Author: (Pipeline Readiness Office)
Date: (May 2007)
PDF Version (970 Kb, 2 pages)
Help on accessing documents in PDF format
can be obtained on the help page.
The public review processes for the proposed MGP began in the fall of 2004. After a technical review phase that lasted through much of 2005, the Joint Review Panel and the National Energy Board started their public hearings in early 2006.
Public hearings have been held in communities across the Northwest Territories, Alberta and in Whitehorse, Yukon.
The JRP is a seven-member, independant body that is evaluating the possible impacts of the project on the environment and the lives of the people in the proposed project area.
The JRP was established by three parties to the Joint Review Panel Agreement: the Mackenzie Valley Environmental Impact Review Board (MVEIRB), the Inuvialuit Game Council (IGC), and the federal Minister of the Environment.
The JRP public hearings are expected to conclude in mid-2007. Following the conclusion of the public hearings, the panel will prepare a report and recommendations.
The NEB is an independant federal regulatory board that regulates certain aspects of the energy industry, including the construction and operation of pipelines. A three-member NEB panel is reviewing applications for three gas field development plans, a natural gas gathering system, a natural gas liquids pipeline to Norman Wells and a natural gas pipeline from Inuvik to northern Alberta.
The initial NEB hearings concluded in December 2006.
After the JRP report has been submitted and responded to by the Government of Canada, the NEB will reconvene its hearing for final argument. Dates for reconvening have yet to be set.
There are several steps following the JRP and NEB hearings before a decision on the proposed project can be made.
After the issuance of the JRP's report, Responsible Ministers under the MVRMA will do one of the following:
Responsible Authorities under CEAA will take into consideration the JRP's report and with approval of the Governor in Council (Federal Cabinet), respond to the report.
After the JRP report has been submitted, and responded to by the federal government (as noted above), the NEB will reconvene its hearing for final argument.
As a designated Regulatory Agency under the MVRMA the NEB has similar responsibilities as responsible ministers (section 137. MVRMA)
After its final argument, the NEB will adjourn its hearing and prepare its decision about the proposed project. The decision is written and published as "Reason for Decision". The decision is a public document.
The NEB decision is submitted to the federal cabinet, which will either reject or accept the decision.
If the MGP is not approved at this step, the process stops.
If the MGP is approved at this step, the regulatory processes continue.
In addition to undergoing the environmental assessment through the JRP and the initial NEB regulatory review, the proposed MGP proponents submit applications for authorizations, such as water licences and land use permits.
There are several regulatory agencies in the North that, under law, assess these applications and if they are approved, issue the permits, leases, licences or other forms of autorizations. Some of the regulatory agencies are required to hold public hearings.
Each regulatory agency determines how and when it will undertake application reviews. To coordinate activities and avoid duplication, regulatory agencies signed the Agreement for Coordination of the Regulatory Review of the Mackenzie Gas Project in April 2004.
June 2002: Cooperation Plan is released
June 2003: Proponent files Preliminary Information Package
April 2004: Regulators' Agreement is signed
August 2004: Joint Review Panel Agreement and Terms of Reference for Environmental Impact Review are released
October 2004: Joint Review Panel Agreement and Terms of Reference for Environmental Impact Review are released
Throughtout 2005: JRP and NEB conduct technical reviews of the EIS and applications
January 2006: NEB public hearings begin; reviewing need for the project, engineering design of facilities and pipeline, economic feasibility, tolls and tariffs
February 2006: JRP public hearings begin; reviewing socio-economic, cultural and environmental matters associated wth the Project
November 2006: Bill C-13 of the Budget implementation Act comes into force, establishing the Corporation to administer the $500 million, Mackenzie Gas Project Impact Fund to offset socio-economic impacts associated with the proposed MGP
December 2006: NEB concludes initial hearings and waits for issuance of the JRP report
Late 2007: JRP hearings expected to conclude
Early 2008: JRP expected to release its report
Mid 2008: Responses to the JRP recommendations
TBD*: NEB reconvenes public hearings for final argument
TBD*: NEB releases its Reasons for Decision

The Mackenzie Gas Project (MGP) is a group of companies that have applied for the right to construct and operate a natural gas pipline and associated facilities to transport natural gas from the Mackenzie Delta in the Northwest Territories to connect with a pipeline system in northern Alberta.
The companies have discovered natural gas in the anchor fields in the Inuvialuit region of the NWT. If the project is approved, there will be two pipelines; the shorter one from Inuvik to Norman Wells will transport natural gas liquids, and the other will carry natural gas (which is in a gaseous form, not liquide) to markets in southern Canada and the United States.
Before the proposed project can be approved it must be assessed for possible environmental and social impacts, and was to reduce those impacts through regulatory requirements. Issues such as routing, safety, tolls and tariffs are also being examined.
The Cooperation Plan, signed in June 2002, is a framework developed to quide the implementation of coordinated environmental impact and regulatory review processes for the proposed project.
It is a "made-in-the-north" approach that helps navigate through, and to ensure consistancy with, a variety of land claim or self-government related agreements and processes.
As described in the Cooperation Plan, agreements among environmental and regulatory agencies were signed, including the Joint Review Panel Agreement and the Agreement for Coordination of the Regulatory Review of the Mackenzie Gas Project, in 2004.
Northern Gas Project Secretariat:
5114 - 49th Street
Yellowknife, NT X1A 1P8
Ph: (867) 766-8600
Toll-free: 1-866-372-8600
www.ngps.nt.ca
Suite 302, Professional Building
125 Mackenzie Rd
PO Box 2412
Inuvik, NT XOE OTO
Indian & Northern Affairs Canada
Pipeline Readiness Office
4914 - 50th Street
PO Box 1500
Yellowknife, NT X1A 2R3
Ph: (867) 669-2855