National First Nations Infrastructure Investment Plan 2011-2012

Date: June 2011
ISSN: 1927-2200
QS: QS-2013-010-EE-A1

PDF Version   (1010 Kb, 54 Pages)




Table of Contents




Introduction

The First Nations Infrastructure Investment Plan (FNIIP) is developed annually by Aboriginal Affairs & Northern Development Canada (AANDC) in partnership with First Nations to strategically plan investments in the short and medium term to support an economically stable future for First Nations in Canada.

The following document provides an overview of investments being planned in line with the FNIIP through the Capital Facilities & Maintenance Program. It includes priority investment areas, provides a rationale to how the FNIIP is developed and outlines details of specific eligible projects for investment. The FNIIP is a planning document. Not all projects identified in the plan will receive the level of funding identified in a particular year. Regional staff work with First Nations throughout the year to support projects on a prioritized basis with available resources. Adjustments to the plan occur throughout the year and into future years as community, project and financial circumstances change. Information presented in this report captures planned projects as of March 2011. A glossary of Acronyms and Terms is presented at the end of this report to assist readers as required.






Program Overview

The mandate of the Capital Facilities & Maintenance Program is to provide financial and advisory assistance to First Nations in the development of basic public infrastructure which is essential for healthy, safe and sustainable communities. The Capital Facilities & Maintenance Program is part of the Department's broader Strategic Outcome "The Economy" which is to support the economic well-being and prosperity of First Nations, Inuit and Métis people.

The Capital Facilities & Maintenance Program objectives are to assist First Nations in making capital and facility operational and maintenance plans and investment decisions that:

  • maximize the life-cycle of physical assets;
  • mitigate health and safety risks;
  • ensure assets meet applicable codes and standards; and
  • ensure programs are managed and delivered in a cost-effective, environmentally sound and sustainable manner.

The Capital Facilities & Maintenance Program is intended to assist First Nations in the planning, design, construction, operation, maintenance, repair, renovation, and replacement of community infrastructure and facilities including the following asset categories:

  • Water supply, storage, treatment and distribution;
  • Wastewater collection, treatment and disposal;
  • Solid Waste collection and disposal;
  • Elementary and secondary educational facilities;
  • Housing;
  • Roads and bridges;
  • Fire protection including fire halls, fire trucks and firefighting equipment;
  • Electrical power generation and distribution;
  • Community buildings such as community/recreation halls and band offices;
  • Flood and erosion protection;
  • Remediation of contaminated sites;
  • Land acquisition for approved community expansion; and
  • Connectivity.





Priority Action Areas

Capital projects are subject to the Department's National Priority Ranking Framework (see Appendix B). The Framework's priorities are defined by the following Program Activity Categories:

  1. Protection of health and safety as well as assets (assets require upgrading or replacement to meet appropriate standards);
  2. Health and safety improvements (upgrades of existing assets, new construction/acquisition projects to mitigate an identified significant risk to health and safety);
  3. Recapitalization/major maintenance (extend the useful operating life of a facility or asset, or maintain the original service level of the asset); and
  4. Growth (anticipated community growth requiring new housing, roads, schools, community buildings, etc.).





Life Cycle Management of AANDC-Funded Community Infrastructure

AANDC promotes the use of full life-cycle costing analysis when approving capital construction projects. This type of analysis allows for the consideration of all the associated costs (e.g. for design, construction, operations and maintenance, insurance, and major renovations) of the proposed infrastructure throughout its entire life cycle. This type of information is used to make comparisons between proposed options (e.g. building an expensive installation with low operating and maintenance costs versus a less-expensive facility with higher operating and maintenance costs) and determine the most cost-effective option in the short, medium, and long term. This exercise is also useful in determining the funding levels required from the First Nation in future years for the operations and maintenance of the proposed infrastructure.

During an asset's service life, AANDC provides funding support to First Nations to pay for operations and maintenance of funded infrastructure assets. AANDC also encourages good asset management practices by requiring that First Nations implement maintenance management plans for various types of major capital assets. In addition, AANDC tracks the ongoing condition of assets through inspections carried out every three years or yearly under the Asset Condition Reporting System and ensures the repairs and maintenance work needed to preserve an asset is being done.

As part of its efforts to encourage good asset management, AANDC funds a mentoring program called the Circuit Rider Training Program (CRTP). The Circuit Rider Training Program provides mentoring support to operators of water and wastewater systems. This program has helped improve the operation of assets as well as to help First Nations exploit the full service life of the assets.






Resource Allocation Process

Resource allocations for the Capital Facilities & Maintenance Program (CFMP) occur on an annual basis from headquarters to regions and then to First Nations to assist in the development and maintenance of basic community infrastructure. The CFMP budget is divided into the following three funding streams:

  • Operations and Maintenance (O&M) (core budget): funding for the operation and maintenance of community infrastructure assets. Allocated at regional level based on formulae that estimate the cost of operating and maintaining assets; level of funding varies from 20% to 100% depending on the type of asset.
  • Minor Capital (core and/or non-core budget): funding can be either formula-driven [Note 1] or project proposal-driven, for the construction, acquisition, renovation, repair, and on-reserve housing projects valued below $1.5 million.
  • Major Capital (non core budget): funding for specific proposal-driven construction, acquisition, renovation, or significant repair projects valued above $1.5 million. Projects over $10 million require approval at the National level.

Major capital projects, especially in education, as well as water and sewer facilities, are funded primarily by targeted programs such as the Building Canada Plan - Gas Tax Fund, and First Nations Water and Wastewater Action Plan. As those funds are distributed on a per-project basis, variances can be observed between regional allocations.

However, it is in the treatment of minor capital that the widest variance in regional practices can be observed. Some differences can be accounted for by the type of funding relationships between different AANDC regions and First Nations, as well as factors like number of First Nations, geography, number and types of assets owned by First Nations in a particular region.






First Nations Infrastructure Investment Plan and the Capital Planning Process

Under the Management Control Framework for the Capital Facilities & Maintenance Program, AANDC uses FNIIPs for capital planning. This process aims to improve resource management and increase accountability through better capital planning. An effective process depends on:

  • nationally consistent planning practices, using a standardized Regional FNIIP template;
  • using the best-available information to create plans and then to update them reflect the current situation;
  • submission of regional plans in a timely manner, as per established timelines;
  • plans that are balanced; planned expenditures align to allocated funds.

The FNIIP planning process reflects the existing approval authorities and roles and responsibilities set out in the Management Control Framework.

The National FNIIP is a five year plan summarizing eight Regional FNIIPs that have been developed in collaboration with First Nation communities. The National FNIIP identifies specific investments per region, and identifies national trends in infrastructure investment and Capital Facilities & Maintenance Program expenditures.

The FNIIP planning process is designed around three linked plans that feed into one-another: a community level plan, detailing infrastructure needs; a regional plan, planning out program expenditures; and a national plan, that provides a strategic overview of First Nations infrastructure needs and Capital Facilities & Maintenance Program investment.

First Nations Infrastructure Investment Plans - Community Level

FNIIPs are five-year capital investment plans created by each First Nation community which detail infrastructure needs and plans. As set out in the Recipient Reporting Guide, an updated FNIIP must be prepared each year before capital funds are released to First Nations. The community level FNIIP is based upon mandatory reporting requirements prescribed by the Recipient Reporting Guide (Asset Condition Reporting System Projects Annual Report, Changes in Capital Assets Annual Report, Fire Losses Annual Report). It is developed by communities with the support of the AANDC Regional Offices and then submitted for validation and incorporation into the Regional FNIIP.

It is AANDC's goal to ensure every community develops their own five year infrastructure plan based on a life-cycle approach. However, at this point in time, several regions have not instituted this requirement as part of their planning process, given that numerous First Nations within their regions neither have the expertise nor the capacity to develop their own five year plans. In such instances, AANDC officials at the regional level support and work with communities to develop infrastructure plans and identify their infrastructure priorities, and capacity is increasing in many areas.

First Nation Infrastructure Investment Plans - Regional Level

Regional FNIIPs are the key planning and reporting tools used by both regions and headquarters throughout the year. They are developed after validating proposed expenditures in First Nations Infrastructure Investment Plans against program criteria, and then planning allocation of available resources to the highest priorities. Regional FNIIP projects are prioritized using the National Priority Ranking Framework and other priority requirements attached to targeted funds (e.g. First Nations Infrastructure Fund). Higher priority projects are placed in the earlier years of the plan, while lower priority projects are placed in the later years, or beyond the current five-year plan. This, as well as the uncertainty with regards to the renewal of targeted funds, explains why some regions do not have planned investments for all categories, especially major capital projects, beyond the current fiscal year (see Appendix A). Regional offices provide updates of their plan for use at the regional and national level. See Appendix B for the National Priority Ranking Framework.

First Nation Infrastructure Investment Plan - National Level

The National FNIIP is a compilation of all eight Regional FNIIPs. It presents national data and analysis of Capital Facilities & Maintenance Program capital planning in a summary document for senior management review. The National FNIIP is reviewed by the departmental Operations Committee made up of AANDC senior management annually, as per the roles and responsibilities set out in the Management Control Framework for the Capital Facilities & Maintenance Program.






National Plan for 2011-2012

For 2011-2012 the Parliamentary Budget Allocation for Capital Facilities & Maintenance Program (CFMP) (Vote 1, Vote 10) is: $1.212 Billion [Note 2]

Parliamentary Budget Allocation for Capital Facilities & Maintenance Program (CFMP) for 2011-2012
Total FNIIP (Planned Vote 10) $965,903,230
Salaries & Operation and Maintenance (Vote 1) $34,965,000
Sub-Total $1,000,598,230
Other items included in Main Estimates  
Planned Reallocation [Note 3] $162,981,994
Unallocated First Nation Water & Wastewater Action Plan (Vote 10) $39,675,950
Other (Vote 10) $136,000
Climate Change Strategy (Vote 1) $80,266
Statutory $3,979,366
Total $1,207,451,806

National breakdown of planned spending for Vote 10 in 2011-2012
Major Capital Projects  
Education Facilities $66,477,040
Water & Sewer $132,067,362
Contaminated Sites $5,373,986
Community Infrastructure [Note 4] $60,995,887
Minor Capital – formula driven (including housing) $201,558,605
Minor Capital - projects < $1.5 million $101,561,235
Infrastructure O&M $397,869,114
Total $965,903,230

National breakdown of planned spending for Vote 10 in 2011-2012

A chart showing the national breakdown of planned spending for Vote 10 in 2011-2012.

Text description of this chart is available on a separate page.

Planned Major & Minor Capital Projects (Excluding Formula-Driven & O&M)
Current Year Five Year Aggregate
# of Projects Total Value # of Projects Total Value
626 $366,426,070 816 $1,177,200,667

Graph 1: National Breakdown by Funding Type

A chart showing the Planned Funding by Major, Minor Capital and O&M for the period between 2011-2012 and 2015-2016 at the national level.

Text description of this chart is available on a separate page.

Note: Minor Capital Formula has only been identified for current year to provide some context into what the typical split is between proposal and formula-driven minor capital in any given year. The split is not available for future years as AANDC Regions were not requested to provide this level of detail beyond current year. The minor capital category beyond current year (2012-2013 to 2015-2016) all includes both the proposal and formula-driven minor capital.

Graph 2: National Breakdown by Funding Source

A chart showing the Planned Funding by funding source for the period between 2011-2012 and 2015-2016 at the national level

Text description of this chart is available on a separate page.

Graphs 1 and 2 were developed using the data provided in the 2011-2012 Regional FNIIPs and illustrate the breakdown of planned spending (vote 10) by funding type (Major, Minor and Operations & Maintenance) (Graph 1) and funding source (Graph 2). Of the total planned allocations for 2011-2012 fiscal year, major capital funding represents 27%, minor capital 32% and O&M 41%. For the 2011-2012 fiscal year, minor capital has been separated into two categories. These categories represent two distinct allocation vehicles. Of the total planned allocation for minor capital funding, 66% is allocated under minor capital formula-driven, while 33% is allocated as minor capital proposal-driven (See Graph 1). Refer to Table 1 for total planned funding.

The spike in capital funding levels in 2011-2012 and the smaller one in 2012-2013, as shown on Graph 1 & 2, are a result of additional investments from Building Canada Fund - Gas Tax Fund extension (BCGTF), First Nations Infrastructure Fund (FNIF) and the First Nations Water and Wastewater Action Plan (FNWWAP). These initiatives provide funding primarily in the areas of major capital projects for education and water and sewer facilities. Furthermore, a significant portion of FNWWAP funding is allocated to address operation and maintenance of water and wastewater facilities and for the training and certification of water and wastewater operators. FNIF also contributes to the spike seen in 2011-2012 and 2012-2013 in the areas of solid waste, energy systems, local roads and bridges, planning and skills development, and connectivity. The FNIF portion shown separately in Graph 2 is a combination of funds approved for 5 years commencing in 2008-2009 and a second phase of funding approved in 2009-2010 for four years and is sourced through the Building Canada Fund in collaboration with Infrastructure Canada. As part of the first phase of funding, AANDC has responsibility for also making a contribution from the Capital Facilities & Maintenance Program. AANDC's planned contribution has been included in the category of A-Base funding and totals approximately $1.8 million in 2011-2012. In total $69 million is planned to be spent under the First Nations Infrastructure Fund in 2011-2012.

While there is a peak in available funding for 2011-2012, there is a noticeable reduction of total infrastructure funding in subsequent years. This decline is largely the result of targeted programs which are scheduled to expire over the next two years with no identified renewal opportunities at this point in time: First Nations Water and Wastewater Action Plan (March 31, 2012), Building Canada Fund - Gas Tax Fund extension (March 31, 2012) and First Nations Infrastructure Fund (March 31, 2013).

There is a slight decline in total funding levels when comparing 2011-2012 major capital and the A-Base funding levels to future years. This is due to a number of factors including over programming of projects and the tendency of developing infrastructure investment plans that emphasize the alignment between projects and current fiscal year resources only, as well as the shifting of projects to the subsequent fiscal years when resource availability has been exhausted.

Planned Funding in 2011-2012

(Major & Minor Proposal Based Projects Only)

Graph 3: National Funding by Asset Class

A chart showing the national breakdown of planned spending for Major and Minor Proposal Based projects in 2011-2012.

Text description of this chart is available on a separate page.

The largest portions of planned projects are in the asset areas of water and sewer at 45%, community infrastructure at 30% (which includes projects such as roads & bridges, electrification, fuel tanks and fire protection) and education facilities representing a total of 20% of planned projects. These three asset classes receiving the majority of funding is a result of targeted initiatives such as FNWWAP for water and wastewater projects, BCGTF for school projects and FNIF which targets areas of community infrastructure such as green energy, roads & bridges, solid waste and connectivity.

Graph 4: Funding by National Priority Ranking

A chart showing the national breakdown of planned spending for Major and Minor Proposal Based projects in 2011-2012.

Text description of this chart is available on a separate page.

Priority 1 projects represent 34.1% of all planned projects being funded this year. Priority 1 can only be used for water or wastewater projects. These projects can either be upgrades to existing systems or new constructions to deal with imminent health and safety risks, water or wastewater quality or legislative/regulatory requirements. Priority 2 projects represent the largest portion of all planned projects at 62.2%. Unlike Priority 1, Priority 2 projects include all asset classes and cover all program activity categories. This explains the high concentration of Priority 2 projects. Included in this category are recent targeted funding initiatives such as BCGTF, which address new construction in education and FNIF in the area of community infrastructure. Priority 3 and 4 projects represent 2.8% and 0.4% of planned expenditures respectively. These priorities mainly focus on anticipated growth and need. The investments needed to effectively address Priority 1 and 2 projects limit the number of projects that can be funded in the Priority 3 and 4 categories. This distribution further highlights the limitations on current levels of CFMP funding. (Refer to Appendix B for the National Priority Ranking Framework).

Infrastructure Capital - Investment Opportunities

For the purpose of the FNIIP, an investment opportunity is defined as a project that meets program criteria, which may or may not have previously received funding but is not scheduled to receive funding within the time period covered by the current plan (2011-2012 to 2015-2016). The 2011-2012 FNIIP identified 2,214 capital projects valued at approximately $3 billion that regions have recorded in their FNIIPs as investment opportunities. These investment opportunities can be further broken down by asset category and National Priority Ranking.

Graph 5: Capital funding requests by asset class

A chart showing the national breakdown of investment opportunities for capital.

Text description of this chart is available on a separate page.

Graph 5 demonstrates the overall need by major asset category. Through the capital planning process, AANDC regions have identified that the highest demand for infrastructure projects is in the asset category of water and sewer at 48%. Community infrastructure projects have been identified as the second asset category most in demand at 29%, followed by education facilities 15%, housing 6% and contaminated sites 2%. This breakdown is based upon information reported by regions and the national priority ranking framework.

Graph 6: Capital funding requests by priority ranking

A chart showing the national breakdown of investment opportunities for capital.

Text description of this chart is available on a separate page.

Graph 6 illustrates that Priority 1 projects represent 21% of the total future investment opportunities as identified by regions. Priority 1 projects can either be repairs/upgrades or new construction of water or wastewater facilities to deal with imminent health and safety risks, water quality and legislative/regulatory requirements. Priority 2 projects represent 46% of all unfunded projects. Priority 2 projects include all asset classes and cover almost all program activity categories which explain its high percentage. Priority 3 and 4 projects represent a combined total of 17% of investment opportunities. These priorities mainly focus on anticipated growth and need. As Priority 1 & 2 represents a total of 67%, the likelihood of Priority 3 & 4 projects receiving funding is minimal. Priority Unassigned [Note 5].

2011-2012 Planned Acquisition and Construction of Facilities (Major & Minor Capital Projects and Operations & Maintenance)

National Summary
Project Category Previous Year
(Planned Amount)
Planned Spending
Current Year
2011-2012
Year +1
2012-2013
Year +2
2013-2014
Year +3
2014-2015
Year +4
2015-2016
Major Capital Projects
Community Infrastructure 51,849,798 60,795,725 36,437,100 11,860,000 6,781,100 5,835,000
Contaminated Sites 33,296,189 5,373,986 250,019 246,000 - -
Education 157,935,266 66,477,040 32,698,767 16,319,820 11,915,200 16,305,400
Housing 1,655,000 200,162 - - - -
Water and Sewer 231,738,475 132,067,362 97,950,612 85,955,340 91,594,352 81,261,366
Sub-Total (Major) $476,474,728 $264,914,275 $167,336,498 $114,381,160 $110,290,652 $103,401,766
Minor Capital Projects [Note 6]
Community Infrastructure 122,389,003 116,905,569 88,814,599 76,321,379 71,894,154 64,320,929
Contaminated Sites 14,391,221 4,733,311 4,854,130 669,220 931,871 350,000
Education 20,017,413 11,914,297 6,789,132 6,886,082 7,123,832 6,825,932
Housing 184,991,731 126,857,405 125,976,186 126,278,795 129,315,096 106,534,544
Water and Sewer 44,411,134 42,709,258 20,260,768 23,013,318 18,441,684 16,877,936
Sub-Total (Minor) $386,200,502 $303,119,840 $246,694,815 $233,168,795 $227,706,638 $194,909,341
Total Capital (Major & Minor)
Community Infrastructure 174,238,801 177,701,294 125,251,699 88,181,379 78,675,254 70,155,929
Contaminated Sites 47,687,410 10,107,297 5,104,149 915,220 931,871 350,000
Education 177,952,679 78,391,337 39,487,899 23,205,902 19,039,032 23,131,332
Housing 186,646,731 127,057,567 125,976,186 126,278,795 129,315,096 106,534,544
Water and Sewer 276,149,609 174,776,620 118,211,380 108,968,658 110,036,036 98,139,302
Total (Minor & Major) $862,675,230 $568,034,116 $414,031,313 $347,549,955 $337,997,290 $298,311,107
Operations & Maintenance
Community Infrastructure 132,706,445 151,485,380 152,297,245 153,123,991 153,965,855 154,803,877
Contaminated Sites 0 - - - - -
Education 101,202,029 116,957,640 117,652,424 118,361,079 119,083,884 119,821,120
Housing 13,527,006 1,164,667 1,164,767 1,164,767 1,164,867 1,164,967
Water and Sewer 104,535,546 128,261,427 81,644,458 81,940,027 82,241,495 82,527,463
Sub-Total (O&M) $351,971,026 $397,869,114 $352,758,893 $354,589,864 $356,456,100 $358,317,428
Grand Total
Community Infrastructure 306,945,246 329,186,674 277,548,944 241,305,371 232,641,109 224,959,807
Contaminated Sites 47,687,410 10,107,297 5,104,149 915,220 931,871 350,000
Education 279,154,708 195,348,978 157,140,323 141,566,982 138,122,916 142,952,453
Housing 200,173,737 128,222,234 127,140,953 127,443,562 130,479,963 107,699,511
Water and Sewer 380,685,155 303,038,047 199,855,838 190,908,685 192,277,531 180,666,765
Grand Total $1,214,646,256 $965,903,230 $766,790,207 $702,139,819 $694,453,390 $656,628,535

The dashes in the above National Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.






Appendix A - Regional Summaries

Atlantic Region

Breakdown of Planned Spending 2011-2012: (Vote 10 Only)
Major Capital Projects  
Education Facilities $5,860,000
Water & Sewer $4,071,000
Contaminated Sites $0
Community Infrastructure $2,309,000
Minor Capital – formula driven (including housing) $8,543,000
Minor Capital - projects < $1.5 million $2,101,000
Infrastructure O&M $18,981,000
Total (FNIIP) - Vote 10 $41,865,000

Breakdown of Planned Spending for Vote 10 in 2011-2012

A chart showing the Atlantic breakdown of planned spending for Vote 10 in 2011-2012.

Text description of this chart is available on a separate page.

Regional Snapshot
First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) 21 Projects $14,341,000
First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) 32 Projects $51,053,000
Infrastructure Investment per Capita
(On-Reserve Registered Indian Population as of Dec. 31, 2010)
21,824 People $1,918

Regional Practices - Minor Capital

Approximately 80% of total capital (core and non-core) is included in First Nations agreements, of which the majority is used for housing. There is low or no monitoring of this funding. For instance, there is no requirement for First Nations to spend minor capital on Asset Condition Reporting System or FNIIP priorities.

Highlights - Fiscal Year 2011-2012

Tobique First Nation - New School
Construction of school - Tobique First Nation
Construction of school - Tobique First Nation (Photo provided by Atlantic Regional office)

This project is the top priority on the Atlantic regional priority list for new school construction. The existing school asset was constructed in 1975 and is 1994 m2 serving kindergarten to Grade five. Since the initial construction there has been no major upgrade or retrofit. In April 2008, the Band Council relocated the students to a temporary facility as the existing school no longer met the standards for indoor air quality, access or emergency efficiency. In addition, there were concerns with the ability of the existing school to accommodate the educational requirements of the growing community in terms of space and function.

Through the Building Canada Plan - Gas Tax Fund, the department was able to secure funding in the order of $10.3 million for the community to proceed with the construction of a new education facility. The scope of the work for this project includes the planning, design and construction of a 2490m2 kindergarten to Grade 8 facility as well as the demolition of the existing structure.

This new school which is anticipated to be completed in September 2011 will provide a safe and quality learning environment for the children of Tobique First Nation. It will limit the need for children to attend school off reserve and ultimately enhance the communities' educational outcomes.

Water Reservoir - Pabineau First Nation
Water Reservoir - Pabineau First Nation (Photo provided by Atlantic Regional office)

Pabineau First Nation - Water Reservoir, Treatment and Distribution System Upgrades

Pabineau First Nation has an on reserve registered population of 101. Their current water source is from individual wells which are not sustainable from either a quantity or quality perspective. The community is currently under boil water advisory which cannot be effectively addressed under their current system. The new project will see the construction of a new reservoir, a new treatment system and new distribution lines. This project will cost $6 million over the next 5 years and will significantly improve the conditions of the drinking water and allow the community to focus their efforts on other priorities.

Pictou Landing First Nation - New Sewage Treatment Plant

Pictou Landing has an on reserve registered population of 452 people. Their current treatment facility has insufficient capacity, is obsolete and does not meet the needs of the community. This project is considered to be essential to meet the significantly increasing demand the community has and will allow for continued growth. Notwithstanding the various health & safety issues, this new plant will address any possible environmental issues that the current facility may present to the community. The new treatment plant will cost $1.6M and the work is expected to be fully completed in the current fiscal year.

Atlantic Summary
Project Category Previous Year
(Planned Amount)
Planned Spending
Current Year
2011-2012
Year +1
2012-2013
Year +2
2013-2014
Year +3
2014-2015
Year +4
2015-2016
Major Capital Projects
Community Infrastructure 500,000 2,309,000 5,631,000 5,000,000 400,000 -
Contaminated Sites 0 - - - - -
Education 8,599,056 5,860,000 - - - -
Housing 0 - - - - -
Water and Sewer 14,696,000 4,071,000 3,471,000 2,382,000 1,297,000 2,723,000
Sub-Total (Major) $23,795,056 $12,240,000 $9,102,000 $7,382,000 $1,697,000 $2,723,000
Minor Capital Projects
Community Infrastructure 2,076,248 2,728,300 2,735,300 1,154,300 854,300 854,300
Contaminated Sites 25,000 65,000 - - - -
Education 0 - - - - -
Housing 12,081,230 7,688,700 7,688,700 7,688,700 7,688,700 7,688,700
Water and Sewer 1,297,000 162,000 130,000 1,171,000 2,156,000 1,130,000
Sub-Total (Minor) $15,479,478 $10,644,000 $10,554,000 $10,014,000 $10,699,000 $9,673,000
Total Capital (Major & Minor)
Community Infrastructure 2,576,248 5,037,300 8,366,300 6,154,300 1,254,300 854,300
Contaminated Sites 25,000 65,000 - - - -
Education 8,599,056 5,860,000 - - - -
Housing 12,081,230 7,688,700 7,688,700 7,688,700 7,688,700 7,688,700
Water and Sewer 15,993,000 4,233,000 3,601,000 3,553,000 3,453,000 3,853,000
Total (Minor & Major) $39,274,534 $22,884,000 $19,656,000 $17,396,000 $12,396,000 $12,396,000
Operations & Maintenance
Community Infrastructure 3,324,321 10,368,600 10,368,600 10,368,600 10,368,600 10,368,600
Contaminated Sites 0 - - - - -
Education 0 3,150,880 3,150,880 3,150,880 3,150,880 3,150,880
Housing 12,278,887 50,000 50,000 50,000 50,000 50,000
Water and Sewer 936,000 5,411,520 4,726,520 4,726,520 4,726,520 4,726,520
Sub-Total (O&M) $16,539,208 $18,981,000 $18,296,000 $18,296,000 $18,296,000 $18,296,000
Grand Total
Community Infrastructure 5,900,569 15,405,900 18,734,900 16,522,900 11,622,900 11,222,900
Contaminated Sites 25,000 65,000 - - - -
Education 8,599,056 9,010,880 3,150,880 3,150,880 3,150,880 3,150,880
Housing 24,360,117 7,738,700 7,738,700 7,738,700 7,738,700 7,738,700
Water and Sewer 16,929,000 9,644,520 8,327,520 8,279,520 8,179,520 8,579,520
Grand Total $55,813,742 $41,865,000 $37,952,000 $35,692,000 $30,692,000 $30,692,000

The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.

Quebec Region

Breakdown of planned spending 2011-2012: (Vote 10 Only)
Major Capital Projects  
Education Facilities $4,824,200
Water & Sewer $8,562,600
Contaminated Sites $0
Community Infrastructure $12,071,200
Minor Capital – formula driven (including housing) $21,274,400
Minor Capital - projects < $1.5 million $7,236,500
Infrastructure O&M $29,909,300
Total (FNIIP) - Vote 10 $83,878,200

Breakdown of Planned Spending for Vote 10 in 2011-2012

A chart showing the Quebec breakdown of planned spending for Vote 10 in 2011-2012.

Text description of this chart is available on a separate page.

Regional Snapshot
First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) 38 Projects $32,694,500
First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) 51 Projects $127,223,100
Infrastructure Investment per Capita
(On-Reserve Registered Indian Population as of Dec. 31, 2010)
52,367 People $1,601

Regional Practices - Minor Capital

About 60% of capital is under core and minor capital funding for First Nations. Funding levels are determined by formula, with housing being a principal driver of funding. First Nations are expected to prioritize projects for minor capital such as Asset Condition Reporting System projects, lot servicing, and housing. The regional office receives annual capital plan updates from First Nations that tell which projects were initiated and/or completed by First Nations as well as the cost and source of funds. This process assists in tracking how minor capital funding is used by First Nations.

Highlights - Fiscal Year 2011-2012

Long Point (Winneway) First Nation - New School

Long Point First Nation is planning the construction of a new school at a total estimated cost of $7.5 million. This project is a result of health and safety issues with the existing education facility. In 2007, based on a report tabled by the First Nation, Health Canada supported the Council's decision to vacate the school due to the presence of mould. Since then, temporary facilities were erected in the existing gymnasium and security and safety measures were put in place. The condition of the existing school combined with the costs of renovating it lead to a common understanding that a new facility would be built. School population is not a factor in this project since overall school population remained constant and the new facility will provide the same level of service.

Construction of an access bridge
Construction of an access bridge (photo provided by AANDC QC region)
Uashat First Nation - Community Development Project

Uashat First Nation is currently undertaking a community development project valued at $7.5 million. The Department, through the First Nation Infrastructure Fund (FNIF), is providing $3.3 million for the construction of an access bridge as part of the overall project.

The community had no more land base available for lot development to accommodate the rapid growth rate; therefore an addition to its existing reserve was necessary. The area that was selected presented a number of challenges such as special requirements from the town of Sept-Îles, access needs to be secured by building a bridge over a small creek and services (water & sewer) to hook up to the existing network. Once access to the new area is completed, the First Nation will be able to proceed with future development.

Natashquan First Nation - Wastewater Treatment Plan Rehabilitation

Natashquan First Nation will benefit from a major wastewater treatment plant rehabilitation project that is currently underway. This project is a result of the limited capacity of the existing treatment plant and the requirements to increase this capacity that will meet the present and future needs of the community in light of significant population growth.

The total estimated cost of the project is $3 million. The project is currently at the feasibility stage and various options such as a third lagoon or a new technology called bio-reactor are being considered. This project also presents a challenge as the existing treatment facility is located in an area sensitive to shoreline erosion.

Quebec Summary
Project Category Previous Year
(Planned Amount)
Planned Spending
Current Year
2011-2012
Year +1
2012-2013
Year +2
2013-2014
Year +3
2014-2015
Year +4
2015-2016
Major Capital Projects
Community Infrastructure 1,483,700 12,071,200 1,407,500 - - -
Contaminated Sites 0 - - - - -
Education 13,771,300 4,824,200 6,416,400 382,900 1,915,200 6,305,400
Housing 0 - - - - -
Water and Sewer 34,996,100 8,562,600 6,381,500 12,635,900 11,312,200 7,633,400
Sub-Total (Major) $50,251,100 $25,458,000 $14,205,400 $13,018,800 $13,227,400 $13,938,800
Minor Capital Projects
Community Infrastructure 13,275,100 14,290,000 212,625,100 11,809,000 11,310,200 11,311,500
Contaminated Sites 344,800 600,000 350,000 350,000 350,000 350,000
Education 640,000 425,600 425,600 425,700 425,800 425,900
Housing 15,967,600 7,105,900 6,876,600 6,877,500 7,378,500 6,879,300
Water and Sewer 5,399,800 6,089,400 2,696,500 2,681,900 2,682,400 2,682,900
Sub-Total (Minor) $35,627,300 $28,510,900 $22,973,800 $22,144,100 $22,146,900 $21,649,600
Total Capital (Major & Minor)
Community Infrastructure 14,758,800 26,361,200 14,032,600 11,809,000 11,310,200 11,311,500
Contaminated Sites 344,800 600,000 350,000 350,000 350,000 350,000
Education 14,411,300 5,249,800 6,842,000 808,600 2,341,000 6,731,300
Housing 15,967,600 7,105,900 6,876,600 6,877,500 7,378,500 6,879,300
Water and Sewer 40,395,900 14,652,000 9,078,000 15,317,800 13,994,600 10,316,300
Total (Minor & Major) $85,878,400 $53,968,900 $37,179,200 $35,162,900 $35,374,300 $35,588,400
Operations & Maintenance
Community Infrastructure 11,981,300 12,015,200 12,233,100 12,454,000 12,677,900 12,904,700
Contaminated Sites 0 - - - - -
Education 9,773,800 9,858,900 9,860,100 9,861,300 9,862,500 9,863,700
Housing 620,500 500,800 500,900 500,900 501,100 501,100
Water and Sewer 7,489,000 7,534,400 4,909,900 4,910,500 4,911,100 4,911,700
Sub-Total (O&M) $29,864,600 $29,909,300 $27,504,000 $27,726,700 $27,952,500 $28,181,200
Grand Total
Community Infrastructure 26,740,100 38,376,400 26,265,700 24,263,000 23,988,100 24,216,200
Contaminated Sites 344,800 600,000 350,000 350,000 350,000 350,000
Education 24,185,100 15,108,700 16,702,100 10,669,900 12,203,500 16,595,000
Housing 16,588,100 7,606,700 7,377,500 7,378,400 7,879,500 7,380,400
Water and Sewer 47,884,900 22,186,400 13,987,900 20,228,300 18,905,700 15,228,000
Grand Total $115,743,000 $83,878,200 $64,683,200 $62,889,600 $63,326,800 $63,769,600

The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.

Ontario Region

Breakdown of planned spending 2011-2012: (Vote 10 Only)
Major Capital Projects  
Education Facilities $16,047,925
Water & Sewer $28,657,314
Contaminated Sites $2,228,986
Community Infrastructure $8,180,298
Minor Capital – formula driven (including housing) $53,501,603
Minor Capital - projects < $1.5 million $29,589,241
Infrastructure O&M $108,517,545
Total (FNIIP) - Vote 10 $246,722,912

Breakdown of Planned Spending for Vote 10 in 2011-2012

A chart showing the Ontario breakdown of planned spending for Vote 10 in 2011-2012.

Text description of this chart is available on a separate page.

Regional Snapshot
First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) 185 Projects $84,703,764
First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) 206 Projects $134,681,703
Infrastructure Investment per Capita
(On-Reserve Registered Indian Population as of Dec. 31, 2010)
88,420 People $2,790

Regional Practices - Minor Capital

Funding levels for minor capital are determined by formula. Minor capital is provided to First Nations to support infrastructure, education facilities, and on reserve housing. Minor capital activities that are supported by this funding are identified by First Nations using the Five Year Capital Plan - Annual Update report. Funding is provided as a Flexible Transfer Payment, the expenditure of which is identified by First Nations annual audited financial statements.

Highlights - Fiscal Year 2011-2012

Wasauksing First Nation - Water Supply, Treatment, Storage and Distribution System Project
Construction of the Water Treatment Plant
Construction of the Water Treatment Plant (photo provided by Diverse Technical Services)

Wasauksing First Nation is a rural community with approximately 475 members living on reserve. The elders' complex, the administration complex which includes the daycare, the school, the health centre, the fire hall and 33 houses are all currently being serviced by the existing water treatment plant. This water treatment plant (constructed in 2003) was erected as an interim measure to address water various water issues. To date, the plant, still in use, no longer meets the current water standards and is operating beyond full capacity.

In addition to the water treatment plant, there are 21 homes being services from several communal drilled groundwater wells that do not meet the current regulations and an additional 10 homes drawing water directly from the lake which are under boil water advisories.

The new water system will service the existing 33 houses, the elders' complex and the administration complex as well as provide rural water delivery to approximately 81 additional houses that are beyond the main core. The other houses will be on future waterline extensions. The water truck along with the installation of cisterns for homes in the rural areas will provide a potable water supply to the majority of the community.

In addition to improving the quality of the drinking water, the new distribution system will provide adequate fire water flows and pressures to all main facilities of the community and improved the access to water for the houses beyond the limited of the distribution system in the event of fire. The current total estimated cost of this project is $17 million.

Lac Seul First Nation - New School
Obishikokaang School - Lac Seul First Nation
Obishikokaang School - Lac Seul First Nation (photo provided by Keewatin-Aski Ltd.)

The new stand alone Obishikokaang School Project at Lac Seul First Nation is substantially complete and has been occupied since September 2010. The Department is providing funding to the community this year to address any minor deficiencies and for the school site development.

The Department provided funding from the Building Canada Plan - Gas Tax Fund to support a 1545 m2 facility. The community contributed $575,000 towards the project which allowed for an additional 498 m2outside the Department's School Space Accommodation Standard. The school is sized to accommodate up to 166 students (K4 to Grade 8) and cost approximately $7 million.

Students from Lac Seul were previously attending a provincially operated school in Hudson, Ontario approximately 13 km from the reserve. It was anticipated that the school board was going to close the Hudson school forcing the students from Lac Seul to attend a provincially operated school in Sioux Lookout. This option was considered unacceptable by the community due to the increased travel time and distance. This new facility will provide a positive impact on both the Lac Seul First Nation and surrounding communities by providing a safe and culturally sensitive learning environment.

Ontario Summary
Project Category Previous Year
(Planned Amount)
Planned Spending
Current Year
2011-2012
Year +1
2012-2013
Year +2
2013-2014
Year +3
2014-2015
Year +4
2015-2016
Major Capital Projects
Community Infrastructure 17,913,628 7,980,136 7,044,000 1,993,000 1,993,000 1,993,000
Contaminated Sites 7,094,289 2,228,986 160,019 156,000 - -
Education 36,210,734 16,047,925 10,697,303 12,000,000 10,000,000 10,000,000
Housing 0 200,162 - - - -
Water and Sewer 39,659,779 28,657,314 34,322,987 24,498,863 23,405,600 18,286,126
Sub-Total (Major) $100,878,430 $55,114,523 $52,224,309 $38,647,863 $35,398,600 $30,279,126
Minor Capital Projects
Community Infrastructure 46,854,207 42,452,027 24,834,362 24,128,130 24,128,130 24,128,130
Contaminated Sites 5,221,321 3,578,251 4,364,130 179,220 431,871 -
Education 5,914,062 6,353,772 2,142,607 2,142,607 2,142,607 2,142,607
Housing 20,150,277 23,421,808 23,421,808 23,421,808 23,421,808 23,421,808
Water and Sewer 8,089,131 7,284,986 4,476,284 3,999,684 3,809,058 3,809,058
Sub-Total (Minor) $86,228,998 $83,090,844 $59,239,191 $53,871,449 $53,933,474 $53,501,603
Total Capital (Major & Minor)
Community Infrastructure 64,767,835 50,432,163 31,878,362 26,121,130 26,121,130 26,121,130
Contaminated Sites 12,315,610 5,807,237 4,524,149 335,220 431,871 -
Education 42,124,796 22,401,697 12,839,910 14,142,607 12,142,607 12,142,607
Housing 20,150,277 23,621,970 23,421,808 23,421,808 23,421,808 23,421,808
Water and Sewer 47,748,910 35,942,300 38,799,271 28,498,547 27,214,658 22,095,184
Total (Minor & Major) $187,107,428 $138,205,367 $111,463,500 $92,519,312 $89,332,074 $83,780,729
Operations & Maintenance
Community Infrastructure 35,304,060 39,226,203 39,226,203 39,226,203 39,226,203 39,226,203
Contaminated Sites 0 - - - - -
Education 30,495,822 31,763,797 31,763,797 31,763,797 31,763,797 31,763,797
Housing 28,500 92,682 92,682 92,682 92,682 92,682
Water and Sewer 21,061,960 37,434,863 18,893,875 18,893,875 18,893,875 18,893,875
Sub-Total (O&M) $86,890,342 $108,517,545 $89,976,557 $89,976,557 $89,976,557 $89,976,557
Grand Total
Community Infrastructure 100,071,895 89,658,366 71,104,565 65,347,333 65,347,333 65,347,333
Contaminated Sites 12,315,610 5,807,237 4,524,149 335,220 431,871 -
Education 72,620,618 54,165,494 44,603,707 45,906,404 43,906,404 43,906,404
Housing 20,178,777 23,714,652 23,514,490 23,514,490 23,514,490 23,514,490
Water and Sewer 68,810,870 73,377,163 57,693,146 47,392,422 46,108,533 40,989,059
Grand Total $273,997,770 $246,722,912 $201,440,057 $182,495,869 $179,308,631 $173,757,286

The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.

Manitoba Region

Breakdown of planned spending 2011-2012: (Vote 10 Only)
Major Capital Projects  
Education Facilities $10,368,000
Water & Sewer $34,816,100
Contaminated Sites $3,055,000
Community Infrastructure $21,604,400
Minor Capital – formula driven (including housing) $48,251,334
Minor Capital - projects < $1.5 million $8,593,500
Infrastructure O&M $62,940,239
Total (FNIIP) - Vote 10 $189,628,573

Breakdown of Planned Spending for Vote 10 in 2011-2012

A chart showing the Manitoba breakdown of planned spending for Vote 10 in 2011-2012.

Text description of this chart is available on a separate page.

Regional Snapshot
First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) 51 Projects $78,437,000
First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) 76 Projects $146,310,900
Infrastructure Investment per Capita
(On-Reserve Registered Indian Population as of Dec. 31, 2010)
84,392 People $2,247

Regional Practices - Minor Capital

Approximately 60% of the total capital budget (including housing) is distributed to First Nations as minor capital distributed on a formula basis. The regional office receives reports from First Nations on tracking the spending of minor capital. For First Nations in multi-year agreements, there is no monitoring of how allocations for minor capital are spent.

Highlights - Fiscal Year 2011-2012

Construction of the St. Theresa Point Middle School
Construction of the St. Theresa Point Middle School (photo provided by Ininew Limited Partnership)
St. Theresa Point First Nation - Phase II School Project

St. Theresa Point First Nation is a remote, winter road access community with approximately 3,231 people living on-reserve. The original Pre-Kindergarten to Grade 12 School opened in 1974 and by the mid 1990's reached its design capacity and was overcrowded. The school project to replace the existing school was initiated in 1996 and was to include a Pre-Kindergarten to Grade 4 and Grade 9 to Grade 12 school with a stand alone Grade 5 to Grade 8 school. Due to the cost of the school facilities, the project was broken into two phases.

Phase I of the school project was completed in September 1999 and included the construction of a 3,997 m2 Grade 9 to Grade 12 high school and 19 teachers' residences. Since the completion of Phase I, the original community school was destroyed by fire on May 12, 2004. The kindergarten to Grade 8 students have since been schooled in 14 temporary classrooms located both in the vicinity of the former school and adjacent to the high school.

Long Plain Sewage Lagoon
Long Plain Sewage Lagoon - (photo provided by Ininew Limited Partnership)


Construction of the south shore Sagkeng Water Treatment Plan
Construction of the south shore Sagkeng Water Treatment Plan (photo provided by P.M. Associates Ltd.)

Phase II of the School Project is currently underway and is receiving funding from the Building Canada Plan - Gas Tax Fund Extension. The project consists of the design and construction of a new 3,382.9 m2 Grade 5 to Grade 8 middle school and a 1,888.8 m2 Kindergarten to Grade 4 addition to the existing high school. The project also consists of the construction of 973 m2 of new teacherages and the conversion of 14 temporary classrooms to teachers' residences. The schools have been designed to accommodate a projected enrolment of 1,150 students. The project is scheduled to be completed in December 2011 with a total project cost of $38 million.

Long Plain First Nation - New Sewage Lagoon

A new aerated lagoon wastewater treatment facility at Long Plain First Nation is currently under construction and scheduled to be completed in the fall of 2011 at a total cost of $10.5 million. The lagoon will service the communities of Long Plain and Dakota Plains and will allow for the decommissioning of the two existing mechanical sewage treatment plants that have been in service since the mid 1990's. This project will provide these communities with wastewater treatment and disposal that will meet their present and future needs in the face of significant growth in population since the original plants were constructed.

Sagkeeng First Nation - Water Treatment Plan

An addition to the South Shore Sagkeeng water treatment plant is currently being constructed and the existing North Shore water treatment plant is being renovated and converted to a pumping station. When completed in the summer 2011, the South Shore water treatment plant will produce the potable water requirements for both the South Shore (population approx. 2,500) and the North Shore (population approx. 1,500) communities of the Sagkeeng First Nation. The project cost is $7.4 million.

Manitoba Summary
Project Category Previous Year
(Planned Amount)
Planned Spending
Current Year
2011-2012
Year +1
2012-2013
Year +2
2013-2014
Year +3
2014-2015
Year +4
2015-2016
Major Capital Projects
Community Infrastructure 14,231,000 21,604,400 7,723,200 3,967,000 3,488,100 2,942,000
Contaminated Sites 14,529,400 3,055,000 - - - -
Education 27,017,500 10,368,000 - - - -
Housing 0 - - - - -
Water and Sewer 45,534,700 34,816,100 11,261,100 7,948,000 11,900,000 11,900,000
Sub-Total (Major) $101,312,600 $69,843,500 $18,984,300 $11,915,000 $15,388,100 $14,842,000
Minor Capital Projects
Community Infrastructure 22,280,236 21,103,859 16,893,957 14,991,862 12,388,185 5,916,319
Contaminated Sites 0 - - - - -
Education 1,987,004 775,000 468,500 535,800 673,000 375,000
Housing 40,418,835 30,746,388 29,679,925 29,999,166 32,280,689 10,317,176
Water and Sewer 2,847,255 4,219,587 4,544,589 7,328,734 2,624,226 741,693
Sub-Total (Minor) $67,533,330 $56,844,834 $51,586,971 $52,855,562 $47,966,100 $17,350,188
Total Capital (Major & Minor)
Community Infrastructure 36,511,236 42,708,259 24,617,157 18,958,862 15,876,285 8,858,319
Contaminated Sites 14,529,400 3,055,000 - - - -
Education 29,004,504 11,143,000 468,500 535,800 673,000 375,000
Housing 40,418,835 30,746,388 29,679,925 29,999,166 32,280,689 10,317,176
Water and Sewer 48,381,955 39,035,687 15,805,689 15,276,734 14,524,226 12,641,693
Total (Minor & Major) $168,845,930 $126,688,334 $70,571,271 $64,770,562 $63,354,200 $32,192,188
Operations & Maintenance
Community Infrastructure 15,980,622 16,030,079 16,030,079 16,030,079 16,030,079 16,030,079
Contaminated Sites 0 - - - - -
Education 19,303,394 20,440,642 20,440,642 20,440,642 20,440,642 20,440,642
Housing 183,819 187,792 187,792 187,792 187,792 187,792
Water and Sewer 27,015,370 26,281,726 18,039,126 18,039,126 18,039,126 18,039,126
Sub-Total (O&M) $62,483,205 $62,940,239 $54,697,639 $54,697,639 $54,697,639 $54,697,639
Grand Total
Community Infrastructure 52,491,858 58,738,338 40,647,236 34,988,941 31,906,364 24,888,398
Contaminated Sites 14,529,400 3,055,000 - - - -
Education 48,307,898 31,583,642 20,909,142 20,976,442 21,113,642 20,815,642
Housing 40,602,654 30,934,180 29,867,717 30,186,958 32,468,481 10,504,968
Water and Sewer 75,397,325 65,317,413 33,844,815 33,315,860 32,563,352 30,680,819
Grand Total $231,329,135 $189,628,573 $125,268,910 $119,468,201 $118,051,839 $86,889,827

The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.

Saskatchewan Region

Saskatchewan Breakdown of planned spending 2011-2012: (Vote 10 Only)
Major Capital Projects  
Education Facilities $7,180,600
Water & Sewer $22,561,500
Contaminated Sites $0
Community Infrastructure $5,059,900
Minor Capital – formula driven (including housing) $28,146,203
Minor Capital - projects < $1.5 million $14,890,400
Infrastructure O&M $51,516,775
Total (FNIIP) - Vote 10 $129,355,378

Saskatchewan Breakdown of Planned Spending for Vote 10 in 2011-2012

A chart showing the Saskatchewan breakdown of planned spending for Vote 10 in 2011-2012.

Text description of this chart is available on a separate page.

Saskatchewan Regional Snapshot
First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) 98 Projects $49,692,400
First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) 129 Projects $178,523,100
Infrastructure Investment per Capita
(On-Reserve Registered Indian Population as of Dec. 31, 2010)
66,707 People $1,939

Regional Practices - Minor Capital

Minor capital is split between two areas. The "band-based capital" is allocated on a formula basis and focus on housing, community buildings and fire protection. Funds are distributed to First Nations when the regional office receives progress reports for previously funded projects (based on inspections in the case of housing). First Nations in multi-year agreements receive band-based capital funding as part of their core funding. There is less control over these funds. The second component is for all other projects under $1.5 million, mostly education and water and sewer facilities. Those projects are proposal-driven and are fully funded by AANDC based on the actual project costs.

Highlights - Fiscal Year 2011-2012

English River First Nation - Willow Heart Bridge Project
Construction of the Willow Heart Bridge - English River First Nation
Construction of the Willow Heart Bridge - English River First Nation (photo provided by Saskatchewan Regional Office)

This project is for a bridge over the Churchill River complete with abutments, immediate approach road works, decking, double lane roadway, and pedestrian walkway.Funded was identified under the First Nation Infrastructure Fund (FNIF). The subdivided area on the Wapachewunak Reserve is almost fully occupied and all economically viable land has been developed for subdivisions. There is no other area available for subdivision development on the Reserve 192D south of the Churchill River at Patuanak. The English River First Nation have initiated a subdivision development plan which will see the immediate construction of between 30 and 50 lots, and the planning for up to 500 lots across the Churchill River, with access via the Willow Heart Bridge across the Churchill River. Future infrastructure development will also include a new lagoon across the Churchill River as the existing lagoon at English River is at capacity.

The design was initiated July 2009 and the project went to tender in March 2010. Construction was started May 2010 and is on schedule for a June/July 2011 completion. Total estimated cost for this project is $8,551,000.

Ahtahkakoop School Addition/Renovation

The existing school asset was constructed in 1976 with a high school addition constructed in 1994 bringing the total school size to 4,218 m2 serving kindergarten to grade twelve. Since 2007, four portable classroom units have been located at this site to deal with overcrowding. A life cycle cost study of the existing school determined that the most economical approach was to replace the original 1,492 m2 elementary portion of the school constructed in 1976 with a new 2,157 m2 addition and to carry out renovation on the 1994 facility. The result is a capital project costing $8,906,000 that saw construction initiated in 2010-2011.

Through the Building Canada Plan - Gas Tax Fund, the Department was able to secure funding of $5.8 million for the community to proceed with the construction of the new education facility. The balance of the project cost is being funded from the Capital Facilities and Maintenance Program.

This school addition/renovation project is anticipated to be completed by March 2012 and will provide a safe and quality learning environment for the children of Ahtahkakoop First Nation.

Poundmaker Water Treatment Plant Upgrade/Expansion

The project consists of upgrading and expanding the treatment, storage and pumping capacity of the school and the core area water treatment plants. The core area water treatment plant will be converted to a re-chlorination and re-distribution booster reservoir with the treatment upgrades being completed at the school water treatment plant. The project includes a source water study, well improvements, and a new distribution line between the school water treatment plant and the core area plant.

Feasibility and design work was completed in 2009-2010 and construction of the project initiated in 2011-2012. The project is currently estimated to cost $6,400,000 and is anticipated to be completed during the 2012-2013 fiscal year. The Poundmaker First Nation currently has an on-reserve population of 750 and the new water treatment plant capacity is designed for a projected 20 year population of 1,355.

Saskatchewan Summary
Project Category Previous Year
(Planned Amount)
Planned Spending
Current Year
2011-2012
Year +1
2012-2013
Year +2
2013-2014
Year +3
2014-2015
Year +4
2015-2016
Major Capital Projects
Community Infrastructure 2,852,200 5,059,900 4,871,400 - - -
Contaminated Sites 0 - - - - -
Education 13,829,900 7,180,600 9,000,000 - - -
Housing 0 - - - - -
Water and Sewer 26,898,200 22,561,500 17,526,700 15,853,000 17,097,000 16,425,000
Sub-Total (Major) $43,580,300 $34,802,000 $31,398,100 $15,853,000 $17,097,000 $16,425,000
Minor Capital Projects
Community Infrastructure 1,305,800 4,360,600 2,722,600 905,500 - -
Contaminated Sites 15,000 - - - - -
Education 1,619,000 2,502,300 1,000,000 1,000,000 1,000,000 1,000,000
Housing 41,103,100 28,146,203 28,474,639 28,615,844 28,759,873 28,906,782
Water and Sewer 8,825,300 8,027,500 1,825,000 3,900,000 3,900,000 3,660,000
Sub-Total (Minor) $52,868,200 $43,036,603 $34,022,239 $34,421,344 $33,659,873 $33,566,782
Total Capital (Major & Minor)
Community Infrastructure 4,158,000 9,420,500 7,594,000 905,500 - -
Contaminated Sites 15,000 - - - - -
Education 15,448,900 9,682,900 10,000,000 1,000,000 1,000,000 1,000,000
Housing 41,103,100 28,146,203 28,474,639 28,615,844 28,759,873 28,906,782
Water and Sewer 35,723,500 30,589,000 19,351,700 19,753,000 20,997,000 20,085,000
Total (Minor & Major) $96,448,500 $77,838,603 $65,420,339 $50,274,344 $50,756,873 $49,991,782
Operations & Maintenance
Community Infrastructure 19,930,200 14,630,875 14,878,793 15,131,668 15,389,602 15,652,694
Contaminated Sites 0 - - - - -
Education 20,998,500 24,381,481 24,854,111 25,336,193 25,827,917 26,329,475
Housing 260,000 260,000 260,000 260,000 260,000 260,000
Water and Sewer 10,806,200 12,244,419 8,154,537 8,317,628 8,483,980 8,653,660
Sub-Total (O&M) $51,994,900 $51,516,775 $48,147,440 $49,045,489 $49,961,499 $50,895,829
Grand Total
Community Infrastructure 24,088,200 24,051,375 22,472,793 16,037,168 15,389,602 15,652,694
Contaminated Sites 15,000 - - - - -
Education 36,447,400 34,064,381 34,854,111 26,336,193 26,827,917 27,329,475
Housing 41,363,100 28,406,203 28,734,639 28,875,844 29,019,873 29,166,782
Water and Sewer 46,529,700 42,833,419 27,506,237 28,070,628 29,480,980 28,738,660
Grand Total $148,443,400 $129,355,378 $113,567,779 $99,319,833 $100,718,371 $100,887,610

The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.

Alberta Region

Breakdown of planned spending 2011-2012: (Vote 10 Only)
Major Capital Projects  
Education Facilities $14,121,122
Water & Sewer $4,262,610
Contaminated Sites $0
Community Infrastructure $8,568,589
Minor Capital – formula driven (including housing) $26,425,827
Minor Capital - projects < $1.5 million $10,448,420
Infrastructure O&M $60,764,086
Total (FNIIP) - Vote 10 $124,590,654

Breakdown of Planned Spending for Vote 10 in 2011-2012

A chart showing the Alberta breakdown of planned spending for Vote 10 in 2011-2012.

Text description of this chart is available on a separate page.

Regional Snapshot
First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) 56 Projects $37,357,301
First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) 62 Projects $48,562,812
Infrastructure Investment per Capita
(On-Reserve Registered Indian Population as of Dec. 31, 2010)
68,394 People $1,822

Regional Practices - Minor Capital

While major capital is distributed from the regional office on a per-project basis, the regional office typically requires First Nations to contribute a portion of minor capital funding to major capital projects. The regional office conducts annual meetings with First Nations to review the use of previous and ongoing capital funding. Housing is included in funding agreements at the beginning of the year and is distributed to First Nations based on an assessment of progress on a case-by-case basis. Minor capital funding is distributed upon receiving reports as well as scopes of work for expenditures from First Nations (except in the case of multi-year agreements where allocations are in First Nations' core budgets). Minor capital is not automatically included in First Nations base funding agreements (except for multi-year), but is included when and if targets in progress reports are met and a scope of work is agreed to.

Highlights - Fiscal Year 2011-2012

Alberta First Nations Technical Services Advisory Group (TSAG) - Connectivity project
Connectivity Project 1
Connectivity Project (photo provided by Alberta Regional Office)

Connectivity Project 2
Connectivity Project (photo provided by Alberta Regional Office)

The Alberta SuperNet was built to connect public institutions across the province to a high broadband network in both urban and rural areas and offers a variety of services including high speed internet access. The superNet also allows rural communities the same access to high speed internet as urban communities.

Administration buildings and water treatment plants are two very important facilities in our First Nation communities and these buildings were not connected to the Alberta SuperNet. This underlies a disparity between Provincial and First Nation communities.

A three year connectivity project was approved under the First Nation Infrastructure Fund (FNIF). All First nations will receive fibre optic cabling and/or wireless high speed connections for the administration buildings and water treatment plants.

The funding of $5,780,159 was approved over a three year period: $1,600,000 in 2010/11, $1,700,000 in 2011/12 and $2,400,000 in 2012/13. Work on this project has proceeded quicker that anticipated and TSAG has undertaken to complete the entire project in two years versus the original three year funding plan. To this end, Alberta Region is attempting to fast track the project funding to completely facilitate the early completion of this very worthwhile project in fiscal year 2011/2012.

Stoney Tribe - Gas Tax Fund School

The original Morley community K4-K12 school was constructed in 1986. Since the initial construction there has been the addition of a gymnasium and portable space, as well as mechanical and electrical upgrades. The school suffered from overcrowding and health and safety issues.

Through the Building Canada Plan - Gas Tax Fund, the department was able to secure funding in the order of $22.2 million for this project. The scope of the project includes the construction of a new K4-6 school with a projected school size of 4100 m2 to accommodate 552 students and the retrofitting of the existing school facility to accommodate the high school students.

Construction of the new Morley School is underway with a scheduled completion date of June 30, 2011. The modernization and renovation of the existing school is estimated to be completed in August 2012.

Alberta Summary
Project Category Previous Year
(Planned Amount)
Planned Spending
Current Year
2011-2012
Year +1
2012-2013
Year +2
2013-2014
Year +3
2014-2015
Year +4
2015-2016
Major Capital Projects
Community Infrastructure 8,024,884 8,568,589 1,500,000 - - -
Contaminated Sites 0 - - - - -
Education 30,751,054 14,121,122 2,585,064 - - -
Housing 1,250,000 - - - - -
Water and Sewer 21,441,887 4,262,610 - - - -
Sub-Total (Major) $61,467,825 $26,952,321 $4,085,064 - - -
Minor Capital Projects
Community Infrastructure 19,576,452 12,338,184 14,028,331 9,172,684 9,172,684 9,172,684
Contaminated Sites 457,600 50,060 - - - -
Education 7,539,454 1,132,425 882,425 882,425 882,425 882,425
Housing 24,744,687 16,370,718 16,370,718 16,370,718 16,370,718 16,370,718
Water and Sewer 10,847,698 6,982,860 - - - -
Sub-Total (Minor) $63,165,891 $36,874,247 $31,281,474 $26,425,827 $26,425,827 $26,425,827
Total Capital (Major & Minor)
Community Infrastructure 27,601,336 20,906,773 15,528,331 9,172,684 9,172,684 9,172,684
Contaminated Sites 457,600 50,060 - - - -
Education 38,290,508 15,253,547 3,467,489 882,425 882,425 882,425
Housing 25,994,687 16,370,718 16,370,718 16,370,718 16,370,718 16,370,718
Water and Sewer 32,289,585 11,245,470 - - - -
Total (Minor & Major) $124,633,716 $63,826,568 $35,366,538 $26,425,827 $26,425,827 $26,425,827
Operations & Maintenance
Community Infrastructure 19,675,610 27,039,046 27,367,095 27,701,708 28,043,012 28,391,143
Contaminated Sites 0 - - - - -
Education 10,845,282 17,284,386 17,505,340 17,730,713 17,960,594 18,195,072
Housing 155,300 73,393 73,393 73,393 73,393 73,393
Water and Sewer 12,520,033 16,367,260 11,632,984 11,744,180 11,857,600 11,973,288
Sub-Total (O&M) $43,196,225 $60,764,086 $56,578,813 $57,249,994 $57,934,599 $58,632,897
Grand Total
Community Infrastructure 47,276,946 47,945,819 42,895,427 36,874,392 37,215,697 37,563,828
Contaminated Sites 457,600 50,060 - - - -
Education 49,135,790 32,537,934 20,972,830 18,613,139 18,843,019 19,077,498
Housing 26,149,987 16,444,111 16,444,111 16,444,111 16,444,111 16,444,111
Water and Sewer 44,809,618 27,612,730 11,632,984 11,744,180 11,857,600 11,973,288
Grand Total $167,829,941 $124,590,654 $91,945,351 $83,675,822 $84,360,427 $85,058,724

The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.

British Columbia Region

Breakdown of planned spending 2011-2012: (Vote 10 Only)
Major Capital Projects  
Education Facilities $8,075,193
Water & Sewer $28,711,238
Contaminated Sites $90,000
Community Infrastructure $3,202,500
Minor Capital – formula driven (including housing) $12,629,158
Minor Capital - projects < $1.5 million $25,413,994
Infrastructure O&M $62,866,422
Total (FNIIP) - Vote 10 $140,988,505

Breakdown of Planned Spending for Vote 10 in 2011-2012

A chart showing the British Columbia breakdown of planned spending for Vote 10 in 2011-2012.

Text description of this chart is available on a separate page.

Regional Snapshot
First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) 151 Projects $65,492,925
First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) 224 Projects $227,969,372
Infrastructure Investment per Capita
(On-Reserve Registered Indian Population as of Dec. 31, 2010)
61,147 People $2,306

Regional Practices - Minor Capital

Only First Nations in multi-year agreements receive minor/core capital (approximately 24% of First Nations in British Columbia and 10% of the regional capital budget). Remaining funding is grouped with the total capital budget and is allocated by project on the basis of need for infrastructure and housing. The regional office engages First Nations in setting allocation policies and priorities through a Joint First Nations/AANDC Capital Policy Committee. Sectoral budgets are established to address regional priorities. All First Nations are required to submit five-year capital plans which are matched with national priorities (using the Priority Ranking system). Lower priority projects may not be included in the regional capital plan due to limited funds. Capital contributions are only made to First Nations that are up-to-date in their reporting on previously-funded projects, and a compliance monitoring process for reporting is in place (established through the joint First Nations/AANDC committee).

Highlights - Fiscal Year 2011-2012

Chemainus First Nation - New Secondary School
construction of the new Stua'ate Lelum Secondary School
Construction of the new Stua'ate Lelum Secondary School (photo provided by BC region)

The new stand alone Stua'ate Lelum Secondary School project at Chemainus First Nation is currently under construction with a November 2011 projected completion date. This 3080 m2 facility will accommodate 114 students from Grade 7 to 12 and will replace the existing school which consisted of a converted restaurant and several portables.

The new school will include various green initiatives such as a geothermal heating system. With construction occurring last fall, currently half of the $9,223,247 (total project cost) has been expended including a contribution from the First Nation to enable additional space beyond what the Department's School Space Accommodation Standard permits.

This new facility will provide a positive impact on both the Chemainus First Nation community and surrounding communities by providing a safe and healthy environment which will enhance educational outcomes.

Kwadacha First Nation - Water Distribution and Road Re-Construction

The current system is dated and is in need of replacement as it is constantly breaking down resulting in interruptions in water services. Over the last few years, there have been numerous emergency repairs required to the system resulting in unmanageable maintenance costs.

The new water distribution and road re-construction project for Kwadacha First Nation consists of the construction of approximately 3,625 meters of new water mains, 2,300 meters of new service pipe, three tie-ins to the remaining existing system, installation of 19 fire hydrants, drilling of a third water supply well and road restoration to applicable standards. The total project cost is $5,745,373 with the First Nation contributing $300,000 towards the project.

This project will benefit the entire community with a population of 272 living in 58 houses. This project will allow for fewer interruptions in services, a reduction in emergency repairs and a greater ability to manage maintenance costs, which all contribute to a healthy and vibrant community.

Williams Lake First Nation - Water Improvement Project

The Williams Lake Water Improvement Project carries a total project cost of $4,867,620. The existing water system was inadequate in both water quantity and water quality needed to meet the needs of approximately 300 people living on-reserve. The community currently has 88 houses, seven public buildings including an administration office, gym, education centre, church, lumber mill, fire hall and carpentry shop.

The project includes the tie-in of two recently drilled wells, the construction of a new water treatment plant, and a new reservoir supply main. The new treatment plant will include chlorination system for disinfection and filtration systems for manganese and arsenic removal. The new treatment plant will also be equipped with a Supervisory Control and Data Acquisition (SCADA) monitoring system which will allow remote monitoring and troubleshooting of any issue including water quality.

The community has been on a boil water advisory since 2006 and it is anticipated the new system will significantly improve the conditions of the drinking water and allow for continued population growth.

British Columbia Summary
Project Category Previous Year
(Planned Amount)
Planned Spending
Current Year
2011-2012
Year +1
2012-2013
Year +2
2013-2014
Year +3
2014-2015
Year +4
2015-2016
Major Capital Projects
Community Infrastructure 6,844,386 3,202,500 8,260,000 900,000 900,000 900,000
Contaminated Sites 11,672,500 90,000 90,000 90,000 - -
Education 27,755,722 8,075,193 4,000,000 3,936,920 - -
Housing 0 - - - - -
Water and Sewer 46,847,809 28,711,238 24,987,325 22,637,577 26,582,552 24,293,840
Sub-Total (Major) $93,120,417 $40,078,931 $37,337,325 $27,564,497 $27,482,552 $25,193,840
Minor Capital Projects
Community Infrastructure 14,878,960 18,875,405 14,096,949 13,195,154 13,057,655 11,500,217
Contaminated Sites 8,327,500 440,000 140,000 140,000 150,000 -
Education 2,287,893 699,700 1,870,000 1,899,550 2,000,000 2,000,000
Housing 28,917,001 11,436,802 11,436,802 11,436,802 11,436,802 11,436,802
Water and Sewer 6,594,950 6,591,245 3,509,395 3,107,000 3,250,000 4,834,285
Sub-Total (Minor) $61,006,304 $38,043,152 $31,053,146 $29,778,506 $29,894,457 $29,771,304
Total Capital (Major & Minor)
Community Infrastructure 21,723,346 22,077,905 22,356,949 14,095,154 13,957,655 12,400,217
Contaminated Sites 20,000,000 530,000 230,000 230,000 150,000 -
Education 30,043,615 8,774,893 5,870,000 5,836,470 2,000,000 2,000,000
Housing 28,917,001 11,436,802 11,436,802 11,436,802 11,436,802 11,436,802
Water and Sewer 53,442,759 35,302,483 28,496,720 25,744,577 29,832,552 29,128,125
Total (Minor & Major) $154,126,721 $78,122,083 $68,390,471 $57,343,003 $57,377,009 $54,965,144
Operations & Maintenance
Community Infrastructure 25,293,333 31,275,467 31,275,467 31,275,467 31,275,467 31,275,467
Contaminated Sites 0 - - - - -
Education 9,785,231 10,077,554 10,077,554 10,077,554 10,077,554 10,077,554
Housing 0 - - - - -
Water and Sewer 22,596,983 21,513,401 14,253,401 14,253,401 14,253,401 14,253,401
Sub-Total (O&M) $57,675,547 $62,866,422 $55,606,422 $55,606,422 $55,606,422 $55,606,422
Grand Total
Community Infrastructure 47,016,679 53,353,372 53,632,416 45,370,621 45,233,122 43,675,684
Contaminated Sites 20,000,000 530,000 230,000 230,000 150,000 -
Education 39,828,846 18,852,447 15,947,554 15,914,024 12,077,554 12,077,554
Housing 28,917,001 11,436,802 11,436,802 11,436,802 11,436,802 11,436,802
Water and Sewer 76,039,742 56,815,884 42,750,121 39,997,978 44,085,953 43,381,526
Grand Total $211,802,268 $140,988,505 $123,996,893 $112,949,425 $112,983,431 $110,571,566

The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.

Yukon Region

Breakdown of planned spending 2011-2012: (Vote 10 Only)
Major Capital Projects  
Education Facilities $0
Water & Sewer $425,000
Contaminated Sites $0
Community Infrastructure $0
Minor Capital – formula driven (including housing) $2,787,080
Minor Capital - projects < $1.5 million $3,288,180
Infrastructure O&M $2,373,748
Total (FNIIP) - Vote 10 $8,874,008

Breakdown of Planned Spending for Vote 10 in 2011-2012

A chart showing the Yukon breakdown of planned spending for Vote 10 in 2011-2012.

Text description of this chart is available on a separate page.

Regional Snapshot
First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) 26 Projects $3,713,180
First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) 36 Projects $6,876,680
Infrastructure Investment per Capita
(On-Reserve Registered Indian Population as of Dec. 31, 2010)
3,959 People $2,242

Regional Practices - Minor Capital

Allocation Methodology for the Indian Act First Nations "A-Base" is based on a 1993 decision, agreed upon by Yukon First Nation Leadership and AANDC. The guiding principle for the methodology is fair, equitable and non-political, consistent from year to year, thereby increasing stability in funding. This methodology provides a base which Yukon First Nations can use to encourage long-term planning. The allocation is designed to account for community differences, specifically for remoteness and population.

Yukon Region uses the five year capital plans provided by the First Nations to prioritize projects using the National Priority Ranking System, Level of Service Standards, National and Regional Practices as well as the Asset Condition Reporting System Assessments to help in identify projects for "targeted funding". Yukon Region encourages the First Nations to do some Asset Condition Reporting System projects based on the assessment on a yearly basis. Also, housing, road, water, wastewater and subdivision projects are identified in the First Nation's five year plans to assist in the maintenance of the community assets and overall community development. Yukon Region uses both multi-year type allocation and single year agreement with Terms and Conditions depending on the type of project being funded.

Highlights - Fiscal Year 2011-2012

construction of Water Distribution System & Service Connection at White River First Nation
Construction of Water Distribution System & Service Connection at White River First Nation (photo provided by EBA Engineering)
White River First Nation - Water Delivery System Expansion

In 2002, White River First Nation was deemed a "high risk' community due to the fact that the community water systems at that time did not have any means of disinfection. In addition to the disinfection, several existing wells were not properly constructed putting the community at further risk. The White River First Nation Water Project has proceeded in addressing these concerns since 2004.

Two new community systems (System 1 and System 2) were designed in 2006 and constructed in 2007-2008 to replace three existing community systems that were in disrepair.

Only houses previously connected to a "community system" or with poor water quality were connected to the distribution system when it was constructed. This new phase of the project will connect the remaining 8 houses, and make some design changes to the two treatment plant systems to help temper water correctly and provide on-line chlorine analysers. This will complete the vision of providing clean safe drinking water to all people in the community and begin to focus their resources on other projects to improve their community. The anticipated cost of this project is $600,000.

Circuit Rider & Water Treatment Plant (WTP) Operators performing routine maintenance -  Taku River Tlingit WTP
Circuit Rider & Water Treatment Plant (WTP) Operators performing routine maintenance - Taku River Tlingit WTP (photo provided by FCS Engineering)
Strategic Maintenance Management Plans (White River, Taku River, Tlingit, Liard and Dease River First Nations)

Maintenance management planning and process implementation is important in promoting vibrant and healthy first nation communities. Implementing strategic maintenance processes will enhance the First Nations ability for early detection of potential issues, and will allow for adequate time to repair or replace components of a system or community building with minimal impact to the community.

The objective of this project is to develop improved maintenance management process for four of Yukon Region's Indian Act communities and will cost approximately $332,000.

Yukon Summary
Project Category Previous Year
(Planned Amount)
Planned Spending
Current Year
2011-2012
Year +1
2012-2013
Year +2
2013-2014
Year +3
2014-2015
Year +4
2015-2016
Major Capital Projects
Community Infrastructure 0 - - - - -
Contaminated Sites 0 - - - - -
Education 0 - - - - -
Housing 405,000 - - - - -
Water and Sewer 1,664,000 425,000 - - - -
Sub-Total (Major) $2,069,000 $425,000 - - - -
Minor Capital Projects
Community Infrastructure 2,142,000 757,194 878,000 964,749 983,000 1,437,779
Contaminated Sites 0 - - - - -
Education 30,000 25,500 - - - -
Housing 1,609,000 1,940,886 2,026,994 1,868,258 1,978,007 1,513,258
Water and Sewer 510,000 3,351,680 3,079,000 825,000 20,000 20,000
Sub-Total (Minor) $4,291,000 $6,075,260 $5,983,994 $3,658,007 $2,981,007 $2,971,037
Total Capital (Major & Minor)
Community Infrastructure 2,142,000 757,194 878,000 964,749 983,000 1,437,779
Contaminated Sites 0 - - - - -
Education 30,000 25,000 - - - -
Housing 2,014,000 1,940,886 2,026,994 1,868,258 1,978,007 1,513,258
Water and Sewer 2,174,000 3,776,680 3,079,000 825,000 20,000 20,000
Total (Minor & Major) $6,360,000 $6,500,260 $5,983,994 $3,658,007 $2,981,007 $2,971,037
Operations & Maintenance
Community Infrastructure 1,217,000 899,910 917,908 936,266 954,992 954,992
Contaminated Sites 0 - - - - -
Education 0 - - - - -
Housing 0 - - - - -
Water and Sewer 2,110,000 1,473,838 1,034,115 1,054,797 1,075,893 1,075,893
Sub-Total (O&M) $3,327,000 $2,373,748 $1,952,023 $1,991,063 $2,030,885 $2,030,885
Grand Total
Community Infrastructure 3,359,000 1,657,104 1,795,908 1,901,015 1,937,992 2,392,771
Contaminated Sites 0 - - - - -
Education 30,000 25,500 - - - -
Housing 2,014,000 1,940,886 2,026,994 1,868,258 1,978,007 1,513,258
Water and Sewer 4,284,000 5,250,518 4,113,115 1,879,797 1,095,893 1,095,893
Grand Total $9,687,000 $8,874,008 $7,936,017 $5,649,070 $5,011,892 $5,001,922

The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.






Appendix B - National Priority Ranking Framework

Background

The Department has a consistent and transparent ranking system to address the most pressing needs in First Nation communities.

The department is committed to the following priorities, listed in order of importance, over the next five years:

  1. Protecting and maintaining the life cycle of existing assets, with an emphasis on health and safety;
  2. Mitigating health and safety risks through existing and new assets;
  3. Addressing the backlog regarding water and sewage systems under Capital and Facilities Maintenance activities; and
  4. Investing in other priorities, including investments in sustainable communities (e.g., housing, electrification, roads, educational facilities and community buildings) and investments in community assets to resolve claims or self-government agreements.

Development of the Priority Framework

AANDC regional offices employ a ranking system as a normal course of business in developing capital plans, as demand historically exceeds available funding resources. The National Priority Framework was designed to align existing regional processes (at the highest level) with departmental priorities, to enable reporting and demonstrate progress in a consistent manner.

Use of the Priority Matrix

Regions are requested to:

  1. Classify all major and minor capital projects to a "best fit" within the matrix areas using definitions in the Project Grid, and
  2. Enter the priority code (i.e. A-2) in the companion reporting spreadsheets.

In this way the Department rolls-up funding allocations to the national priorities by asset category. The objective is to demonstrate allocation to the highest priorities as regions see fit, however, pending direction from the allocation methodologies study it may be necessary to set funding levels or targets for the priority areas. The Department may also wish to roll-up unfunded projects in each priority area as a way to demonstrate where the needs reside and how they may shift over time.

Figure 1: National Priority1 Funding Evaluation and Measurement Matrix

The National Priority Funding Evaluation and Measurement Matrix

Text description of this chart is available on a separate page.

Notes:

  1. Priority ranking excludes emergency projects that may occur from time to time
  2. Contaminated Sites refer to holdings south of 60. Refer to Northern Contaminated Sites Work plan for contaminated sites north of 60.

Definitions

Program Activity - Categories "A" to "D"
Protection of Health & Safety and Assets

North/South Custodial Assets (A):
Maintenance projects required to protect the asset and would mitigate the identified high-risk health and safety issues.

Water/Sewer (B), Education (C), Community Infrastructure (D):
Assets require upgrading or replacement to meet appropriate standards. Maintenance projects to address significant risk to health and safety: 1) classified as Group 2 Projects resulting from Asset Condition Reporting System inspections; and/or 2) to address high and medium risks as identified in the AANDC May 2003 National Assessment of Water and Wastewater Systems in First Nations Communities. These projects are to be recorded and tracked for completion in the departmental Capital Asset Management System.

Health and Safety Improvements

North/South Custodial Assets (A), Water/Sewer (B), Education (C), Community Infrastructure (D):
Upgrades of existing assets, new construction / acquisition projects to mitigate an identified significant risk to health and safety.

Recapitalization / Major Maintenance

North/South Custodial Assets (A), Water/Sewer (B), Education (C), Community Infrastructure (D):
Projects required to extend the useful operating life of a facility or asset, or to maintain the original service level of the asset.

Growth - Need Less Than Two Years

North/South Custodial Assets (A), Water/Sewer (B), Education (C), Community Infrastructure (D):
Anticipated community growth requires new construction / expansion / procurement of assets to maintain the level of service standards within a timeframe of less than two years.

Growth - Need After Two Years

North/South Custodial Assets (A) Water/Sewer (B), Education (C), Community Infrastructure (D):
Anticipated community growth requires new construction / expansion / procurement of assets to maintain the level of service standards within a timeframe of greater than two years.

Program Activity - Category "E" (Contaminated Sites)

Note: Remediation/risk management includes monitoring

National Contaminated Sites Classification System (NCSCS) Class 1
Assessment, remediation/risk management of all NCSCS Class 1 contaminated sites on a priority basis to avert risk to community health and safety and water sources in accordance with the departmental Contaminated Sites Management policy.

NCSCS Class 2
Assessment, remediation/risk management of all NCSCS Class 2 contaminated sites on a priority basis to avert risk to community health and safety in accordance with the departmental Contaminated Sites Management policy.

NCSCS Class 3
Assessment, remediation/risk management of all NCSCS Class 3 contaminated sites on a cost efficiency basis.

Program Activity - Category "F" (Housing)

Renovation
Projects required to correct what could be an unsafe condition to the occupants or projects beyond routine maintenance to extend the useful lifespan of the house

New Construction
Construction of dwelling units to address the community's housing need.

Operation and Maintenance:
Routine maintenance and activities to preserve the housing portfolio.

AANDC Capital Asset Funding Categories

Custodial Assets: Administration buildings, vehicles, machinery and equipment required to deliver programs to First Nations, Inuit, and Northern communities.

Water / Sewer: Assets that comprise the distribution / collection system and assets required in the treatment and disposal process including major equipment, vehicles, machinery and buildings.

Education Facilities: Schools, staff residences (teacherages), student residences, temporary facilities associated with delivering the educational program in the community.

Community Infrastructure: Assets and systems not already specified above - including operative, administrative, utility and recreational buildings; solid waste vehicles, dumps and transfer stations; community roads and bridges; electrical power supply and distribution; fire-fighting vehicles and supporting buildings; and fuel tanks and distribution systems.

Contaminated Sites: Sites requiring assessment, remediation / risk management to protect the health and safety as well as the environment of communities.

Housing: Funding to assist in community housing services i.e., the construction, maintenance and management of the community housing portfolio.

Project Grid

Note: The following is not an exhaustive list of project activities, but are examples provided to assist in categorizing potential projects.

Custodial Assets
(A-1)
  • Major Maintenance of assets to avoid immediate risk to health and safety of staff or public
  • Major Maintenance of assets to avoid immediate risk of contamination of environment
(A-2)
  • Action required to meet health and safety legislative requirements (Canadian Environmental Protection Act, Canadian Labour Code)
  • Imminent risk to health and safety of staff or public
  • Imminent risk of contamination of environment
(A-3)
  • Major repair to improve / protect integrity of asset or replacement of asset
  • Significantly improve asset integrity / utility through repair or replacement
  • Improve condition / operating cost of asset through repair or replacement
(A-4) (A-5)
  • Maintain program operations which could be seriously hindered due to serious asset defects or unserviceable assets
  • Maintain operational efficiency of program operations
  • Enhance operations to meet future demands
Water and Wastewater Assets
(B-1)
  • Repairs/upgrades/replacements to deal with imminent health and safety risks arising from the community systems as identified in Asset Condition Ranking System inspections and others means (e.g. the National Assessment noted above), including legislative / regulatory requirements and potential violations (i.e. Fisheries Act). Water source protection is included.
  • Water unsatisfactory with respect to microbiological or physical/chemical quality based on health considerations noted in "Guidelines for Canadian Drinking Water Quality".
  • Wastewater systems posing potential medium to high risks that could negatively impact wastewater effluent quality, including legislative / regulatory requirements and potential violations (i.e. Fishery Act).
(B-2)
  • Water system does not provide fire protection capacity (flow & pressure) and there is multiple life loss risk and/or high property value risks
  • Water quantity is insufficient to meet residential demand
(B-3)
  • Reconstruction / Major repairs required to restore asset
(B-4)
  • Water / sewage systems (residential sub-division development including supporting infrastructure)
  • Water quality is unsatisfactory based on "aesthetic objectives" as defined in "Guidelines for Canadian Drinking Water Quality"
(B-5)
  • Improvements to groundwater system are required to provide a back-up supply for existing houses
  • Improvements to existing system are recommended but not mandatory
  • Growth needed for water / sewer systems greater than two years
Educational Facilities
(C-1)
  • Renovations or improvements to existing facilities are needed to deal with serious operational problems with immediate health and safety risks (i.e. identified in Asset Condition Ranking System inspections)
  • Health and safety code violations
(C-2)
  • Severe overcrowding requires an expansion to facility
(C-3)
  • Reconstruction / replacement of On-Reserve facilities.
  • Minor code conformance (infractions)
(C-4) (C-5)
  • New facilities on-reserve
Community Infrastructure
(D-1)

Fuel Tank Systems

  • Improvements to existing system to meet legislative/regulatory compliance.

Fire safety systems

  • Imminent health and safety risks as identified in Asset Condition Ranking System inspections.
  • Provision of file protection capabilities critical to safety of the community, either through the use of purchased fire protection services or by acquiring apparatus and fire protection equipment.

Solid waste

  • Improvements to existing system are needed to deal with serious operational problems, safety problems and/or system reliability
  • Solid waste facility presents an imminent threat to public health or safety, or to the environment

Electrification

  • Required to assure integrity of water supply and/or sewage collection and treatment

Transportation

  • Bridge/high boardwalk where it is the sole access to reserve - imminent failure if not repaired/replaced
  • Serious community access hazards which impair accessibility of community for emergencies
(D-2)

Fire Safety Systems

  • Improvements to equipment needed to deal with serious operational problems, safety problems and/or system reliability

Solid waste

  • Solid waste facility presents a significant threat to public health or safety, or to the environment

Electrification

  • Unsafe facilities causing a threat to the public

Transportation

  • Road-hazardous geometric problems
  • Bridge/high boardwalk - structural problems
  • Bridge/high boardwalk - capacity [size] problems
(D-3)

Fire safety systems

  • Reconstruction/replacement
  • Major repairs to assets/equipment

Solid waste

  • Reconstruction/replacement
  • Major repairs to assets/equipment

Electrification

  • Reconstruction/replacement
  • Major repairs to assets/equipment

Transportation

  • Bridge/high boardwalk - reconstruction - reached end of service life
  • Road reconstruction - serious structural problems
  • Major road repairs to restore asset - significant structure problems
(D-4) (D-5)

Admin Buildings

  • Renovations or improvements to existing facilities / assets are needed to deal with serious operational problems.

Fire safety systems

  • Improvements to existing system are recommended but not mandatory

Solid waste

  • Improvements to existing system are recommended but not mandatory

Electrification

  • Improvements to existing system are recommended but not mandatory

Transportation

  • Improvements to existing system are recommended but not mandatory
Contaminated Sites
(E-1)

National Contaminated Sites Classification System Class 1

  • Sites with an NCSCS score equal or greater than 70 (i.e.: NCSCS Class 1) where remediation/ risk-management is currently underway and further remediation/risk management is required.
  • Sites identified where a Phase I or Phase II environmental site assessments (ESA) is required or where existing sites (Class I - Insufficient evidence) require a follow up to confirm site classification.
  • Sites with an NCSCS score equal or greater than 70 (i.e.: NCSCS Class 1) where the Phase II ESA has been completed and remediation/risk management is required but has yet to be initiated.
(E-2)

National Contaminated Sites Classification System Class 2

  • Sites with an NCSCS score equal to 50 but less than 70 (i.e.: NCSCS Class 2 sites) where remediation/risk-management is currently underway and further remediation/risk management is required.
  • Sites with an NCSCS score equal to 50 but less than 70 (i.e.: NCSCS Class 2) where the Phase II ESA has been completed and remediation/risk management is required but has yet to be initiated.
(E-3)

National Contaminated Sites Classification System Class 3

  • Sites with an NCSCS score equal to 37 or less (i.e.: NCSCS Class 3 sites) where a Phase II ESA has been completed, remediation/risk management is required and there are cost efficiencies to include this site in conjunction with other Class 1 or 2 remediation/risk management projects currently underway.
Housing
(F-1)

Renovation

Repairing unsafe conditions could include:

  • Unsafe outside steps or stairways in need of replacement;
  • Interior structural problems (e.g. falling material from ceilings);
  • Defective or unsafe plumbing/electrical wiring/heating;
  • Mould contamination

Extending the useful lifespan of the house could include:

  • Roof replacement
  • Structural and foundation repair
  • Energy efficiency improvements (e.g. doors, windows, insulation levels)
  • Replacement of furnace/heating unit
(F-2)

New Construction

  • Addition to existing dwelling units or construction of new dwelling units to address overcrowding.
(F-3)

Operation & Maintenance

  • Routine maintenance to protect housing structure, envelope, interior
  • Fire Prevention - e.g. provision and installation of smoke detectors, extinguishers
  • Funding for housing authority to review/inspect housing stock, including routine fire safety compliance checks
  • Payment of insurance policy premiums
(F-4)

New Construction to address population growth in less than 2 years

  • Addition to existing dwelling units or construction of new dwelling units to address population growth.
(F-5)

New Construction to address population growth after 2 years

  • Addition to existing dwelling units or construction of new dwelling units to address population growth.





Glossary of Acronyms and Terms

Acronym
In Full
AANDC
Aboriginal Affairs and Northern Development Canada
ACRS
Asset Condition Reporting System
BCGTF
Building Canada Plan - Gas Tax Fund
CEAP
Canada's Economic Action Plan
CFMP
Capital Facilities & Maintenance Program
CFO
Chief Financial Officer
CMHC
Canada Mortgage and Housing Corporation
CRTP
Circuit Rider Training Program
FNIF
First Nation Infrastructure Fund
FNIIP
First Nations Infrastructure Investment Plan
FNWWAP
First Nations Water and Wastewater Action Plan
MCF
Management Control Framework
NPRF
National Priority Ranking Framework
TEC
Total Estimated Cost

Term
Definition
Canada First Nations Funding Agreements (CFNFAs)
Multi-year arrangements where First Nations have the authority to reallocate Major Capital and O&M funding between priorities, provided that minimum program terms and conditions are met.
Comprehensive Funding Agreements (CFAs)
Single-year arrangements tied to individual activities.
Major Capital
Funding allocated for specific proposal-driven construction, acquisition, renovation or significant repair projects valued above $1.5 million.
Minor Capital
Can either be formula-based or proposal-driven funding. This funding is typically allocated for on reserve housing and for construction, acquisition, renovation and/or repair projects of community infrastructure valued below $1.5 million.
Operations & Maintenance (O&M)
Formula-based funding specifically allocated for the on-going operation and maintenance of community Infrastructure assets as well as First Nation Training.
A-Base or Base Budget
A recurring set of funds provided to a department at the onset of each budget period. The base budget is used to keep the department functioning, and is derived from the previous year's spending and adjustments such as inflation. It is not designed to fund special projects.





Footnotes:

  1. Established by using a formula that considers multiple variables such as: population, geographic remoteness, and actual costs of operating and maintenance assets. (return to source paragraph)
  2. 2011-2012 Main Estimates provided by Chief Financial Officer Sector. (return to source paragraph)
  3. The majority of the $163 million (planned) reallocation to other programs is targeted to cover potential shortfalls in core program areas such as education and social. This reallocation from the CFMP occurs at the regional level. It is expected that the actual reallocation will be substantially lower, which can be verified when Public Accounts are finalized for the 2011-2012 fiscal year. (return to source paragraph)
  4. Community Infrastructure captures multiple capital asset funding categories. These categories include but are not limited to roads & bridges, electrification, connectivity, fuel tanks, green energy, solid waste and fire protection. (return to source paragraph)
  5. At the time the FNIIP was produced, these projects were not yet assessed for priority. Priority will be assigned once projects are approved for funding. (return to source paragraph)
  6. Projects are a combination of both formula-driven and project-driven as presented in diagram on Page 8. (return to source paragraph)