Date: June 2011
ISSN: 1927-2200
QS: QS-2013-010-EE-A1
PDF Version (1010 Kb, 54 Pages)
Help on accessing documents in PDF format can be obtained on the help page.
The First Nations Infrastructure Investment Plan (FNIIP) is developed annually by Aboriginal Affairs & Northern Development Canada (AANDC) in partnership with First Nations to strategically plan investments in the short and medium term to support an economically stable future for First Nations in Canada.
The following document provides an overview of investments being planned in line with the FNIIP through the Capital Facilities & Maintenance Program. It includes priority investment areas, provides a rationale to how the FNIIP is developed and outlines details of specific eligible projects for investment. The FNIIP is a planning document. Not all projects identified in the plan will receive the level of funding identified in a particular year. Regional staff work with First Nations throughout the year to support projects on a prioritized basis with available resources. Adjustments to the plan occur throughout the year and into future years as community, project and financial circumstances change. Information presented in this report captures planned projects as of March 2011. A glossary of Acronyms and Terms is presented at the end of this report to assist readers as required.
The mandate of the Capital Facilities & Maintenance Program is to provide financial and advisory assistance to First Nations in the development of basic public infrastructure which is essential for healthy, safe and sustainable communities. The Capital Facilities & Maintenance Program is part of the Department's broader Strategic Outcome "The Economy" which is to support the economic well-being and prosperity of First Nations, Inuit and Métis people.
The Capital Facilities & Maintenance Program objectives are to assist First Nations in making capital and facility operational and maintenance plans and investment decisions that:
The Capital Facilities & Maintenance Program is intended to assist First Nations in the planning, design, construction, operation, maintenance, repair, renovation, and replacement of community infrastructure and facilities including the following asset categories:
Capital projects are subject to the Department's National Priority Ranking Framework (see Appendix B). The Framework's priorities are defined by the following Program Activity Categories:
AANDC promotes the use of full life-cycle costing analysis when approving capital construction projects. This type of analysis allows for the consideration of all the associated costs (e.g. for design, construction, operations and maintenance, insurance, and major renovations) of the proposed infrastructure throughout its entire life cycle. This type of information is used to make comparisons between proposed options (e.g. building an expensive installation with low operating and maintenance costs versus a less-expensive facility with higher operating and maintenance costs) and determine the most cost-effective option in the short, medium, and long term. This exercise is also useful in determining the funding levels required from the First Nation in future years for the operations and maintenance of the proposed infrastructure.
During an asset's service life, AANDC provides funding support to First Nations to pay for operations and maintenance of funded infrastructure assets. AANDC also encourages good asset management practices by requiring that First Nations implement maintenance management plans for various types of major capital assets. In addition, AANDC tracks the ongoing condition of assets through inspections carried out every three years or yearly under the Asset Condition Reporting System and ensures the repairs and maintenance work needed to preserve an asset is being done.
As part of its efforts to encourage good asset management, AANDC funds a mentoring program called the Circuit Rider Training Program (CRTP). The Circuit Rider Training Program provides mentoring support to operators of water and wastewater systems. This program has helped improve the operation of assets as well as to help First Nations exploit the full service life of the assets.
Resource allocations for the Capital Facilities & Maintenance Program (CFMP) occur on an annual basis from headquarters to regions and then to First Nations to assist in the development and maintenance of basic community infrastructure. The CFMP budget is divided into the following three funding streams:
Major capital projects, especially in education, as well as water and sewer facilities, are funded primarily by targeted programs such as the Building Canada Plan - Gas Tax Fund, and First Nations Water and Wastewater Action Plan. As those funds are distributed on a per-project basis, variances can be observed between regional allocations.
However, it is in the treatment of minor capital that the widest variance in regional practices can be observed. Some differences can be accounted for by the type of funding relationships between different AANDC regions and First Nations, as well as factors like number of First Nations, geography, number and types of assets owned by First Nations in a particular region.
Under the Management Control Framework for the Capital Facilities & Maintenance Program, AANDC uses FNIIPs for capital planning. This process aims to improve resource management and increase accountability through better capital planning. An effective process depends on:
The FNIIP planning process reflects the existing approval authorities and roles and responsibilities set out in the Management Control Framework.
The National FNIIP is a five year plan summarizing eight Regional FNIIPs that have been developed in collaboration with First Nation communities. The National FNIIP identifies specific investments per region, and identifies national trends in infrastructure investment and Capital Facilities & Maintenance Program expenditures.
The FNIIP planning process is designed around three linked plans that feed into one-another: a community level plan, detailing infrastructure needs; a regional plan, planning out program expenditures; and a national plan, that provides a strategic overview of First Nations infrastructure needs and Capital Facilities & Maintenance Program investment.
FNIIPs are five-year capital investment plans created by each First Nation community which detail infrastructure needs and plans. As set out in the Recipient Reporting Guide, an updated FNIIP must be prepared each year before capital funds are released to First Nations. The community level FNIIP is based upon mandatory reporting requirements prescribed by the Recipient Reporting Guide (Asset Condition Reporting System Projects Annual Report, Changes in Capital Assets Annual Report, Fire Losses Annual Report). It is developed by communities with the support of the AANDC Regional Offices and then submitted for validation and incorporation into the Regional FNIIP.
It is AANDC's goal to ensure every community develops their own five year infrastructure plan based on a life-cycle approach. However, at this point in time, several regions have not instituted this requirement as part of their planning process, given that numerous First Nations within their regions neither have the expertise nor the capacity to develop their own five year plans. In such instances, AANDC officials at the regional level support and work with communities to develop infrastructure plans and identify their infrastructure priorities, and capacity is increasing in many areas.
Regional FNIIPs are the key planning and reporting tools used by both regions and headquarters throughout the year. They are developed after validating proposed expenditures in First Nations Infrastructure Investment Plans against program criteria, and then planning allocation of available resources to the highest priorities. Regional FNIIP projects are prioritized using the National Priority Ranking Framework and other priority requirements attached to targeted funds (e.g. First Nations Infrastructure Fund). Higher priority projects are placed in the earlier years of the plan, while lower priority projects are placed in the later years, or beyond the current five-year plan. This, as well as the uncertainty with regards to the renewal of targeted funds, explains why some regions do not have planned investments for all categories, especially major capital projects, beyond the current fiscal year (see Appendix A). Regional offices provide updates of their plan for use at the regional and national level. See Appendix B for the National Priority Ranking Framework.
The National FNIIP is a compilation of all eight Regional FNIIPs. It presents national data and analysis of Capital Facilities & Maintenance Program capital planning in a summary document for senior management review. The National FNIIP is reviewed by the departmental Operations Committee made up of AANDC senior management annually, as per the roles and responsibilities set out in the Management Control Framework for the Capital Facilities & Maintenance Program.
For 2011-2012 the Parliamentary Budget Allocation for Capital Facilities & Maintenance Program (CFMP) (Vote 1, Vote 10) is: $1.212 Billion [Note 2]
| Total FNIIP (Planned Vote 10) | $965,903,230 |
| Salaries & Operation and Maintenance (Vote 1) | $34,965,000 |
| Sub-Total | $1,000,598,230 |
| Other items included in Main Estimates | |
| Planned Reallocation [Note 3] | $162,981,994 |
| Unallocated First Nation Water & Wastewater Action Plan (Vote 10) | $39,675,950 |
| Other (Vote 10) | $136,000 |
| Climate Change Strategy (Vote 1) | $80,266 |
| Statutory | $3,979,366 |
| Total | $1,207,451,806 |
| Major Capital Projects | |
|---|---|
| Education Facilities | $66,477,040 |
| Water & Sewer | $132,067,362 |
| Contaminated Sites | $5,373,986 |
| Community Infrastructure [Note 4] | $60,995,887 |
| Minor Capital – formula driven (including housing) | $201,558,605 |
| Minor Capital - projects < $1.5 million | $101,561,235 |
| Infrastructure O&M | $397,869,114 |
| Total | $965,903,230 |
National breakdown of planned spending for Vote 10 in 2011-2012

Text description of this chart is available on a separate page.
| Current Year | Five Year Aggregate | ||
|---|---|---|---|
| # of Projects | Total Value | # of Projects | Total Value |
| 626 | $366,426,070 | 816 | $1,177,200,667 |
Graph 1: National Breakdown by Funding Type

Text description of this chart is available on a separate page.
Note: Minor Capital Formula has only been identified for current year to provide some context into what the typical split is between proposal and formula-driven minor capital in any given year. The split is not available for future years as AANDC Regions were not requested to provide this level of detail beyond current year. The minor capital category beyond current year (2012-2013 to 2015-2016) all includes both the proposal and formula-driven minor capital.
Graph 2: National Breakdown by Funding Source

Text description of this chart is available on a separate page.
Graphs 1 and 2 were developed using the data provided in the 2011-2012 Regional FNIIPs and illustrate the breakdown of planned spending (vote 10) by funding type (Major, Minor and Operations & Maintenance) (Graph 1) and funding source (Graph 2). Of the total planned allocations for 2011-2012 fiscal year, major capital funding represents 27%, minor capital 32% and O&M 41%. For the 2011-2012 fiscal year, minor capital has been separated into two categories. These categories represent two distinct allocation vehicles. Of the total planned allocation for minor capital funding, 66% is allocated under minor capital formula-driven, while 33% is allocated as minor capital proposal-driven (See Graph 1). Refer to Table 1 for total planned funding.
The spike in capital funding levels in 2011-2012 and the smaller one in 2012-2013, as shown on Graph 1 & 2, are a result of additional investments from Building Canada Fund - Gas Tax Fund extension (BCGTF), First Nations Infrastructure Fund (FNIF) and the First Nations Water and Wastewater Action Plan (FNWWAP). These initiatives provide funding primarily in the areas of major capital projects for education and water and sewer facilities. Furthermore, a significant portion of FNWWAP funding is allocated to address operation and maintenance of water and wastewater facilities and for the training and certification of water and wastewater operators. FNIF also contributes to the spike seen in 2011-2012 and 2012-2013 in the areas of solid waste, energy systems, local roads and bridges, planning and skills development, and connectivity. The FNIF portion shown separately in Graph 2 is a combination of funds approved for 5 years commencing in 2008-2009 and a second phase of funding approved in 2009-2010 for four years and is sourced through the Building Canada Fund in collaboration with Infrastructure Canada. As part of the first phase of funding, AANDC has responsibility for also making a contribution from the Capital Facilities & Maintenance Program. AANDC's planned contribution has been included in the category of A-Base funding and totals approximately $1.8 million in 2011-2012. In total $69 million is planned to be spent under the First Nations Infrastructure Fund in 2011-2012.
While there is a peak in available funding for 2011-2012, there is a noticeable reduction of total infrastructure funding in subsequent years. This decline is largely the result of targeted programs which are scheduled to expire over the next two years with no identified renewal opportunities at this point in time: First Nations Water and Wastewater Action Plan (March 31, 2012), Building Canada Fund - Gas Tax Fund extension (March 31, 2012) and First Nations Infrastructure Fund (March 31, 2013).
There is a slight decline in total funding levels when comparing 2011-2012 major capital and the A-Base funding levels to future years. This is due to a number of factors including over programming of projects and the tendency of developing infrastructure investment plans that emphasize the alignment between projects and current fiscal year resources only, as well as the shifting of projects to the subsequent fiscal years when resource availability has been exhausted.
(Major & Minor Proposal Based Projects Only)
Graph 3: National Funding by Asset Class

Text description of this chart is available on a separate page.
The largest portions of planned projects are in the asset areas of water and sewer at 45%, community infrastructure at 30% (which includes projects such as roads & bridges, electrification, fuel tanks and fire protection) and education facilities representing a total of 20% of planned projects. These three asset classes receiving the majority of funding is a result of targeted initiatives such as FNWWAP for water and wastewater projects, BCGTF for school projects and FNIF which targets areas of community infrastructure such as green energy, roads & bridges, solid waste and connectivity.
Graph 4: Funding by National Priority Ranking

Text description of this chart is available on a separate page.
Priority 1 projects represent 34.1% of all planned projects being funded this year. Priority 1 can only be used for water or wastewater projects. These projects can either be upgrades to existing systems or new constructions to deal with imminent health and safety risks, water or wastewater quality or legislative/regulatory requirements. Priority 2 projects represent the largest portion of all planned projects at 62.2%. Unlike Priority 1, Priority 2 projects include all asset classes and cover all program activity categories. This explains the high concentration of Priority 2 projects. Included in this category are recent targeted funding initiatives such as BCGTF, which address new construction in education and FNIF in the area of community infrastructure. Priority 3 and 4 projects represent 2.8% and 0.4% of planned expenditures respectively. These priorities mainly focus on anticipated growth and need. The investments needed to effectively address Priority 1 and 2 projects limit the number of projects that can be funded in the Priority 3 and 4 categories. This distribution further highlights the limitations on current levels of CFMP funding. (Refer to Appendix B for the National Priority Ranking Framework).
For the purpose of the FNIIP, an investment opportunity is defined as a project that meets program criteria, which may or may not have previously received funding but is not scheduled to receive funding within the time period covered by the current plan (2011-2012 to 2015-2016). The 2011-2012 FNIIP identified 2,214 capital projects valued at approximately $3 billion that regions have recorded in their FNIIPs as investment opportunities. These investment opportunities can be further broken down by asset category and National Priority Ranking.
Graph 5: Capital funding requests by asset class

Text description of this chart is available on a separate page.
Graph 5 demonstrates the overall need by major asset category. Through the capital planning process, AANDC regions have identified that the highest demand for infrastructure projects is in the asset category of water and sewer at 48%. Community infrastructure projects have been identified as the second asset category most in demand at 29%, followed by education facilities 15%, housing 6% and contaminated sites 2%. This breakdown is based upon information reported by regions and the national priority ranking framework.
Graph 6: Capital funding requests by priority ranking

Text description of this chart is available on a separate page.
Graph 6 illustrates that Priority 1 projects represent 21% of the total future investment opportunities as identified by regions. Priority 1 projects can either be repairs/upgrades or new construction of water or wastewater facilities to deal with imminent health and safety risks, water quality and legislative/regulatory requirements. Priority 2 projects represent 46% of all unfunded projects. Priority 2 projects include all asset classes and cover almost all program activity categories which explain its high percentage. Priority 3 and 4 projects represent a combined total of 17% of investment opportunities. These priorities mainly focus on anticipated growth and need. As Priority 1 & 2 represents a total of 67%, the likelihood of Priority 3 & 4 projects receiving funding is minimal. Priority Unassigned [Note 5].
2011-2012 Planned Acquisition and Construction of Facilities (Major & Minor Capital Projects and Operations & Maintenance)
| Project Category | Previous Year (Planned Amount) |
Planned Spending | ||||
|---|---|---|---|---|---|---|
| Current Year 2011-2012 |
Year +1 2012-2013 |
Year +2 2013-2014 |
Year +3 2014-2015 |
Year +4 2015-2016 |
||
| Major Capital Projects | ||||||
| Community Infrastructure | 51,849,798 | 60,795,725 | 36,437,100 | 11,860,000 | 6,781,100 | 5,835,000 |
| Contaminated Sites | 33,296,189 | 5,373,986 | 250,019 | 246,000 | - | - |
| Education | 157,935,266 | 66,477,040 | 32,698,767 | 16,319,820 | 11,915,200 | 16,305,400 |
| Housing | 1,655,000 | 200,162 | - | - | - | - |
| Water and Sewer | 231,738,475 | 132,067,362 | 97,950,612 | 85,955,340 | 91,594,352 | 81,261,366 |
| Sub-Total (Major) | $476,474,728 | $264,914,275 | $167,336,498 | $114,381,160 | $110,290,652 | $103,401,766 |
| Minor Capital Projects [Note 6] | ||||||
| Community Infrastructure | 122,389,003 | 116,905,569 | 88,814,599 | 76,321,379 | 71,894,154 | 64,320,929 |
| Contaminated Sites | 14,391,221 | 4,733,311 | 4,854,130 | 669,220 | 931,871 | 350,000 |
| Education | 20,017,413 | 11,914,297 | 6,789,132 | 6,886,082 | 7,123,832 | 6,825,932 |
| Housing | 184,991,731 | 126,857,405 | 125,976,186 | 126,278,795 | 129,315,096 | 106,534,544 |
| Water and Sewer | 44,411,134 | 42,709,258 | 20,260,768 | 23,013,318 | 18,441,684 | 16,877,936 |
| Sub-Total (Minor) | $386,200,502 | $303,119,840 | $246,694,815 | $233,168,795 | $227,706,638 | $194,909,341 |
| Total Capital (Major & Minor) | ||||||
| Community Infrastructure | 174,238,801 | 177,701,294 | 125,251,699 | 88,181,379 | 78,675,254 | 70,155,929 |
| Contaminated Sites | 47,687,410 | 10,107,297 | 5,104,149 | 915,220 | 931,871 | 350,000 |
| Education | 177,952,679 | 78,391,337 | 39,487,899 | 23,205,902 | 19,039,032 | 23,131,332 |
| Housing | 186,646,731 | 127,057,567 | 125,976,186 | 126,278,795 | 129,315,096 | 106,534,544 |
| Water and Sewer | 276,149,609 | 174,776,620 | 118,211,380 | 108,968,658 | 110,036,036 | 98,139,302 |
| Total (Minor & Major) | $862,675,230 | $568,034,116 | $414,031,313 | $347,549,955 | $337,997,290 | $298,311,107 |
| Operations & Maintenance | ||||||
| Community Infrastructure | 132,706,445 | 151,485,380 | 152,297,245 | 153,123,991 | 153,965,855 | 154,803,877 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 101,202,029 | 116,957,640 | 117,652,424 | 118,361,079 | 119,083,884 | 119,821,120 |
| Housing | 13,527,006 | 1,164,667 | 1,164,767 | 1,164,767 | 1,164,867 | 1,164,967 |
| Water and Sewer | 104,535,546 | 128,261,427 | 81,644,458 | 81,940,027 | 82,241,495 | 82,527,463 |
| Sub-Total (O&M) | $351,971,026 | $397,869,114 | $352,758,893 | $354,589,864 | $356,456,100 | $358,317,428 |
| Grand Total | ||||||
| Community Infrastructure | 306,945,246 | 329,186,674 | 277,548,944 | 241,305,371 | 232,641,109 | 224,959,807 |
| Contaminated Sites | 47,687,410 | 10,107,297 | 5,104,149 | 915,220 | 931,871 | 350,000 |
| Education | 279,154,708 | 195,348,978 | 157,140,323 | 141,566,982 | 138,122,916 | 142,952,453 |
| Housing | 200,173,737 | 128,222,234 | 127,140,953 | 127,443,562 | 130,479,963 | 107,699,511 |
| Water and Sewer | 380,685,155 | 303,038,047 | 199,855,838 | 190,908,685 | 192,277,531 | 180,666,765 |
| Grand Total | $1,214,646,256 | $965,903,230 | $766,790,207 | $702,139,819 | $694,453,390 | $656,628,535 |
The dashes in the above National Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.
| Major Capital Projects | |
|---|---|
| Education Facilities | $5,860,000 |
| Water & Sewer | $4,071,000 |
| Contaminated Sites | $0 |
| Community Infrastructure | $2,309,000 |
| Minor Capital – formula driven (including housing) | $8,543,000 |
| Minor Capital - projects < $1.5 million | $2,101,000 |
| Infrastructure O&M | $18,981,000 |
| Total (FNIIP) - Vote 10 | $41,865,000 |
Breakdown of Planned Spending for Vote 10 in 2011-2012

Text description of this chart is available on a separate page.
| First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) | 21 Projects | $14,341,000 |
| First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) | 32 Projects | $51,053,000 |
| Infrastructure Investment per Capita (On-Reserve Registered Indian Population as of Dec. 31, 2010) |
21,824 People | $1,918 |
Approximately 80% of total capital (core and non-core) is included in First Nations agreements, of which the majority is used for housing. There is low or no monitoring of this funding. For instance, there is no requirement for First Nations to spend minor capital on Asset Condition Reporting System or FNIIP priorities.

This project is the top priority on the Atlantic regional priority list for new school construction. The existing school asset was constructed in 1975 and is 1994 m2 serving kindergarten to Grade five. Since the initial construction there has been no major upgrade or retrofit. In April 2008, the Band Council relocated the students to a temporary facility as the existing school no longer met the standards for indoor air quality, access or emergency efficiency. In addition, there were concerns with the ability of the existing school to accommodate the educational requirements of the growing community in terms of space and function.
Through the Building Canada Plan - Gas Tax Fund, the department was able to secure funding in the order of $10.3 million for the community to proceed with the construction of a new education facility. The scope of the work for this project includes the planning, design and construction of a 2490m2 kindergarten to Grade 8 facility as well as the demolition of the existing structure.
This new school which is anticipated to be completed in September 2011 will provide a safe and quality learning environment for the children of Tobique First Nation. It will limit the need for children to attend school off reserve and ultimately enhance the communities' educational outcomes.

Pabineau First Nation - Water Reservoir, Treatment and Distribution System Upgrades
Pabineau First Nation has an on reserve registered population of 101. Their current water source is from individual wells which are not sustainable from either a quantity or quality perspective. The community is currently under boil water advisory which cannot be effectively addressed under their current system. The new project will see the construction of a new reservoir, a new treatment system and new distribution lines. This project will cost $6 million over the next 5 years and will significantly improve the conditions of the drinking water and allow the community to focus their efforts on other priorities.
Pictou Landing has an on reserve registered population of 452 people. Their current treatment facility has insufficient capacity, is obsolete and does not meet the needs of the community. This project is considered to be essential to meet the significantly increasing demand the community has and will allow for continued growth. Notwithstanding the various health & safety issues, this new plant will address any possible environmental issues that the current facility may present to the community. The new treatment plant will cost $1.6M and the work is expected to be fully completed in the current fiscal year.
| Project Category | Previous Year (Planned Amount) |
Planned Spending | ||||
|---|---|---|---|---|---|---|
| Current Year 2011-2012 |
Year +1 2012-2013 |
Year +2 2013-2014 |
Year +3 2014-2015 |
Year +4 2015-2016 |
||
| Major Capital Projects | ||||||
| Community Infrastructure | 500,000 | 2,309,000 | 5,631,000 | 5,000,000 | 400,000 | - |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 8,599,056 | 5,860,000 | - | - | - | - |
| Housing | 0 | - | - | - | - | - |
| Water and Sewer | 14,696,000 | 4,071,000 | 3,471,000 | 2,382,000 | 1,297,000 | 2,723,000 |
| Sub-Total (Major) | $23,795,056 | $12,240,000 | $9,102,000 | $7,382,000 | $1,697,000 | $2,723,000 |
| Minor Capital Projects | ||||||
| Community Infrastructure | 2,076,248 | 2,728,300 | 2,735,300 | 1,154,300 | 854,300 | 854,300 |
| Contaminated Sites | 25,000 | 65,000 | - | - | - | - |
| Education | 0 | - | - | - | - | - |
| Housing | 12,081,230 | 7,688,700 | 7,688,700 | 7,688,700 | 7,688,700 | 7,688,700 |
| Water and Sewer | 1,297,000 | 162,000 | 130,000 | 1,171,000 | 2,156,000 | 1,130,000 |
| Sub-Total (Minor) | $15,479,478 | $10,644,000 | $10,554,000 | $10,014,000 | $10,699,000 | $9,673,000 |
| Total Capital (Major & Minor) | ||||||
| Community Infrastructure | 2,576,248 | 5,037,300 | 8,366,300 | 6,154,300 | 1,254,300 | 854,300 |
| Contaminated Sites | 25,000 | 65,000 | - | - | - | - |
| Education | 8,599,056 | 5,860,000 | - | - | - | - |
| Housing | 12,081,230 | 7,688,700 | 7,688,700 | 7,688,700 | 7,688,700 | 7,688,700 |
| Water and Sewer | 15,993,000 | 4,233,000 | 3,601,000 | 3,553,000 | 3,453,000 | 3,853,000 |
| Total (Minor & Major) | $39,274,534 | $22,884,000 | $19,656,000 | $17,396,000 | $12,396,000 | $12,396,000 |
| Operations & Maintenance | ||||||
| Community Infrastructure | 3,324,321 | 10,368,600 | 10,368,600 | 10,368,600 | 10,368,600 | 10,368,600 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 0 | 3,150,880 | 3,150,880 | 3,150,880 | 3,150,880 | 3,150,880 |
| Housing | 12,278,887 | 50,000 | 50,000 | 50,000 | 50,000 | 50,000 |
| Water and Sewer | 936,000 | 5,411,520 | 4,726,520 | 4,726,520 | 4,726,520 | 4,726,520 |
| Sub-Total (O&M) | $16,539,208 | $18,981,000 | $18,296,000 | $18,296,000 | $18,296,000 | $18,296,000 |
| Grand Total | ||||||
| Community Infrastructure | 5,900,569 | 15,405,900 | 18,734,900 | 16,522,900 | 11,622,900 | 11,222,900 |
| Contaminated Sites | 25,000 | 65,000 | - | - | - | - |
| Education | 8,599,056 | 9,010,880 | 3,150,880 | 3,150,880 | 3,150,880 | 3,150,880 |
| Housing | 24,360,117 | 7,738,700 | 7,738,700 | 7,738,700 | 7,738,700 | 7,738,700 |
| Water and Sewer | 16,929,000 | 9,644,520 | 8,327,520 | 8,279,520 | 8,179,520 | 8,579,520 |
| Grand Total | $55,813,742 | $41,865,000 | $37,952,000 | $35,692,000 | $30,692,000 | $30,692,000 |
The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.
| Major Capital Projects | |
|---|---|
| Education Facilities | $4,824,200 |
| Water & Sewer | $8,562,600 |
| Contaminated Sites | $0 |
| Community Infrastructure | $12,071,200 |
| Minor Capital – formula driven (including housing) | $21,274,400 |
| Minor Capital - projects < $1.5 million | $7,236,500 |
| Infrastructure O&M | $29,909,300 |
| Total (FNIIP) - Vote 10 | $83,878,200 |
Breakdown of Planned Spending for Vote 10 in 2011-2012

Text description of this chart is available on a separate page.
| First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) | 38 Projects | $32,694,500 |
| First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) | 51 Projects | $127,223,100 |
| Infrastructure Investment per Capita (On-Reserve Registered Indian Population as of Dec. 31, 2010) |
52,367 People | $1,601 |
About 60% of capital is under core and minor capital funding for First Nations. Funding levels are determined by formula, with housing being a principal driver of funding. First Nations are expected to prioritize projects for minor capital such as Asset Condition Reporting System projects, lot servicing, and housing. The regional office receives annual capital plan updates from First Nations that tell which projects were initiated and/or completed by First Nations as well as the cost and source of funds. This process assists in tracking how minor capital funding is used by First Nations.
Long Point First Nation is planning the construction of a new school at a total estimated cost of $7.5 million. This project is a result of health and safety issues with the existing education facility. In 2007, based on a report tabled by the First Nation, Health Canada supported the Council's decision to vacate the school due to the presence of mould. Since then, temporary facilities were erected in the existing gymnasium and security and safety measures were put in place. The condition of the existing school combined with the costs of renovating it lead to a common understanding that a new facility would be built. School population is not a factor in this project since overall school population remained constant and the new facility will provide the same level of service.

Uashat First Nation is currently undertaking a community development project valued at $7.5 million. The Department, through the First Nation Infrastructure Fund (FNIF), is providing $3.3 million for the construction of an access bridge as part of the overall project.
The community had no more land base available for lot development to accommodate the rapid growth rate; therefore an addition to its existing reserve was necessary. The area that was selected presented a number of challenges such as special requirements from the town of Sept-Îles, access needs to be secured by building a bridge over a small creek and services (water & sewer) to hook up to the existing network. Once access to the new area is completed, the First Nation will be able to proceed with future development.
Natashquan First Nation will benefit from a major wastewater treatment plant rehabilitation project that is currently underway. This project is a result of the limited capacity of the existing treatment plant and the requirements to increase this capacity that will meet the present and future needs of the community in light of significant population growth.
The total estimated cost of the project is $3 million. The project is currently at the feasibility stage and various options such as a third lagoon or a new technology called bio-reactor are being considered. This project also presents a challenge as the existing treatment facility is located in an area sensitive to shoreline erosion.
| Project Category | Previous Year (Planned Amount) |
Planned Spending | ||||
|---|---|---|---|---|---|---|
| Current Year 2011-2012 |
Year +1 2012-2013 |
Year +2 2013-2014 |
Year +3 2014-2015 |
Year +4 2015-2016 |
||
| Major Capital Projects | ||||||
| Community Infrastructure | 1,483,700 | 12,071,200 | 1,407,500 | - | - | - |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 13,771,300 | 4,824,200 | 6,416,400 | 382,900 | 1,915,200 | 6,305,400 |
| Housing | 0 | - | - | - | - | - |
| Water and Sewer | 34,996,100 | 8,562,600 | 6,381,500 | 12,635,900 | 11,312,200 | 7,633,400 |
| Sub-Total (Major) | $50,251,100 | $25,458,000 | $14,205,400 | $13,018,800 | $13,227,400 | $13,938,800 |
| Minor Capital Projects | ||||||
| Community Infrastructure | 13,275,100 | 14,290,000 | 212,625,100 | 11,809,000 | 11,310,200 | 11,311,500 |
| Contaminated Sites | 344,800 | 600,000 | 350,000 | 350,000 | 350,000 | 350,000 |
| Education | 640,000 | 425,600 | 425,600 | 425,700 | 425,800 | 425,900 |
| Housing | 15,967,600 | 7,105,900 | 6,876,600 | 6,877,500 | 7,378,500 | 6,879,300 |
| Water and Sewer | 5,399,800 | 6,089,400 | 2,696,500 | 2,681,900 | 2,682,400 | 2,682,900 |
| Sub-Total (Minor) | $35,627,300 | $28,510,900 | $22,973,800 | $22,144,100 | $22,146,900 | $21,649,600 |
| Total Capital (Major & Minor) | ||||||
| Community Infrastructure | 14,758,800 | 26,361,200 | 14,032,600 | 11,809,000 | 11,310,200 | 11,311,500 |
| Contaminated Sites | 344,800 | 600,000 | 350,000 | 350,000 | 350,000 | 350,000 |
| Education | 14,411,300 | 5,249,800 | 6,842,000 | 808,600 | 2,341,000 | 6,731,300 |
| Housing | 15,967,600 | 7,105,900 | 6,876,600 | 6,877,500 | 7,378,500 | 6,879,300 |
| Water and Sewer | 40,395,900 | 14,652,000 | 9,078,000 | 15,317,800 | 13,994,600 | 10,316,300 |
| Total (Minor & Major) | $85,878,400 | $53,968,900 | $37,179,200 | $35,162,900 | $35,374,300 | $35,588,400 |
| Operations & Maintenance | ||||||
| Community Infrastructure | 11,981,300 | 12,015,200 | 12,233,100 | 12,454,000 | 12,677,900 | 12,904,700 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 9,773,800 | 9,858,900 | 9,860,100 | 9,861,300 | 9,862,500 | 9,863,700 |
| Housing | 620,500 | 500,800 | 500,900 | 500,900 | 501,100 | 501,100 |
| Water and Sewer | 7,489,000 | 7,534,400 | 4,909,900 | 4,910,500 | 4,911,100 | 4,911,700 |
| Sub-Total (O&M) | $29,864,600 | $29,909,300 | $27,504,000 | $27,726,700 | $27,952,500 | $28,181,200 |
| Grand Total | ||||||
| Community Infrastructure | 26,740,100 | 38,376,400 | 26,265,700 | 24,263,000 | 23,988,100 | 24,216,200 |
| Contaminated Sites | 344,800 | 600,000 | 350,000 | 350,000 | 350,000 | 350,000 |
| Education | 24,185,100 | 15,108,700 | 16,702,100 | 10,669,900 | 12,203,500 | 16,595,000 |
| Housing | 16,588,100 | 7,606,700 | 7,377,500 | 7,378,400 | 7,879,500 | 7,380,400 |
| Water and Sewer | 47,884,900 | 22,186,400 | 13,987,900 | 20,228,300 | 18,905,700 | 15,228,000 |
| Grand Total | $115,743,000 | $83,878,200 | $64,683,200 | $62,889,600 | $63,326,800 | $63,769,600 |
The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.
| Major Capital Projects | |
|---|---|
| Education Facilities | $16,047,925 |
| Water & Sewer | $28,657,314 |
| Contaminated Sites | $2,228,986 |
| Community Infrastructure | $8,180,298 |
| Minor Capital – formula driven (including housing) | $53,501,603 |
| Minor Capital - projects < $1.5 million | $29,589,241 |
| Infrastructure O&M | $108,517,545 |
| Total (FNIIP) - Vote 10 | $246,722,912 |
Breakdown of Planned Spending for Vote 10 in 2011-2012

Text description of this chart is available on a separate page.
| First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) | 185 Projects | $84,703,764 |
| First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) | 206 Projects | $134,681,703 |
| Infrastructure Investment per Capita (On-Reserve Registered Indian Population as of Dec. 31, 2010) |
88,420 People | $2,790 |
Funding levels for minor capital are determined by formula. Minor capital is provided to First Nations to support infrastructure, education facilities, and on reserve housing. Minor capital activities that are supported by this funding are identified by First Nations using the Five Year Capital Plan - Annual Update report. Funding is provided as a Flexible Transfer Payment, the expenditure of which is identified by First Nations annual audited financial statements.

Wasauksing First Nation is a rural community with approximately 475 members living on reserve. The elders' complex, the administration complex which includes the daycare, the school, the health centre, the fire hall and 33 houses are all currently being serviced by the existing water treatment plant. This water treatment plant (constructed in 2003) was erected as an interim measure to address water various water issues. To date, the plant, still in use, no longer meets the current water standards and is operating beyond full capacity.
In addition to the water treatment plant, there are 21 homes being services from several communal drilled groundwater wells that do not meet the current regulations and an additional 10 homes drawing water directly from the lake which are under boil water advisories.
The new water system will service the existing 33 houses, the elders' complex and the administration complex as well as provide rural water delivery to approximately 81 additional houses that are beyond the main core. The other houses will be on future waterline extensions. The water truck along with the installation of cisterns for homes in the rural areas will provide a potable water supply to the majority of the community.
In addition to improving the quality of the drinking water, the new distribution system will provide adequate fire water flows and pressures to all main facilities of the community and improved the access to water for the houses beyond the limited of the distribution system in the event of fire. The current total estimated cost of this project is $17 million.

The new stand alone Obishikokaang School Project at Lac Seul First Nation is substantially complete and has been occupied since September 2010. The Department is providing funding to the community this year to address any minor deficiencies and for the school site development.
The Department provided funding from the Building Canada Plan - Gas Tax Fund to support a 1545 m2 facility. The community contributed $575,000 towards the project which allowed for an additional 498 m2outside the Department's School Space Accommodation Standard. The school is sized to accommodate up to 166 students (K4 to Grade 8) and cost approximately $7 million.
Students from Lac Seul were previously attending a provincially operated school in Hudson, Ontario approximately 13 km from the reserve. It was anticipated that the school board was going to close the Hudson school forcing the students from Lac Seul to attend a provincially operated school in Sioux Lookout. This option was considered unacceptable by the community due to the increased travel time and distance. This new facility will provide a positive impact on both the Lac Seul First Nation and surrounding communities by providing a safe and culturally sensitive learning environment.
| Project Category | Previous Year (Planned Amount) |
Planned Spending | ||||
|---|---|---|---|---|---|---|
| Current Year 2011-2012 |
Year +1 2012-2013 |
Year +2 2013-2014 |
Year +3 2014-2015 |
Year +4 2015-2016 |
||
| Major Capital Projects | ||||||
| Community Infrastructure | 17,913,628 | 7,980,136 | 7,044,000 | 1,993,000 | 1,993,000 | 1,993,000 |
| Contaminated Sites | 7,094,289 | 2,228,986 | 160,019 | 156,000 | - | - |
| Education | 36,210,734 | 16,047,925 | 10,697,303 | 12,000,000 | 10,000,000 | 10,000,000 |
| Housing | 0 | 200,162 | - | - | - | - |
| Water and Sewer | 39,659,779 | 28,657,314 | 34,322,987 | 24,498,863 | 23,405,600 | 18,286,126 |
| Sub-Total (Major) | $100,878,430 | $55,114,523 | $52,224,309 | $38,647,863 | $35,398,600 | $30,279,126 |
| Minor Capital Projects | ||||||
| Community Infrastructure | 46,854,207 | 42,452,027 | 24,834,362 | 24,128,130 | 24,128,130 | 24,128,130 |
| Contaminated Sites | 5,221,321 | 3,578,251 | 4,364,130 | 179,220 | 431,871 | - |
| Education | 5,914,062 | 6,353,772 | 2,142,607 | 2,142,607 | 2,142,607 | 2,142,607 |
| Housing | 20,150,277 | 23,421,808 | 23,421,808 | 23,421,808 | 23,421,808 | 23,421,808 |
| Water and Sewer | 8,089,131 | 7,284,986 | 4,476,284 | 3,999,684 | 3,809,058 | 3,809,058 |
| Sub-Total (Minor) | $86,228,998 | $83,090,844 | $59,239,191 | $53,871,449 | $53,933,474 | $53,501,603 |
| Total Capital (Major & Minor) | ||||||
| Community Infrastructure | 64,767,835 | 50,432,163 | 31,878,362 | 26,121,130 | 26,121,130 | 26,121,130 |
| Contaminated Sites | 12,315,610 | 5,807,237 | 4,524,149 | 335,220 | 431,871 | - |
| Education | 42,124,796 | 22,401,697 | 12,839,910 | 14,142,607 | 12,142,607 | 12,142,607 |
| Housing | 20,150,277 | 23,621,970 | 23,421,808 | 23,421,808 | 23,421,808 | 23,421,808 |
| Water and Sewer | 47,748,910 | 35,942,300 | 38,799,271 | 28,498,547 | 27,214,658 | 22,095,184 |
| Total (Minor & Major) | $187,107,428 | $138,205,367 | $111,463,500 | $92,519,312 | $89,332,074 | $83,780,729 |
| Operations & Maintenance | ||||||
| Community Infrastructure | 35,304,060 | 39,226,203 | 39,226,203 | 39,226,203 | 39,226,203 | 39,226,203 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 30,495,822 | 31,763,797 | 31,763,797 | 31,763,797 | 31,763,797 | 31,763,797 |
| Housing | 28,500 | 92,682 | 92,682 | 92,682 | 92,682 | 92,682 |
| Water and Sewer | 21,061,960 | 37,434,863 | 18,893,875 | 18,893,875 | 18,893,875 | 18,893,875 |
| Sub-Total (O&M) | $86,890,342 | $108,517,545 | $89,976,557 | $89,976,557 | $89,976,557 | $89,976,557 |
| Grand Total | ||||||
| Community Infrastructure | 100,071,895 | 89,658,366 | 71,104,565 | 65,347,333 | 65,347,333 | 65,347,333 |
| Contaminated Sites | 12,315,610 | 5,807,237 | 4,524,149 | 335,220 | 431,871 | - |
| Education | 72,620,618 | 54,165,494 | 44,603,707 | 45,906,404 | 43,906,404 | 43,906,404 |
| Housing | 20,178,777 | 23,714,652 | 23,514,490 | 23,514,490 | 23,514,490 | 23,514,490 |
| Water and Sewer | 68,810,870 | 73,377,163 | 57,693,146 | 47,392,422 | 46,108,533 | 40,989,059 |
| Grand Total | $273,997,770 | $246,722,912 | $201,440,057 | $182,495,869 | $179,308,631 | $173,757,286 |
The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.
| Major Capital Projects | |
|---|---|
| Education Facilities | $10,368,000 |
| Water & Sewer | $34,816,100 |
| Contaminated Sites | $3,055,000 |
| Community Infrastructure | $21,604,400 |
| Minor Capital – formula driven (including housing) | $48,251,334 |
| Minor Capital - projects < $1.5 million | $8,593,500 |
| Infrastructure O&M | $62,940,239 |
| Total (FNIIP) - Vote 10 | $189,628,573 |
Breakdown of Planned Spending for Vote 10 in 2011-2012

Text description of this chart is available on a separate page.
| First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) | 51 Projects | $78,437,000 |
| First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) | 76 Projects | $146,310,900 |
| Infrastructure Investment per Capita (On-Reserve Registered Indian Population as of Dec. 31, 2010) |
84,392 People | $2,247 |
Approximately 60% of the total capital budget (including housing) is distributed to First Nations as minor capital distributed on a formula basis. The regional office receives reports from First Nations on tracking the spending of minor capital. For First Nations in multi-year agreements, there is no monitoring of how allocations for minor capital are spent.

St. Theresa Point First Nation is a remote, winter road access community with approximately 3,231 people living on-reserve. The original Pre-Kindergarten to Grade 12 School opened in 1974 and by the mid 1990's reached its design capacity and was overcrowded. The school project to replace the existing school was initiated in 1996 and was to include a Pre-Kindergarten to Grade 4 and Grade 9 to Grade 12 school with a stand alone Grade 5 to Grade 8 school. Due to the cost of the school facilities, the project was broken into two phases.
Phase I of the school project was completed in September 1999 and included the construction of a 3,997 m2 Grade 9 to Grade 12 high school and 19 teachers' residences. Since the completion of Phase I, the original community school was destroyed by fire on May 12, 2004. The kindergarten to Grade 8 students have since been schooled in 14 temporary classrooms located both in the vicinity of the former school and adjacent to the high school.


Phase II of the School Project is currently underway and is receiving funding from the Building Canada Plan - Gas Tax Fund Extension. The project consists of the design and construction of a new 3,382.9 m2 Grade 5 to Grade 8 middle school and a 1,888.8 m2 Kindergarten to Grade 4 addition to the existing high school. The project also consists of the construction of 973 m2 of new teacherages and the conversion of 14 temporary classrooms to teachers' residences. The schools have been designed to accommodate a projected enrolment of 1,150 students. The project is scheduled to be completed in December 2011 with a total project cost of $38 million.
A new aerated lagoon wastewater treatment facility at Long Plain First Nation is currently under construction and scheduled to be completed in the fall of 2011 at a total cost of $10.5 million. The lagoon will service the communities of Long Plain and Dakota Plains and will allow for the decommissioning of the two existing mechanical sewage treatment plants that have been in service since the mid 1990's. This project will provide these communities with wastewater treatment and disposal that will meet their present and future needs in the face of significant growth in population since the original plants were constructed.
An addition to the South Shore Sagkeeng water treatment plant is currently being constructed and the existing North Shore water treatment plant is being renovated and converted to a pumping station. When completed in the summer 2011, the South Shore water treatment plant will produce the potable water requirements for both the South Shore (population approx. 2,500) and the North Shore (population approx. 1,500) communities of the Sagkeeng First Nation. The project cost is $7.4 million.
| Project Category | Previous Year (Planned Amount) |
Planned Spending | ||||
|---|---|---|---|---|---|---|
| Current Year 2011-2012 |
Year +1 2012-2013 |
Year +2 2013-2014 |
Year +3 2014-2015 |
Year +4 2015-2016 |
||
| Major Capital Projects | ||||||
| Community Infrastructure | 14,231,000 | 21,604,400 | 7,723,200 | 3,967,000 | 3,488,100 | 2,942,000 |
| Contaminated Sites | 14,529,400 | 3,055,000 | - | - | - | - |
| Education | 27,017,500 | 10,368,000 | - | - | - | - |
| Housing | 0 | - | - | - | - | - |
| Water and Sewer | 45,534,700 | 34,816,100 | 11,261,100 | 7,948,000 | 11,900,000 | 11,900,000 |
| Sub-Total (Major) | $101,312,600 | $69,843,500 | $18,984,300 | $11,915,000 | $15,388,100 | $14,842,000 |
| Minor Capital Projects | ||||||
| Community Infrastructure | 22,280,236 | 21,103,859 | 16,893,957 | 14,991,862 | 12,388,185 | 5,916,319 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 1,987,004 | 775,000 | 468,500 | 535,800 | 673,000 | 375,000 |
| Housing | 40,418,835 | 30,746,388 | 29,679,925 | 29,999,166 | 32,280,689 | 10,317,176 |
| Water and Sewer | 2,847,255 | 4,219,587 | 4,544,589 | 7,328,734 | 2,624,226 | 741,693 |
| Sub-Total (Minor) | $67,533,330 | $56,844,834 | $51,586,971 | $52,855,562 | $47,966,100 | $17,350,188 |
| Total Capital (Major & Minor) | ||||||
| Community Infrastructure | 36,511,236 | 42,708,259 | 24,617,157 | 18,958,862 | 15,876,285 | 8,858,319 |
| Contaminated Sites | 14,529,400 | 3,055,000 | - | - | - | - |
| Education | 29,004,504 | 11,143,000 | 468,500 | 535,800 | 673,000 | 375,000 |
| Housing | 40,418,835 | 30,746,388 | 29,679,925 | 29,999,166 | 32,280,689 | 10,317,176 |
| Water and Sewer | 48,381,955 | 39,035,687 | 15,805,689 | 15,276,734 | 14,524,226 | 12,641,693 |
| Total (Minor & Major) | $168,845,930 | $126,688,334 | $70,571,271 | $64,770,562 | $63,354,200 | $32,192,188 |
| Operations & Maintenance | ||||||
| Community Infrastructure | 15,980,622 | 16,030,079 | 16,030,079 | 16,030,079 | 16,030,079 | 16,030,079 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 19,303,394 | 20,440,642 | 20,440,642 | 20,440,642 | 20,440,642 | 20,440,642 |
| Housing | 183,819 | 187,792 | 187,792 | 187,792 | 187,792 | 187,792 |
| Water and Sewer | 27,015,370 | 26,281,726 | 18,039,126 | 18,039,126 | 18,039,126 | 18,039,126 |
| Sub-Total (O&M) | $62,483,205 | $62,940,239 | $54,697,639 | $54,697,639 | $54,697,639 | $54,697,639 |
| Grand Total | ||||||
| Community Infrastructure | 52,491,858 | 58,738,338 | 40,647,236 | 34,988,941 | 31,906,364 | 24,888,398 |
| Contaminated Sites | 14,529,400 | 3,055,000 | - | - | - | - |
| Education | 48,307,898 | 31,583,642 | 20,909,142 | 20,976,442 | 21,113,642 | 20,815,642 |
| Housing | 40,602,654 | 30,934,180 | 29,867,717 | 30,186,958 | 32,468,481 | 10,504,968 |
| Water and Sewer | 75,397,325 | 65,317,413 | 33,844,815 | 33,315,860 | 32,563,352 | 30,680,819 |
| Grand Total | $231,329,135 | $189,628,573 | $125,268,910 | $119,468,201 | $118,051,839 | $86,889,827 |
The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.
| Major Capital Projects | |
|---|---|
| Education Facilities | $7,180,600 |
| Water & Sewer | $22,561,500 |
| Contaminated Sites | $0 |
| Community Infrastructure | $5,059,900 |
| Minor Capital – formula driven (including housing) | $28,146,203 |
| Minor Capital - projects < $1.5 million | $14,890,400 |
| Infrastructure O&M | $51,516,775 |
| Total (FNIIP) - Vote 10 | $129,355,378 |
Saskatchewan Breakdown of Planned Spending for Vote 10 in 2011-2012

Text description of this chart is available on a separate page.
| First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) | 98 Projects | $49,692,400 |
| First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) | 129 Projects | $178,523,100 |
| Infrastructure Investment per Capita (On-Reserve Registered Indian Population as of Dec. 31, 2010) |
66,707 People | $1,939 |
Minor capital is split between two areas. The "band-based capital" is allocated on a formula basis and focus on housing, community buildings and fire protection. Funds are distributed to First Nations when the regional office receives progress reports for previously funded projects (based on inspections in the case of housing). First Nations in multi-year agreements receive band-based capital funding as part of their core funding. There is less control over these funds. The second component is for all other projects under $1.5 million, mostly education and water and sewer facilities. Those projects are proposal-driven and are fully funded by AANDC based on the actual project costs.

This project is for a bridge over the Churchill River complete with abutments, immediate approach road works, decking, double lane roadway, and pedestrian walkway.Funded was identified under the First Nation Infrastructure Fund (FNIF). The subdivided area on the Wapachewunak Reserve is almost fully occupied and all economically viable land has been developed for subdivisions. There is no other area available for subdivision development on the Reserve 192D south of the Churchill River at Patuanak. The English River First Nation have initiated a subdivision development plan which will see the immediate construction of between 30 and 50 lots, and the planning for up to 500 lots across the Churchill River, with access via the Willow Heart Bridge across the Churchill River. Future infrastructure development will also include a new lagoon across the Churchill River as the existing lagoon at English River is at capacity.
The design was initiated July 2009 and the project went to tender in March 2010. Construction was started May 2010 and is on schedule for a June/July 2011 completion. Total estimated cost for this project is $8,551,000.
The existing school asset was constructed in 1976 with a high school addition constructed in 1994 bringing the total school size to 4,218 m2 serving kindergarten to grade twelve. Since 2007, four portable classroom units have been located at this site to deal with overcrowding. A life cycle cost study of the existing school determined that the most economical approach was to replace the original 1,492 m2 elementary portion of the school constructed in 1976 with a new 2,157 m2 addition and to carry out renovation on the 1994 facility. The result is a capital project costing $8,906,000 that saw construction initiated in 2010-2011.
Through the Building Canada Plan - Gas Tax Fund, the Department was able to secure funding of $5.8 million for the community to proceed with the construction of the new education facility. The balance of the project cost is being funded from the Capital Facilities and Maintenance Program.
This school addition/renovation project is anticipated to be completed by March 2012 and will provide a safe and quality learning environment for the children of Ahtahkakoop First Nation.
The project consists of upgrading and expanding the treatment, storage and pumping capacity of the school and the core area water treatment plants. The core area water treatment plant will be converted to a re-chlorination and re-distribution booster reservoir with the treatment upgrades being completed at the school water treatment plant. The project includes a source water study, well improvements, and a new distribution line between the school water treatment plant and the core area plant.
Feasibility and design work was completed in 2009-2010 and construction of the project initiated in 2011-2012. The project is currently estimated to cost $6,400,000 and is anticipated to be completed during the 2012-2013 fiscal year. The Poundmaker First Nation currently has an on-reserve population of 750 and the new water treatment plant capacity is designed for a projected 20 year population of 1,355.
| Project Category | Previous Year (Planned Amount) |
Planned Spending | ||||
|---|---|---|---|---|---|---|
| Current Year 2011-2012 |
Year +1 2012-2013 |
Year +2 2013-2014 |
Year +3 2014-2015 |
Year +4 2015-2016 |
||
| Major Capital Projects | ||||||
| Community Infrastructure | 2,852,200 | 5,059,900 | 4,871,400 | - | - | - |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 13,829,900 | 7,180,600 | 9,000,000 | - | - | - |
| Housing | 0 | - | - | - | - | - |
| Water and Sewer | 26,898,200 | 22,561,500 | 17,526,700 | 15,853,000 | 17,097,000 | 16,425,000 |
| Sub-Total (Major) | $43,580,300 | $34,802,000 | $31,398,100 | $15,853,000 | $17,097,000 | $16,425,000 |
| Minor Capital Projects | ||||||
| Community Infrastructure | 1,305,800 | 4,360,600 | 2,722,600 | 905,500 | - | - |
| Contaminated Sites | 15,000 | - | - | - | - | - |
| Education | 1,619,000 | 2,502,300 | 1,000,000 | 1,000,000 | 1,000,000 | 1,000,000 |
| Housing | 41,103,100 | 28,146,203 | 28,474,639 | 28,615,844 | 28,759,873 | 28,906,782 |
| Water and Sewer | 8,825,300 | 8,027,500 | 1,825,000 | 3,900,000 | 3,900,000 | 3,660,000 |
| Sub-Total (Minor) | $52,868,200 | $43,036,603 | $34,022,239 | $34,421,344 | $33,659,873 | $33,566,782 |
| Total Capital (Major & Minor) | ||||||
| Community Infrastructure | 4,158,000 | 9,420,500 | 7,594,000 | 905,500 | - | - |
| Contaminated Sites | 15,000 | - | - | - | - | - |
| Education | 15,448,900 | 9,682,900 | 10,000,000 | 1,000,000 | 1,000,000 | 1,000,000 |
| Housing | 41,103,100 | 28,146,203 | 28,474,639 | 28,615,844 | 28,759,873 | 28,906,782 |
| Water and Sewer | 35,723,500 | 30,589,000 | 19,351,700 | 19,753,000 | 20,997,000 | 20,085,000 |
| Total (Minor & Major) | $96,448,500 | $77,838,603 | $65,420,339 | $50,274,344 | $50,756,873 | $49,991,782 |
| Operations & Maintenance | ||||||
| Community Infrastructure | 19,930,200 | 14,630,875 | 14,878,793 | 15,131,668 | 15,389,602 | 15,652,694 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 20,998,500 | 24,381,481 | 24,854,111 | 25,336,193 | 25,827,917 | 26,329,475 |
| Housing | 260,000 | 260,000 | 260,000 | 260,000 | 260,000 | 260,000 |
| Water and Sewer | 10,806,200 | 12,244,419 | 8,154,537 | 8,317,628 | 8,483,980 | 8,653,660 |
| Sub-Total (O&M) | $51,994,900 | $51,516,775 | $48,147,440 | $49,045,489 | $49,961,499 | $50,895,829 |
| Grand Total | ||||||
| Community Infrastructure | 24,088,200 | 24,051,375 | 22,472,793 | 16,037,168 | 15,389,602 | 15,652,694 |
| Contaminated Sites | 15,000 | - | - | - | - | - |
| Education | 36,447,400 | 34,064,381 | 34,854,111 | 26,336,193 | 26,827,917 | 27,329,475 |
| Housing | 41,363,100 | 28,406,203 | 28,734,639 | 28,875,844 | 29,019,873 | 29,166,782 |
| Water and Sewer | 46,529,700 | 42,833,419 | 27,506,237 | 28,070,628 | 29,480,980 | 28,738,660 |
| Grand Total | $148,443,400 | $129,355,378 | $113,567,779 | $99,319,833 | $100,718,371 | $100,887,610 |
The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.
| Major Capital Projects | |
|---|---|
| Education Facilities | $14,121,122 |
| Water & Sewer | $4,262,610 |
| Contaminated Sites | $0 |
| Community Infrastructure | $8,568,589 |
| Minor Capital – formula driven (including housing) | $26,425,827 |
| Minor Capital - projects < $1.5 million | $10,448,420 |
| Infrastructure O&M | $60,764,086 |
| Total (FNIIP) - Vote 10 | $124,590,654 |
Breakdown of Planned Spending for Vote 10 in 2011-2012

Text description of this chart is available on a separate page.
| First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) | 56 Projects | $37,357,301 |
| First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) | 62 Projects | $48,562,812 |
| Infrastructure Investment per Capita (On-Reserve Registered Indian Population as of Dec. 31, 2010) |
68,394 People | $1,822 |
While major capital is distributed from the regional office on a per-project basis, the regional office typically requires First Nations to contribute a portion of minor capital funding to major capital projects. The regional office conducts annual meetings with First Nations to review the use of previous and ongoing capital funding. Housing is included in funding agreements at the beginning of the year and is distributed to First Nations based on an assessment of progress on a case-by-case basis. Minor capital funding is distributed upon receiving reports as well as scopes of work for expenditures from First Nations (except in the case of multi-year agreements where allocations are in First Nations' core budgets). Minor capital is not automatically included in First Nations base funding agreements (except for multi-year), but is included when and if targets in progress reports are met and a scope of work is agreed to.


The Alberta SuperNet was built to connect public institutions across the province to a high broadband network in both urban and rural areas and offers a variety of services including high speed internet access. The superNet also allows rural communities the same access to high speed internet as urban communities.
Administration buildings and water treatment plants are two very important facilities in our First Nation communities and these buildings were not connected to the Alberta SuperNet. This underlies a disparity between Provincial and First Nation communities.
A three year connectivity project was approved under the First Nation Infrastructure Fund (FNIF). All First nations will receive fibre optic cabling and/or wireless high speed connections for the administration buildings and water treatment plants.
The funding of $5,780,159 was approved over a three year period: $1,600,000 in 2010/11, $1,700,000 in 2011/12 and $2,400,000 in 2012/13. Work on this project has proceeded quicker that anticipated and TSAG has undertaken to complete the entire project in two years versus the original three year funding plan. To this end, Alberta Region is attempting to fast track the project funding to completely facilitate the early completion of this very worthwhile project in fiscal year 2011/2012.
The original Morley community K4-K12 school was constructed in 1986. Since the initial construction there has been the addition of a gymnasium and portable space, as well as mechanical and electrical upgrades. The school suffered from overcrowding and health and safety issues.
Through the Building Canada Plan - Gas Tax Fund, the department was able to secure funding in the order of $22.2 million for this project. The scope of the project includes the construction of a new K4-6 school with a projected school size of 4100 m2 to accommodate 552 students and the retrofitting of the existing school facility to accommodate the high school students.
Construction of the new Morley School is underway with a scheduled completion date of June 30, 2011. The modernization and renovation of the existing school is estimated to be completed in August 2012.
| Project Category | Previous Year (Planned Amount) |
Planned Spending | ||||
|---|---|---|---|---|---|---|
| Current Year 2011-2012 |
Year +1 2012-2013 |
Year +2 2013-2014 |
Year +3 2014-2015 |
Year +4 2015-2016 |
||
| Major Capital Projects | ||||||
| Community Infrastructure | 8,024,884 | 8,568,589 | 1,500,000 | - | - | - |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 30,751,054 | 14,121,122 | 2,585,064 | - | - | - |
| Housing | 1,250,000 | - | - | - | - | - |
| Water and Sewer | 21,441,887 | 4,262,610 | - | - | - | - |
| Sub-Total (Major) | $61,467,825 | $26,952,321 | $4,085,064 | - | - | - |
| Minor Capital Projects | ||||||
| Community Infrastructure | 19,576,452 | 12,338,184 | 14,028,331 | 9,172,684 | 9,172,684 | 9,172,684 |
| Contaminated Sites | 457,600 | 50,060 | - | - | - | - |
| Education | 7,539,454 | 1,132,425 | 882,425 | 882,425 | 882,425 | 882,425 |
| Housing | 24,744,687 | 16,370,718 | 16,370,718 | 16,370,718 | 16,370,718 | 16,370,718 |
| Water and Sewer | 10,847,698 | 6,982,860 | - | - | - | - |
| Sub-Total (Minor) | $63,165,891 | $36,874,247 | $31,281,474 | $26,425,827 | $26,425,827 | $26,425,827 |
| Total Capital (Major & Minor) | ||||||
| Community Infrastructure | 27,601,336 | 20,906,773 | 15,528,331 | 9,172,684 | 9,172,684 | 9,172,684 |
| Contaminated Sites | 457,600 | 50,060 | - | - | - | - |
| Education | 38,290,508 | 15,253,547 | 3,467,489 | 882,425 | 882,425 | 882,425 |
| Housing | 25,994,687 | 16,370,718 | 16,370,718 | 16,370,718 | 16,370,718 | 16,370,718 |
| Water and Sewer | 32,289,585 | 11,245,470 | - | - | - | - |
| Total (Minor & Major) | $124,633,716 | $63,826,568 | $35,366,538 | $26,425,827 | $26,425,827 | $26,425,827 |
| Operations & Maintenance | ||||||
| Community Infrastructure | 19,675,610 | 27,039,046 | 27,367,095 | 27,701,708 | 28,043,012 | 28,391,143 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 10,845,282 | 17,284,386 | 17,505,340 | 17,730,713 | 17,960,594 | 18,195,072 |
| Housing | 155,300 | 73,393 | 73,393 | 73,393 | 73,393 | 73,393 |
| Water and Sewer | 12,520,033 | 16,367,260 | 11,632,984 | 11,744,180 | 11,857,600 | 11,973,288 |
| Sub-Total (O&M) | $43,196,225 | $60,764,086 | $56,578,813 | $57,249,994 | $57,934,599 | $58,632,897 |
| Grand Total | ||||||
| Community Infrastructure | 47,276,946 | 47,945,819 | 42,895,427 | 36,874,392 | 37,215,697 | 37,563,828 |
| Contaminated Sites | 457,600 | 50,060 | - | - | - | - |
| Education | 49,135,790 | 32,537,934 | 20,972,830 | 18,613,139 | 18,843,019 | 19,077,498 |
| Housing | 26,149,987 | 16,444,111 | 16,444,111 | 16,444,111 | 16,444,111 | 16,444,111 |
| Water and Sewer | 44,809,618 | 27,612,730 | 11,632,984 | 11,744,180 | 11,857,600 | 11,973,288 |
| Grand Total | $167,829,941 | $124,590,654 | $91,945,351 | $83,675,822 | $84,360,427 | $85,058,724 |
The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.
| Major Capital Projects | |
|---|---|
| Education Facilities | $8,075,193 |
| Water & Sewer | $28,711,238 |
| Contaminated Sites | $90,000 |
| Community Infrastructure | $3,202,500 |
| Minor Capital – formula driven (including housing) | $12,629,158 |
| Minor Capital - projects < $1.5 million | $25,413,994 |
| Infrastructure O&M | $62,866,422 |
| Total (FNIIP) - Vote 10 | $140,988,505 |
Breakdown of Planned Spending for Vote 10 in 2011-2012

Text description of this chart is available on a separate page.
| First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) | 151 Projects | $65,492,925 |
| First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) | 224 Projects | $227,969,372 |
| Infrastructure Investment per Capita (On-Reserve Registered Indian Population as of Dec. 31, 2010) |
61,147 People | $2,306 |
Only First Nations in multi-year agreements receive minor/core capital (approximately 24% of First Nations in British Columbia and 10% of the regional capital budget). Remaining funding is grouped with the total capital budget and is allocated by project on the basis of need for infrastructure and housing. The regional office engages First Nations in setting allocation policies and priorities through a Joint First Nations/AANDC Capital Policy Committee. Sectoral budgets are established to address regional priorities. All First Nations are required to submit five-year capital plans which are matched with national priorities (using the Priority Ranking system). Lower priority projects may not be included in the regional capital plan due to limited funds. Capital contributions are only made to First Nations that are up-to-date in their reporting on previously-funded projects, and a compliance monitoring process for reporting is in place (established through the joint First Nations/AANDC committee).

The new stand alone Stua'ate Lelum Secondary School project at Chemainus First Nation is currently under construction with a November 2011 projected completion date. This 3080 m2 facility will accommodate 114 students from Grade 7 to 12 and will replace the existing school which consisted of a converted restaurant and several portables.
The new school will include various green initiatives such as a geothermal heating system. With construction occurring last fall, currently half of the $9,223,247 (total project cost) has been expended including a contribution from the First Nation to enable additional space beyond what the Department's School Space Accommodation Standard permits.
This new facility will provide a positive impact on both the Chemainus First Nation community and surrounding communities by providing a safe and healthy environment which will enhance educational outcomes.
The current system is dated and is in need of replacement as it is constantly breaking down resulting in interruptions in water services. Over the last few years, there have been numerous emergency repairs required to the system resulting in unmanageable maintenance costs.
The new water distribution and road re-construction project for Kwadacha First Nation consists of the construction of approximately 3,625 meters of new water mains, 2,300 meters of new service pipe, three tie-ins to the remaining existing system, installation of 19 fire hydrants, drilling of a third water supply well and road restoration to applicable standards. The total project cost is $5,745,373 with the First Nation contributing $300,000 towards the project.
This project will benefit the entire community with a population of 272 living in 58 houses. This project will allow for fewer interruptions in services, a reduction in emergency repairs and a greater ability to manage maintenance costs, which all contribute to a healthy and vibrant community.
The Williams Lake Water Improvement Project carries a total project cost of $4,867,620. The existing water system was inadequate in both water quantity and water quality needed to meet the needs of approximately 300 people living on-reserve. The community currently has 88 houses, seven public buildings including an administration office, gym, education centre, church, lumber mill, fire hall and carpentry shop.
The project includes the tie-in of two recently drilled wells, the construction of a new water treatment plant, and a new reservoir supply main. The new treatment plant will include chlorination system for disinfection and filtration systems for manganese and arsenic removal. The new treatment plant will also be equipped with a Supervisory Control and Data Acquisition (SCADA) monitoring system which will allow remote monitoring and troubleshooting of any issue including water quality.
The community has been on a boil water advisory since 2006 and it is anticipated the new system will significantly improve the conditions of the drinking water and allow for continued population growth.
| Project Category | Previous Year (Planned Amount) |
Planned Spending | ||||
|---|---|---|---|---|---|---|
| Current Year 2011-2012 |
Year +1 2012-2013 |
Year +2 2013-2014 |
Year +3 2014-2015 |
Year +4 2015-2016 |
||
| Major Capital Projects | ||||||
| Community Infrastructure | 6,844,386 | 3,202,500 | 8,260,000 | 900,000 | 900,000 | 900,000 |
| Contaminated Sites | 11,672,500 | 90,000 | 90,000 | 90,000 | - | - |
| Education | 27,755,722 | 8,075,193 | 4,000,000 | 3,936,920 | - | - |
| Housing | 0 | - | - | - | - | - |
| Water and Sewer | 46,847,809 | 28,711,238 | 24,987,325 | 22,637,577 | 26,582,552 | 24,293,840 |
| Sub-Total (Major) | $93,120,417 | $40,078,931 | $37,337,325 | $27,564,497 | $27,482,552 | $25,193,840 |
| Minor Capital Projects | ||||||
| Community Infrastructure | 14,878,960 | 18,875,405 | 14,096,949 | 13,195,154 | 13,057,655 | 11,500,217 |
| Contaminated Sites | 8,327,500 | 440,000 | 140,000 | 140,000 | 150,000 | - |
| Education | 2,287,893 | 699,700 | 1,870,000 | 1,899,550 | 2,000,000 | 2,000,000 |
| Housing | 28,917,001 | 11,436,802 | 11,436,802 | 11,436,802 | 11,436,802 | 11,436,802 |
| Water and Sewer | 6,594,950 | 6,591,245 | 3,509,395 | 3,107,000 | 3,250,000 | 4,834,285 |
| Sub-Total (Minor) | $61,006,304 | $38,043,152 | $31,053,146 | $29,778,506 | $29,894,457 | $29,771,304 |
| Total Capital (Major & Minor) | ||||||
| Community Infrastructure | 21,723,346 | 22,077,905 | 22,356,949 | 14,095,154 | 13,957,655 | 12,400,217 |
| Contaminated Sites | 20,000,000 | 530,000 | 230,000 | 230,000 | 150,000 | - |
| Education | 30,043,615 | 8,774,893 | 5,870,000 | 5,836,470 | 2,000,000 | 2,000,000 |
| Housing | 28,917,001 | 11,436,802 | 11,436,802 | 11,436,802 | 11,436,802 | 11,436,802 |
| Water and Sewer | 53,442,759 | 35,302,483 | 28,496,720 | 25,744,577 | 29,832,552 | 29,128,125 |
| Total (Minor & Major) | $154,126,721 | $78,122,083 | $68,390,471 | $57,343,003 | $57,377,009 | $54,965,144 |
| Operations & Maintenance | ||||||
| Community Infrastructure | 25,293,333 | 31,275,467 | 31,275,467 | 31,275,467 | 31,275,467 | 31,275,467 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 9,785,231 | 10,077,554 | 10,077,554 | 10,077,554 | 10,077,554 | 10,077,554 |
| Housing | 0 | - | - | - | - | - |
| Water and Sewer | 22,596,983 | 21,513,401 | 14,253,401 | 14,253,401 | 14,253,401 | 14,253,401 |
| Sub-Total (O&M) | $57,675,547 | $62,866,422 | $55,606,422 | $55,606,422 | $55,606,422 | $55,606,422 |
| Grand Total | ||||||
| Community Infrastructure | 47,016,679 | 53,353,372 | 53,632,416 | 45,370,621 | 45,233,122 | 43,675,684 |
| Contaminated Sites | 20,000,000 | 530,000 | 230,000 | 230,000 | 150,000 | - |
| Education | 39,828,846 | 18,852,447 | 15,947,554 | 15,914,024 | 12,077,554 | 12,077,554 |
| Housing | 28,917,001 | 11,436,802 | 11,436,802 | 11,436,802 | 11,436,802 | 11,436,802 |
| Water and Sewer | 76,039,742 | 56,815,884 | 42,750,121 | 39,997,978 | 44,085,953 | 43,381,526 |
| Grand Total | $211,802,268 | $140,988,505 | $123,996,893 | $112,949,425 | $112,983,431 | $110,571,566 |
The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.
| Major Capital Projects | |
|---|---|
| Education Facilities | $0 |
| Water & Sewer | $425,000 |
| Contaminated Sites | $0 |
| Community Infrastructure | $0 |
| Minor Capital – formula driven (including housing) | $2,787,080 |
| Minor Capital - projects < $1.5 million | $3,288,180 |
| Infrastructure O&M | $2,373,748 |
| Total (FNIIP) - Vote 10 | $8,874,008 |
Breakdown of Planned Spending for Vote 10 in 2011-2012

Text description of this chart is available on a separate page.
| First Nation Infrastructure Capital Projects funded this fiscal year (major and minor projects only) | 26 Projects | $3,713,180 |
| First Nation Infrastructure Capital Projects funded in the five year plan (major and minor projects only) | 36 Projects | $6,876,680 |
| Infrastructure Investment per Capita (On-Reserve Registered Indian Population as of Dec. 31, 2010) |
3,959 People | $2,242 |
Allocation Methodology for the Indian Act First Nations "A-Base" is based on a 1993 decision, agreed upon by Yukon First Nation Leadership and AANDC. The guiding principle for the methodology is fair, equitable and non-political, consistent from year to year, thereby increasing stability in funding. This methodology provides a base which Yukon First Nations can use to encourage long-term planning. The allocation is designed to account for community differences, specifically for remoteness and population.
Yukon Region uses the five year capital plans provided by the First Nations to prioritize projects using the National Priority Ranking System, Level of Service Standards, National and Regional Practices as well as the Asset Condition Reporting System Assessments to help in identify projects for "targeted funding". Yukon Region encourages the First Nations to do some Asset Condition Reporting System projects based on the assessment on a yearly basis. Also, housing, road, water, wastewater and subdivision projects are identified in the First Nation's five year plans to assist in the maintenance of the community assets and overall community development. Yukon Region uses both multi-year type allocation and single year agreement with Terms and Conditions depending on the type of project being funded.

In 2002, White River First Nation was deemed a "high risk' community due to the fact that the community water systems at that time did not have any means of disinfection. In addition to the disinfection, several existing wells were not properly constructed putting the community at further risk. The White River First Nation Water Project has proceeded in addressing these concerns since 2004.
Two new community systems (System 1 and System 2) were designed in 2006 and constructed in 2007-2008 to replace three existing community systems that were in disrepair.
Only houses previously connected to a "community system" or with poor water quality were connected to the distribution system when it was constructed. This new phase of the project will connect the remaining 8 houses, and make some design changes to the two treatment plant systems to help temper water correctly and provide on-line chlorine analysers. This will complete the vision of providing clean safe drinking water to all people in the community and begin to focus their resources on other projects to improve their community. The anticipated cost of this project is $600,000.

Maintenance management planning and process implementation is important in promoting vibrant and healthy first nation communities. Implementing strategic maintenance processes will enhance the First Nations ability for early detection of potential issues, and will allow for adequate time to repair or replace components of a system or community building with minimal impact to the community.
The objective of this project is to develop improved maintenance management process for four of Yukon Region's Indian Act communities and will cost approximately $332,000.
| Project Category | Previous Year (Planned Amount) |
Planned Spending | ||||
|---|---|---|---|---|---|---|
| Current Year 2011-2012 |
Year +1 2012-2013 |
Year +2 2013-2014 |
Year +3 2014-2015 |
Year +4 2015-2016 |
||
| Major Capital Projects | ||||||
| Community Infrastructure | 0 | - | - | - | - | - |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 0 | - | - | - | - | - |
| Housing | 405,000 | - | - | - | - | - |
| Water and Sewer | 1,664,000 | 425,000 | - | - | - | - |
| Sub-Total (Major) | $2,069,000 | $425,000 | - | - | - | - |
| Minor Capital Projects | ||||||
| Community Infrastructure | 2,142,000 | 757,194 | 878,000 | 964,749 | 983,000 | 1,437,779 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 30,000 | 25,500 | - | - | - | - |
| Housing | 1,609,000 | 1,940,886 | 2,026,994 | 1,868,258 | 1,978,007 | 1,513,258 |
| Water and Sewer | 510,000 | 3,351,680 | 3,079,000 | 825,000 | 20,000 | 20,000 |
| Sub-Total (Minor) | $4,291,000 | $6,075,260 | $5,983,994 | $3,658,007 | $2,981,007 | $2,971,037 |
| Total Capital (Major & Minor) | ||||||
| Community Infrastructure | 2,142,000 | 757,194 | 878,000 | 964,749 | 983,000 | 1,437,779 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 30,000 | 25,000 | - | - | - | - |
| Housing | 2,014,000 | 1,940,886 | 2,026,994 | 1,868,258 | 1,978,007 | 1,513,258 |
| Water and Sewer | 2,174,000 | 3,776,680 | 3,079,000 | 825,000 | 20,000 | 20,000 |
| Total (Minor & Major) | $6,360,000 | $6,500,260 | $5,983,994 | $3,658,007 | $2,981,007 | $2,971,037 |
| Operations & Maintenance | ||||||
| Community Infrastructure | 1,217,000 | 899,910 | 917,908 | 936,266 | 954,992 | 954,992 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 0 | - | - | - | - | - |
| Housing | 0 | - | - | - | - | - |
| Water and Sewer | 2,110,000 | 1,473,838 | 1,034,115 | 1,054,797 | 1,075,893 | 1,075,893 |
| Sub-Total (O&M) | $3,327,000 | $2,373,748 | $1,952,023 | $1,991,063 | $2,030,885 | $2,030,885 |
| Grand Total | ||||||
| Community Infrastructure | 3,359,000 | 1,657,104 | 1,795,908 | 1,901,015 | 1,937,992 | 2,392,771 |
| Contaminated Sites | 0 | - | - | - | - | - |
| Education | 30,000 | 25,500 | - | - | - | - |
| Housing | 2,014,000 | 1,940,886 | 2,026,994 | 1,868,258 | 1,978,007 | 1,513,258 |
| Water and Sewer | 4,284,000 | 5,250,518 | 4,113,115 | 1,879,797 | 1,095,893 | 1,095,893 |
| Grand Total | $9,687,000 | $8,874,008 | $7,936,017 | $5,649,070 | $5,011,892 | $5,001,922 |
The dashes in the above Regional Summary Table indicate that planned funding in this category has yet to be determined. Funding levels may only be known just prior to the commencement of the fiscal year in question.
The Department has a consistent and transparent ranking system to address the most pressing needs in First Nation communities.
The department is committed to the following priorities, listed in order of importance, over the next five years:
AANDC regional offices employ a ranking system as a normal course of business in developing capital plans, as demand historically exceeds available funding resources. The National Priority Framework was designed to align existing regional processes (at the highest level) with departmental priorities, to enable reporting and demonstrate progress in a consistent manner.
Regions are requested to:
In this way the Department rolls-up funding allocations to the national priorities by asset category. The objective is to demonstrate allocation to the highest priorities as regions see fit, however, pending direction from the allocation methodologies study it may be necessary to set funding levels or targets for the priority areas. The Department may also wish to roll-up unfunded projects in each priority area as a way to demonstrate where the needs reside and how they may shift over time.
Figure 1: National Priority1 Funding Evaluation and Measurement Matrix

Text description of this chart is available on a separate page.
Notes:
North/South Custodial Assets (A):
Maintenance projects required to protect the asset and would mitigate the identified high-risk health and safety issues.
Water/Sewer (B), Education (C), Community Infrastructure (D):
Assets require upgrading or replacement to meet appropriate standards. Maintenance projects to address significant risk to health and safety: 1) classified as Group 2 Projects resulting from Asset Condition Reporting System inspections; and/or 2) to address high and medium risks as identified in the AANDC May 2003 National Assessment of Water and Wastewater Systems in First Nations Communities. These projects are to be recorded and tracked for completion in the departmental Capital Asset Management System.
North/South Custodial Assets (A), Water/Sewer (B), Education (C), Community Infrastructure (D):
Upgrades of existing assets, new construction / acquisition projects to mitigate an identified significant risk to health and safety.
North/South Custodial Assets (A), Water/Sewer (B), Education (C), Community Infrastructure (D):
Projects required to extend the useful operating life of a facility or asset, or to maintain the original service level of the asset.
North/South Custodial Assets (A), Water/Sewer (B), Education (C), Community Infrastructure (D):
Anticipated community growth requires new construction / expansion / procurement of assets to maintain the level of service standards within a timeframe of less than two years.
North/South Custodial Assets (A) Water/Sewer (B), Education (C), Community Infrastructure (D):
Anticipated community growth requires new construction / expansion / procurement of assets to maintain the level of service standards within a timeframe of greater than two years.
Note: Remediation/risk management includes monitoring
National Contaminated Sites Classification System (NCSCS) Class 1
Assessment, remediation/risk management of all NCSCS Class 1 contaminated sites on a priority basis to avert risk to community health and safety and water sources in accordance with the departmental Contaminated Sites Management policy.
NCSCS Class 2
Assessment, remediation/risk management of all NCSCS Class 2 contaminated sites on a priority basis to avert risk to community health and safety in accordance with the departmental Contaminated Sites Management
policy.
NCSCS Class 3
Assessment, remediation/risk management of all NCSCS Class 3 contaminated sites on a cost efficiency basis.
Renovation
Projects required to correct what could be an unsafe condition to the occupants or projects beyond routine maintenance to extend the useful lifespan of the house
New Construction
Construction of dwelling units to address the community's housing need.
Operation and Maintenance:
Routine maintenance and activities to preserve the housing portfolio.
Custodial Assets: Administration buildings, vehicles, machinery and equipment required to deliver programs to First Nations, Inuit, and Northern communities.
Water / Sewer: Assets that comprise the distribution / collection system and assets required in the treatment and disposal process including major equipment, vehicles, machinery and buildings.
Education Facilities: Schools, staff residences (teacherages), student residences, temporary facilities associated with delivering the educational program in the community.
Community Infrastructure: Assets and systems not already specified above - including operative, administrative, utility and recreational buildings; solid waste vehicles, dumps and transfer stations; community roads and bridges; electrical power supply and distribution; fire-fighting vehicles and supporting buildings; and fuel tanks and distribution systems.
Contaminated Sites: Sites requiring assessment, remediation / risk management to protect the health and safety as well as the environment of communities.
Housing: Funding to assist in community housing services i.e., the construction, maintenance and management of the community housing portfolio.
Note: The following is not an exhaustive list of project activities, but are examples provided to assist in categorizing potential projects.
Fuel Tank Systems
Fire safety systems
Solid waste
Electrification
Transportation
Fire Safety Systems
Solid waste
Electrification
Transportation
Fire safety systems
Solid waste
Electrification
Transportation
Admin Buildings
Fire safety systems
Solid waste
Electrification
Transportation
National Contaminated Sites Classification System Class 1
National Contaminated Sites Classification System Class 2
National Contaminated Sites Classification System Class 3
Renovation
Repairing unsafe conditions could include:
Extending the useful lifespan of the house could include:
New Construction
Operation & Maintenance
New Construction to address population growth in less than 2 years
New Construction to address population growth after 2 years