incidents.

Future Plans

Due to the fact that all the contamination was removed from the site, no long-term monitoring will be required.

 

Return to Table of Contents





Program Management

NAO's Northern Contaminated Sites Program Management Framework has been in place since 2002 and guides the effective and efficient management of the NCSP. The Framework includes:

The NCSP also produces annual work plans to further guide its program management activities. This section of the report outlines the NCSP's performance on five key program management activities that were undertaken during 2007-2008:

  1. Integrated Risk Management;
  2. Office of the Auditor General (OAG) Audit and Results;
  3. Service Level Agreement (SLA) with Public Works and Government Services Canada (PWGSC);
  4. Environment, Health and Safety Audits and Training; and
  5. Integrated Environmental Management Systems (IEMS).

Integrated Risk Management

Integrated Risk Management: the consideration of risk information in planning, priority setting, and decision-making, through the use of enterprise wide criteria approved for that program, and applied through a process that ensures consistency across program elements and over time.

Integrated Risk Management is the integration of risk considerations by managers into their decision-making in a consistent, thorough, and balanced manner.

In 2007, the NCSP began the process of building on the use of risk to assist site level planning by incorporating strategic level risk profiling and risk assessment to decision making. This work commenced in the summer of 2007 with a series of interviews of senior staff to identify key risks. In September a workshop was held with the four Directors to validate the risk list developed from interviews and to assess the risk levels at a program level.

In the fall of 2007, workshops were held in Iqaluit, Yellowknife and Whitehorse to assess the risk levels in each of the three northern regions. These workshops included the Directors, program staff and a representative from PWGSC. In December, a Corporate Risk Profile was completed which identified the top three risks in the Northern Contaminated Sites Program and as well identified the program outcomes that are most at risk.

The NCSP also commissioned and received specific guidelines on the implementation of Integrated Risk Management as well as tools to support the risk workshops and mitigation planning. The Directors have committed to imbedding Integrated Risk Management information as an integral part of the planning cycle and committed to developing specific mitigation plans. Plans are in place for 2008-2009 to track the effectiveness of the mitigation and as well to reassess the risk levels and their impact on the achievement of program objectives. The INAC NCSP is a leader at the federal level in responding to the risk management requirements set down in the Treasury Board Management Accountability Framework.

OAG Audit and Results

In 2002, 11 years after the federal government began to tackle contaminated sites; the Office of the Auditor General reported that little progress had been made on managing contaminated sites. The federal government was not providing central leadership to deal with the sites, nor had it established how many contaminated sites existed, what environmental or health risks they posed, or what it would cost to remediate them. A subsequent audit by the OAG, completed in March 2008, set out to determine to what extent four government departments - Fisheries and Oceans Canada, Indian and Northern Affairs Canada, National Defence, and Transport Canada - who account for approximately 89% of the federal government's known and suspected contaminated sites, had addressed select recommendations outlined in the 2002 audit. Environment Canada and Treasury Board were included in the audit as well as the FCSAP Secretariat.

Overall, the OAG concluded that these four government departments have made satisfactory progress in managing contaminated sites. More specifically, they have made progress in providing a central leadership role; identifying and assessing contaminated sites, and determining the costs of dealing with contaminated sites. By October 2007, the federal government had identified roughly 17,800 known and suspected contaminated sites. Clear objectives were identified in a Federal Contaminated Sites Action Plan (FCSAP) that was developed to allocate funding to specific sites based on their level of risk. Funding – $1.5 billion over five years – has been initially allocated to manage priority sites. Roughly 340 sites have been remediated, and another 480 are undergoing remediation. All four departments have developed management plans that contain some time-bound commitments aimed at reducing risks posed to human health and the environment. Specifically, INAC invested a significant effort in dealing with four contaminated sites identified as having serious issues in the 2002 audit: Colomac, Faro, Giant, and Mount Nansen. Federal government contaminated sites are estimated to represent a liability of about $3.1 billion (excluding costs for decommissioning nuclear facilities).

Service Level Agreement with PWGSC

In October 2007, a Service Level Agreement (SLA) was approved by both INAC and PWGSC, outlining an updated terms of reference for their combined efforts in contributing to the NCSP. The NCSP Directors reviewed drafts of the SLA and their comments were considered in preparing the final version which they endorsed for approval.

Prior to the SLA, INAC and PWGSC entered into a Memorandum of Understanding (MOU) in February, 2005 whereby PWGSC committed to provide project management and procurement services in support of the NCSP. This MOU provided general direction for the agreement and was to be supplemented by more detailed regional and project charters. In 2007-2008, both departments agreed that the MOU should be reviewed and updated to clarify: i) roles and responsibilities for project and contract management; ii) project lifecycle and handoffs between the two departments; and iii) conditions of service (e.g. fees, reporting). The MOU review began in April 2007, and the outcome was a recommendation that the MOU be replaced with a more precise SLA that would be endorsed by the NCSP Directors and regional Directors and approved by the Director General, Natural Resources and Environment Branch, on behalf of INAC, and by the PWGSC Regional Director General for Western Region. The SLA would be supplemented by Specific Services Agreements (SSAs) at the project level.

The SLA acknowledges that both departments have legitimate authority for the NCSP and clarifies responsibilities and roles for each authority. INAC is the program owner and is accountable for results and budget and PWGSC has contracting authority for construction services. In addition, INAC delegates authority to PWGSC for project management during certain phases of the projects. The party with the designated authority is accountable for ensuring the defined activities are accomplished. The SSAs enable INAC to transfer funds to PWGSC for specific projects or packages of work and for establishing additional conditions of service for each project. To date, two model SSAs have been developed, one for a large project (Giant Mine) and another for a smaller site (Tundra Mine).

Environment, Health and Safety Audits and Training

Audits

NCSP's Environment, Health and Safety (EH&S) Management System and the EH&S Standard Operating Procedures (SOPs) were introduced in the fall of 2006. The purpose of the EH&S Management System and SOPs is to establish minimum standards and requirements for identifying and proactively managing environmental aspects and health and safety hazards within NCSP's area of responsibility. In March 2007, the NCSP developed an EH&S Audit Program Guide that describes how the NAO will conduct EH&S audits as part of the EH&S Management System. This Audit Program is the primary means, along with quarterly reports, for HQ to assess compliance of NCSP operations with the requirements of the EH&S Management System. EH&S Management System and Compliance Audits were undertaken in Nunavut and the Northwest Territories in July 2007. However, an audit was not completed for the Yukon due to administrative challenges. These audits were the first EH&S management system and compliance audits of the NCSP operations. Table 14 summarizes findings of non-conformance and areas of improvement reported in the audits, for which priority rankings were assigned. Priority rankings are defined as follows:

  1. Major regulatory violation; could result in legal action; immediate remedy required
  2. Regulatory violation; could result in legal action; remedy required as soon as possible
  3. Minor regulatory or policy breach; could result in breach of commitment; remedy required when funding and time permits
  4. No regulatory breach; could result in cost savings; would demonstrate a proactive EH&S management approach
  5. Would maintain EH&S compliance; would demonstrate proactive EH&S management, pollution prevention, and process simplification and improvement
Table 14: 2007 Audit Non-Conformance and Areas of Improvement Issues Receiving Priority Rankings
REGION NUMBER OF NON-CONFORMANCE AND AREAS OF IMPROVEMENT ISSUES
  PRIORITY RANKING
Note: Priority rankings assigned based on INAC NCSP Audit Finding Priority Ranking system.
  1 2 3 4 5
NWT 0 6 6 0 0
Nunavut 0 2 14 2 1
TOTAL 0 8 20 2 1

INAC NCSP developed a Corrective and Preventative Action Plan (CPAP) system to address audit findings. For each finding, NCSP identified corrective and/or preventive actions, assigned responsibility, and established a completion date. CPAPs were developed for both regions, and included actions for HQ, regional staff, and project managers. Progress on addressing CPAP items are not discussed in this report, given that 2007-2008 was the first year of audits and corrective planning for the NCSP. This year will be used to develop a baseline, and results on CPAPs will likely be reported in 2008-2009.

Training
Training Evaluation Results

Based on feedback compiled from evaluation forms submitted by training session participants, overall satisfaction with the training sessions was varied:

EH&S MS and compliance training

  • 30% very satisfied
  • 70% satisfied

Detailed work planning and risk management training

  • 15% very satisfied
  • 59% satisfied
  • 19% take it or leave it
  • 7% dissatisfied

During 2007-2008, NCSP undertook a number of training initiatives to help build the capacities of NCSP Project Managers to understand Program requirements and the NCSP EH&S Management System. The initial step in this process included conducting a training needs analysis in order to identify the specific learning needs of NCSP staff. Personnel at headquarters and 16 members of the potential training audience from the three regions where the Program operates - NWT, Nunavut and the Yukon - were interviewed as part of this process. The needs analysis identified specific learning objectives and provided recommendations on potential training session themes. Two training sessions were targeted for delivery to the regions during the fiscal year including:

Training was delivered to 37 NCSP and PWGSC staff. [Note 4] A variety of factors and issues affected the success of these training sessions and a number of lessons learned from the experience have been identified to improve future training initiatives.

Integrated Environmental Management Systems (IEMS)

Treasury Board has mandated that there must be an inventory of contaminated sites, and NAO has been using its own database to manage both financial and non-financial elements of individual NCSP projects and the NCSP as a whole. The database was initially designed to manage the Program's inventory, but it is now also used to satisfy the Treasury Board's reporting requirements. New functionality was added to the database over time, and the database currently acts as the platform for NCSP's corporate procedures and risk management tool. In 2006-2007, a user needs analysis was conducted with regional offices to identify limitations of the existing inventory, and to determine what additional functionality that users deemed relevant. Using the results of this exercise, a functional specifications document was written to revamp NCSP's database in 2007-2008.

In August 2007, the Chief Financial Officer (CFO) of INAC decided to merge Land Trust Services (LTS) and NAOs database systems to develop a broader integrated environmental management system. One of the goals of this initiative was to bring about cost savings to both organizations. Since that decision, LTS and NAO have met several times to discuss merging their applications into a single corporate environmental system. LTS, NAO, and Information Management Branch (IMB) working groups have met to determine the feasibility of a single system, including the next steps of the process. Release of the new database was delayed from March 2008, but is expected to occur in December 2008, at which point it will contain the following features:

 

Return to Table of Contents





Future Directions

NCSP continues to manage the immense task of remediating INAC's northern contaminated sites. Improvements such as the creation of a new Project Management Technical Advisory Committee (PMTAC) and the development of a corporate risk profile, as well as consistent funding provided through the Federal Contaminated Sites Action Plan, have resulted in significant progress. Modifications made to the NCSP program based on recommendations made in the review conducted in 2006-2007 have also resulted in significant improvements to the delivery of the program across the North.

Future directions for the program include:

Thank you for your interest in INAC's Northern Contaminated Sites Program. If you have any questions about this report or require additional information, please contact Joanna Ankersmit, Director of the Contaminated Sites Program, at (819) 997-7247 or Joanna.Ankersmit@aadnc-aandc.gc.ca.

Return to Table of Contents





Appendix 1: Acronyms

CCME – Canadian Council of Ministers of the Environment
CPAP – Corrective and Preventative Action Plan
DEW – Distant Early Warning
DIAND – Department of Indian Affairs and Northern Development
EH&S – Environment, Health and Safety
EH&S MS – Environment, Health and Safety Management System
FCSAP – Federal Contaminated Sites Action Plan
IEMS – Integrated Environmental Management Systems
INAC – Indian and Northern Affairs Canada
IPRP – Independent Peer Review Panel
LTA – Lost-Time Accident
LTS – Land Trust Services
MOU – Memorandum of Understanding
NAO – Northern Affairs Organization
NCS – National Classification System
NCSP – Northern Contaminated Sites Program
NWT – Northwest Territories
OAG – Office of the Auditor General
PCB – Polychlorinated Biphenyl
PWGSC – Public Works and Government Services Canada
SLA – Service Level Agreement
SOP – Standard Operating Procedure
SSA – Specific Services Agreement
UKHM – United Keno Hill Mine
WHMIS – Workplace Hazardous Materials Information System

Return to Table of Contents





Appendix 2: Expenditures by Site


This image shows the expenditures per site from 2003/04 to 2007/08.

Text description of expenditures per site from 2003/04 to 2007/08

This image is for NWT with over 35 sites listed.

 

This image is for Yukon, with 15 sites/programs listed.

Text description of Yukon, with 15 sites/programs listed

This image is for Yukon, with 15 sites/programs listed. Note that expenditures under Yukon Devolution relate to hundreds of small waste sites in the Yukon that have been grouped under one name. As part of the devolution transfer agreement, $2 million/year has been earmarked for the next seven years to clean up these sites.

 

This image shows the expenditures per site for Nunavut, with over 30 sites listed.

Text description of the expenditures per site for Nunavut, with over 30 sites listed

This image shows the expenditures per site for Nunavut, with over 30 sites listed.

 

Return to Table of Contents





Appendix 3: Project Management Component Definitions

Care and Maintenance

Care and maintenance activities at high-risk sites generally include, but are not limited to:

Monitoring

Conditions of water and land-use permits associated with work being carried out at sites in the northern territories, INAC is required to carry out monitoring activities. These monitoring activities are non-discretionary and must absolutely continue to maintain legal compliance.

Regulatory Approvals

Regulatory approvals are essential to carrying out care and maintenance. The discharge of water for instance at Faro, Colomac and Giant are subject to water licensing processes. This component includes costs associated with the process of obtaining water licences, land-use permits, etc.

Consultations

This component includes any costs associated with organizing workshops, meetings, printing information sheets, etc.

Site Investigation and Assessment

This includes any environmental studies (including ecological and human health risk assessments) that need to be completed to advance the understanding of the conditions of the site and to be able to put together a closure plan.

Site Remediation

Any activity deemed part of site clean up. This includes many types of activities, such as removal of contaminated soil and hazardous material, destruction of buildings, etc.

Project Management

The project organization and systems required to manage the work including planning, estimating, reporting, contracts, resources, financial, quality and risk.

Return to Table of Contents





Footnotes

  1. Priority sites are defined as those with a National Classification System (NCS) 1 classification, but do not include sites under risk management/monitoring or contingent liabilities. (return to source paragraph)
  2. Of the initial surplus of $26 million, just over $1 million of INAC-contributed funds were returned to the department for other work. Of the remaining amount ($25 million), NCSP was allowed to carry forward $4.5 million to the 2008-2009 fiscal year, and $17.9 million was reprofiled; however, $2.7 million was considered surplus or lapsed funds that NCSP did not use due, in large part, to challenges in estimating contingencies within projects and across the program. This represents 3% of the total expenditures ($89.1 million) in 2007-2008, a decrease from the 3.4% of total expenditures lapsed in 2006-2007. (return to source paragraph)
  3. Project Management and Project Administration are reported separately in Figures 3 and 4 (return to source paragraph)
  4. PWGSC staff assist in the delivery of NCSP projects the departments work together to achieve the Program's objectives. (return to source paragraph)