Figure 4.2 - Breakdown of the Estimated Construction Costs to Meet INAC’s Protocol: Wastewater ($ - M)
This pie chart provides a breakdown of the estimated construction costs (in millions of dollars) for wastewater systems in First Nations communities in Saskatchewan to meet INAC’s Protocol.
The chart is divided into eight categories:
- Building;
- Collection System;
- Engineering & Contingencies;
- Equipment;
- Monitoring Equipment;
- Pumping Stations;
- Standby Power; and
- Treatment.
- The estimated building cost for wastewater systems to meet INAC’s Protocol is 0.1 million dollars.
- The estimated collection system cost for wastewater systems to meet INAC’s Protocol is 13.7 million dollars.
- The estimated engineering and contingencies cost for wastewater systems to meet INAC’s Protocol is 10.5 million dollars.
- The estimated equipment cost for wastewater systems to meet INAC’s Protocol is 0.1 million dollars.
- The estimated monitoring equipment cost for wastewater systems to meet INAC’s Protocol is 0.3 million dollars.
- The estimated cost pumping stations for wastewater systems to meet INAC’s Protocol is 0.5 million dollars.
- The estimated standby power cost for wastewater systems to meet INAC’s Protocol is 5.7 million dollars.
- The estimated treatment cost for wastewater systems to meet INAC’s Protocol is 21.5 million dollars.
Return to source image